LPA:136.11 Local Public Agency Construction: Difference between revisions

From Engineering_Policy_Guide
Jump to navigation Jump to search
Smithk (talk | contribs)
m →‎136.11.17.1 Material Acceptance: Per LPA, Small Material Quantity Acceptance Table removed. Current info available at EPG Off-Systems Guide Schedule for Federal-Aid Acceptance Sampling & Testing
 
(94 intermediate revisions by 5 users not shown)
Line 1: Line 1:
This article is intended as a guide to Local Public Agencys (LPAs) to ensure federal-aid project requirements are met while administering the construction of and corresponding documentation required of a typical LPA project.  No work is to be initiated on any part of the project until federal funding has been approved (obligated) by [http://www.fhwa.dot.gov/ FHWA] and the local agency has been notified by MoDOT to proceed.  
This article is intended as a guide to Local Public Agencys (LPAs) to ensure federal-aid project requirements are met while administering the construction of and corresponding documentation required of a typical LPA project.  No work is to be initiated on any part of the project until federal funding has been approved (obligated) by [http://www.fhwa.dot.gov/ FHWA] and the local agency has been notified by MoDOT to proceed.  
{|style="padding: 0.3em; margin-left:7px; border:2px solid #a9a9a9; text-align:left; font-size: 95%; background:#f5f5f5" width="360px" align="right"  
{|style="padding: 0.3em; margin-left:7px; border:2px solid #a9a9a9; text-align:left; font-size: 95%; background:#f5f5f5" width="400px" align="right"  
|-
|-
|<center>'''Figures'''</center>
|<center>'''Figures'''</center>
|-
|[[LPA:136.12 Figures, Glossary and Other Useful Links#Construction Reimbursement Form|Fig. 136.3.18, Construction Reimbursement Form]]
|-
|-
|[[media:136.11.1 Nov 2013.doc|Fig. 136.11.1, General Guidelines for LPA Preconstruction Conference]]
|[[media:136.11.1 Nov 2013.doc|Fig. 136.11.1, General Guidelines for LPA Preconstruction Conference]]
|-
|-
|[[media:136.11.2.doc|Fig. 136.11.2, Change Order Form]]
|[[media:136.11.2.xlsx|Fig. 136.11.2, Change Order Form]]
|-
|-
|[[media:136.11.3.doc|Fig. 136.11.3, Progress Report]]
|[[media:136.11.3 2016.pdf|Fig. 136.11.3, Progress Report]]
|-
|-
|[[media:136.11.4.doc|Fig. 136.11.4, Request for Approval of Subcontract]]
|[https://epg.modot.org/forms/general_files/DE/RW-LPA/Request_to_Subcontract_C_220.pdf Fig. 136.11.4, Request for Approval of Subcontract]
|-
|-
|[[media:136.11.5 2015.xls|Fig. 136.11.5, DBE Subcontract Worksheet]]
|[[media:136.11.5 Dec 2015.xls|Fig. 136.11.5, DBE Subcontract Worksheet]]
|-
|-
|[[media:136.11.6 2015.doc|Fig. 136.11.6, Contractor’s Instructions for Filling out Request to Subcontract Work]]
|[[media:136.11.6 Dec 2015.pdf|Fig. 136.11.6, Subcontractor Certification Regarding Affirmative Action]]
|-
|-
|[[media:136.11.7.doc|Fig. 136.11.7, Wage Rate Interview (Labor Compliance/EEO)]]
|[https://epg.modot.org/forms/CM/CR1_Wage_Rate_Interview.pdf Fig. 136.11.7, Wage Rate Interview (Labor Compliance/EEO)]
|-
|-
|[[media:136.11.8.doc|Fig. 136.11.8, Form FHWA-1391]]
|[[media:136.11.8.doc|Fig. 136.11.8, Form FHWA-1391]]
|-
|-
|[[media:136.11.9.doc|Fig. 136.11.9, Contractor DBE Certification]]
|[[media:136.11.9 2016.docx|Fig. 136.11.9, Contractor DBE Certification]]
|-
|-
|[[media:136.11.10.doc|Fig. 136.11.10, Contractor’s Affidavit Regarding Settlement of Claims]]
|[[media:136.11.10.doc|Fig. 136.11.10, Contractor’s Affidavit Regarding Settlement of Claims]]
Line 28: Line 30:
|[[media:136.11.12.doc|Fig. 136.11.12, Site Visit Checklist]]
|[[media:136.11.12.doc|Fig. 136.11.12, Site Visit Checklist]]
|-
|-
|[[media:110.2 checklist Sept 2013.pdf|Fig. 136.11.13, Job Bulletin Board Checklist]]
|[https://epg.modot.org/forms/CM/Job_Site_Bulletin_Board_Checklist_fillable.pdf Fig. 136.11.13, Job Bulletin Board Checklist]
|-
|-
|[[media:Fig. 136.11.14.pdf|Fig. 136.11.14, Construction Invoice Example 1]]
|[[media:Fig. 136.11.14 secure.pdf|Fig. 136.11.14, Construction Invoice Example 1]]
|-
|-
|[[media:Fig. 136.11.15.pdf|Fig. 136.11.15, Construction Invoice Example 2]]
|[[media:Fig. 136.11.15.pdf|Fig. 136.11.15, Construction Invoice Example 2]]
|-
|-
|[[media:Fig. 136.11.16.docx|Fig. 136.11.16, Approved Contract Administration Software]]
|[[media:136.11.18.docx|Fig. 136.11.18, LPA Final Inspection Letter]]
|-
|[[media:136.11.19.docx|Fig. 136.11.19, LPA Final List of Acceptance Testers]]
|-
|[[media:136.11.20.docx|Fig. 136.11.20, LPA DBE Certification Letter]]
|-
|[[media:136.11.21.docx|Fig. 136.11.21, LPA Vendor Lien Waiver]]
|-
|[[media:136.11.22.docx|Fig. 136.11.22, LPA Final Acceptance Checklist]]
|-
|[[media:136.11.23 2016.pdf|Fig. 136.11.23, LPA Semi-Final Inspection Checklist (Form C-236 LPA)]]
|-
|[[media:Form C-239 2016.pdf|Fig. 136.11.24, LPA Final Acceptance Report (Form C-239 LPA)]]
|-
|[https://epg.modot.org/forms/CM/CUF_Determination_Form_Contracts_Let_After_03_2021.pdf Commercially Useful Function (CUF) Determination Form]
|-
|-
| [[Off-Systems Guide Schedule for Federal-Aid Acceptance Sampling and Testing (FAST)|Off-Systems Guide Schedule for Federal-Aid Acceptance Sampling & Testing (FAST)]]
| [[Off-Systems Guide Schedule for Federal-Aid Acceptance Sampling and Testing (FAST)|Off-Systems Guide Schedule for Federal-Aid Acceptance Sampling & Testing (FAST)]]
Line 53: Line 69:
|-
|-
|[http://www.fhwa.dot.gov/federal-aidessentials/catmod.cfm?category=civilrig Civil Rights]
|[http://www.fhwa.dot.gov/federal-aidessentials/catmod.cfm?category=civilrig Civil Rights]
|-
|<center>'''Brochure'''</center>
|-
|[[media:136.11 Buy America Brochure.pdf|Buy America Requirements for the Federal-Aid Construction Program]]
|}
|}
==136.11.1 Project Oversight==
==136.11.1 Project Oversight==
Line 58: Line 78:
The LPA shall have a '''person in "responsible charge"''' (RC) of the administration of the project including construction inspection.  This person must be an employee or a paid elected official of the local agency who is accountable for the project.  If a consultant is hired to oversee the project the RC should be available at all times to respond to any issues on the project.  The RC or designated consultant should have the necessary experience, training and knowledge to ensure that project construction and administration follows all requirements as described in the project documents and standard practice.  The RC will be the primary contact for MoDOT regarding any contract administration issues.
The LPA shall have a '''person in "responsible charge"''' (RC) of the administration of the project including construction inspection.  This person must be an employee or a paid elected official of the local agency who is accountable for the project.  If a consultant is hired to oversee the project the RC should be available at all times to respond to any issues on the project.  The RC or designated consultant should have the necessary experience, training and knowledge to ensure that project construction and administration follows all requirements as described in the project documents and standard practice.  The RC will be the primary contact for MoDOT regarding any contract administration issues.


All items of work on the project shall be inspected.  Major items of work such as bridge deck pouring, paving or other high cost or critical items may require more attention than other minor items of work.  MoDOT’s Engineering Policy Guide or [http://www.modot.org/business/manuals/LPAContacts.htm MoDOT district representatives] are good sources for tools to adequately administer the project.
All items of work on the project shall be inspected.  Major items of work such as bridge deck pouring, paving or other high cost or critical items may require more attention than other minor items of work.  MoDOT’s Engineering Policy Guide or [https://www.modot.org/about-lpacontact-us MoDOT district representatives] are good sources for tools to adequately administer the project.


==136.11.2 Work by LPA Forces==
==136.11.2 Work by LPA Forces==
Line 76: Line 96:
A preconstruction conference shall be conducted by the LPA, prior to the start of work, to ensure that all parties involved are aware of their responsibilities. Those invited to attend shall include but not be limited to representatives from the consultant (if applicable), contractor, subcontractors, utilities (if involved), local police, fire, postal, other emergency services (if necessary),  any school agencies (if traffic is to be severely restricted or road closed), and MoDOT. Arrangements for and notice given of the meeting shall be completed at least one week prior to the meeting date. [[media:136.11.1 Nov 2013.doc|Fig. 136.11.1 General Guidelines for LPA Preconstruction Conference]] outlines this conference.  Note that the initial data pertaining to the project is required within two working days after the start of work.
A preconstruction conference shall be conducted by the LPA, prior to the start of work, to ensure that all parties involved are aware of their responsibilities. Those invited to attend shall include but not be limited to representatives from the consultant (if applicable), contractor, subcontractors, utilities (if involved), local police, fire, postal, other emergency services (if necessary),  any school agencies (if traffic is to be severely restricted or road closed), and MoDOT. Arrangements for and notice given of the meeting shall be completed at least one week prior to the meeting date. [[media:136.11.1 Nov 2013.doc|Fig. 136.11.1 General Guidelines for LPA Preconstruction Conference]] outlines this conference.  Note that the initial data pertaining to the project is required within two working days after the start of work.


For projects that have specified contractor furnished borrow or require disposal of waste material off the LPA right of way, the contractor should be reminded of the requirement that the affected areas must be reviewed by DNR for environmental clearances that will include, but not be limited to the Clean Water Act, the Endangered Species Act, the National Historic Preservation Act, the Farmland Protection Act, Resource Conservation and Recovery Act, Comprehensive Environmental Response, Compensation, and Liability Act and RSMo Chapter 194, Section 194.400 Unmarked Human Burial Sites.  A copy of the correspondence from these agencies should be filed with the [http://www.modot.org/business/manuals/LPAContacts.htm MoDOT district representative]. More information on contractor furnished borrow and waste sites can be found in [[136.6 Environmental and Cultural Requirements|EPG 136.6 Environmental and Cultural Requirements]].  Failure to comply with this requirement can cause loss of federal funding.
For projects that have specified contractor furnished borrow or require disposal of waste material off the LPA right of way, the contractor should be reminded of the requirement that the affected areas must be reviewed by DNR for environmental clearances that will include, but not be limited to the Clean Water Act, the Endangered Species Act, the National Historic Preservation Act, the Farmland Protection Act, Resource Conservation and Recovery Act, Comprehensive Environmental Response, Compensation, and Liability Act and RSMo Chapter 194, Section 194.400 Unmarked Human Burial Sites.  A copy of the correspondence from these agencies should be filed with the [https://www.modot.org/about-lpacontact-us MoDOT district representative]. More information on contractor furnished borrow and waste sites can be found in [[136.6 Environmental and Cultural Requirements|EPG 136.6 Environmental and Cultural Requirements]].  Failure to comply with this requirement can cause loss of federal funding.


If ADA improvements are included within the project, then the [[media:136.9.4 2015.doc|ADA Checklist]] should be included in the discussion.   
If ADA improvements are included within the project, then the [https://epg.modot.org/forms/CM/ADA_Checklist.pdf ADA Checklist, (PDF version of Fig. 136.9.4)] (or the [https://epg.modot.org/forms/CM/ADA_Checklist.docx MS Word version of the ADA Checklist, Fig. 136.9.4]) should be included in the discussion.   


'''Initial Data from LPA'''
'''Initial Data from LPA'''
Line 87: Line 107:
:'''2.''' Contractor’s name and address;  
:'''2.''' Contractor’s name and address;  
:'''3.''' Construction Inspector’s name, address, and phone number;  
:'''3.''' Construction Inspector’s name, address, and phone number;  
:'''4.''' Name of full-time employee of agency to be in "responsible charge" of project, including projects with consultant services ([http://cfr.vlex.com/vid/635-105-supervising-agency-19725301 23 CFR 635.105]). "Responsible charge" means:  
:'''4.''' Name of full-time employee of agency to be in "responsible charge" of project, including projects with consultant services ([https://www.law.cornell.edu/cfr/text/23/635.105 23 CFR 635.105]). "Responsible charge" means:  


::a. Aware of day-to-day operations on the project  
::a. Aware of day-to-day operations on the project  
Line 104: Line 124:
:'''13.''' Date of preconstruction conference;  
:'''13.''' Date of preconstruction conference;  
:'''14.''' Date on which work actually started; and  
:'''14.''' Date on which work actually started; and  
:'''15.''' Summary of Disadvantaged Business Enterprise (DBE) intent.  
:'''15.''' Summary of Disadvantaged Business Enterprise (DBE) intent.


==136.11.5 Subcontracts ==
==136.11.5 Subcontracts ==


Federal-aid contracts require that no less than 30% of the contract work shall be performed by the prime contractor’s own forces and equipment. All contracts shall further hold to the right of approval of any subcontract prior to performance of subcontract work. The form of approval shall be such as to assure the local agency that the proposed subcontractor is both qualified to perform the proposed items of work and legally bound to comply with all the requirements of the contract as they would apply to the prime contractor, for example, wage rates, equal employment opportunity regulations, submittal of payrolls, etc. No subcontractor may further subcontract any of his work.  
Federal-aid contracts require that no less than 30% of the contract work shall be performed by the prime contractor’s own forces and equipment. All contracts shall further hold to the right of approval of any subcontracts prior to performance of subcontract work. The local agency is responsible for assuring the proposed subcontractors are both qualified to perform the proposed items of work and legally bound to comply with all the requirements of the contract as they would apply to the prime contractor, for example, wage rates, equal employment opportunity regulations, submittal of payrolls, etc.
 
The LPA shall furnish the MoDOT representative the name and address of each subcontractor, the percentage of work sublet to that particular subcontractor, the percentages awarded to DBEs, and the total percentage of work sublet to date. DBEs must be on the MoDOT-approved listing at the time of letting. Subcontract approval forms ([https://epg.modot.org/forms/general_files/DE/RW-LPA/Request_to_Subcontract_C_220.pdf Fig. 136.11.4], [[media:136.11.5 Dec 2015.xls|Fig. 136.11.5]] and [[media:136.11.6 Dec 2015.pdf|Fig. 136.11.6]]) must be used for submitting subcontractor information. [http://www.fhwa.dot.gov/programadmin/contracts/1273/1273.pdf FHWA 1273, Required Federal Contract Provisions], is included in all federal aid contracts, and it is the prime contractor’s responsibility to ensure that all subcontract agreements also include a copy of FHWA 1273. The reviewer should perform a random check on the submitted subcontract agreements to help ensure the prime is meeting this requirement.


The Subcontracts will be submitted to MoDOT for approval. The LPA shall furnish the MoDOT representative the name and address of each subcontractor, the percentage of work sublet to that particular subcontractor, the percentages awarded to DBEs, and the total percentage of work sublet to date. DBEs must be on the MoDOT-approved listing at the time of letting. In figuring the percentage of the contract work performed, all prices for sublet work shall be at contract unit bid prices. Sample forms ([[media:136.11.4.doc|Fig. 136.11.4]] and [[media:136.11.5 2015.xls|Fig. 136.11.5]]) may be used for submitting subcontractor information and instructions for completing the forms are available ([[media:136.11.6 2015.doc|Fig. 136.11.6]]).
Upon approval from the prime contractor, subcontractors may sublet a portion of their assigned work to another subcontractor. This relationship is called “2nd tier subcontracting”. A separate [https://epg.modot.org/forms/general_files/DE/RW-LPA/Request_to_Subcontract_C_220.pdf Fig.136.11.4], Request for Approval of Subcontract, submitted by the prime, is required for 2nd tier subcontract requests. The contractor shall disclose the name of the 1st tier subcontractor on the form.
 
The Request for Approval of Subcontract for the 1st tier subcontractor should list all of the work items they plan to perform, as well as all work they plan to sublet to their second tier subcontractors. The quantity and unit price for each line shall be that designated in the subcontract agreement between the prime contractor and the first tier subcontractor. The Request for Approval of Subcontract for the 2nd tier subcontract work lists only the work the 2nd tier sub will perform, and shows the quantity and price from the subcontract agreement between the 1st and 2nd tier subcontractors.


==136.11.6 Information Posters==
==136.11.6 Information Posters==


The contracts for highway construction projects require certain information to be conspicuously displayed on the project where employees regularly congregate in preparation for the day’s work.  The RC or a delegated representative is to conduct inspections of the bulletin boards. The first inspection should occur when employees begin work on the project.  After the initial review, inspections should be conducted every other month until the project is completed to ensure the bulletin board is in good condition and still displays the required posters. The list of required information to be posted both on the project and in the project office is located in [http://epg.modot.org/index.php?title=Category:110_State_and_Federal_Wage_Rates_and_Other_Requirements#110.2_Federal-Aid_Projects_.28Guidance_for_Sec_110.2.29 EPG 110.2].  Many of the posters can be downloaded from MoDOT’s internet contractor resources website.  A [http://www.modot.mo.gov/business/lpa/checklist.htm checklist of the job bulletin board posters] is also available.  All posters shall be completed as required, showing names and telephone numbers where indicated.  For more information on the Federal Davis-Bacon prevailing wage rates see [[136.9 Plans, Specs and Estimates (PS & E)#136.9.4.1.1.10.1 Federal Wage Rates (23 USC 113 and 29 CFR 5)|EPG 136.9.4.1.1.10.1 Federal Wage Rates]].
The contracts for highway construction projects require certain information to be conspicuously displayed on the project where employees regularly congregate in preparation for the day’s work.  The RC or a delegated representative is to conduct inspections of the bulletin boards. The first inspection should occur when employees begin work on the project.  After the initial review, inspections should be conducted every other month until the project is completed to ensure the bulletin board is in good condition and still displays the required posters. The list of required information to be posted both on the project and in the project office is located in [https://epg.modot.org/index.php?title=Category:110_State_and_Federal_Wage_Rates_and_Other_Requirements#110.2_Federal-Aid_Projects_.28Guidance_for_Sec_110.2.29 EPG 110.2].  Many of the posters can be downloaded from MoDOT’s internet contractor resources website.  A [https://epg.modot.org/forms/CM/Job_Site_Bulletin_Board_Checklist_fillable.pdf checklist of the job bulletin board posters] is also available.  All posters shall be completed as required, showing names and telephone numbers where indicated.  For more information on the Federal Davis-Bacon prevailing wage rates see [[136.9 Plans, Specs and Estimates (PS & E)#136.9.4.1.1.10.1 Federal Wage Rates (23 USC 113 and 29 CFR 5)|EPG 136.9.4.1.1.10.1 Federal Wage Rates]].
 
==136.11.7 Equal Employment Opportunity Requirements==
==136.11.7 Equal Employment Opportunity Requirements==


The [http://ecfr.gpoaccess.gov/cgi/t/text/text-idx?c=ecfr&sid=3275bea9e2d87163209535159a10234d&rgn=div5&view=text&node=41:1.2.3.1.1&idno=41 EEO requirements (41 CFR 60.1)] and [http://ecfr.gpoaccess.gov/cgi/t/text/text-idx?c=ecfr&sid=3275bea9e2d87163209535159a10234d&rgn=div5&view=text&node=41:1.2.3.1.2&idno=41 (41 CFR 60.2)] are contained in the contract. The local agency should be familiar with and enforce those requirements.  
The [http://ecfr.gpoaccess.gov/cgi/t/text/text-idx?c=ecfr&sid=3275bea9e2d87163209535159a10234d&rgn=div5&view=text&node=41:1.2.3.1.1&idno=41 EEO requirements (41 CFR 60.1)] and [http://ecfr.gpoaccess.gov/cgi/t/text/text-idx?c=ecfr&sid=3275bea9e2d87163209535159a10234d&rgn=div5&view=text&node=41:1.2.3.1.2&idno=41 (41 CFR 60.2)] are contained in the contract. The local agency should be familiar with and enforce those requirements.  


All contractors or subcontractors whose contract or subcontract is $10,000.00 or more must submit Federal-Aid Highway Construction Contractors Annual EEO Report, [[media:136.11.6 2015.doc|Fig. 136.11.6 Form FHWA-1391]], to the MoDOT External Civil Rights Division. Employment data should total correctly on this report.  
The LPA shall furnish the name of the contractor or subcontractor whose contract or subcontract is $10,000.00 or more and must submit Federal-Aid Highway Construction Contractors Annual EEO Report, [[media:136.11.8.doc|Fig. 136.11.8, Form FHWA-1391]], to the MoDOT External Civil Rights Division. Employment data should total correctly on this report.  


If a contractor or subcontractor has been active on a project but no work was performed during the above payroll report period, a “No Work Was Performed” report is to be submitted. If a project has not started, no report is required.  
If a contractor or subcontractor has been active on a project but no work was performed during the above payroll report period, a “No Work Was Performed” report is to be submitted. If a project has not started, no report is required.  
Line 126: Line 150:
==136.11.8 Disadvantaged Business Enterprise (DBE)==
==136.11.8 Disadvantaged Business Enterprise (DBE)==


Disadvantaged Business Enterprise (DBE) requirements are also covered in [[:Category:146 Disadvantaged Business Enterprise (DBE)|EPG 146 Disadvantaged Business Enterprise (DBE)]].  DBE compliance consists of ensuring that the prime contractors utilize DBEs as indicated in their good faith effort.  These vendors will be a combination of subcontractors working on the project, suppliers, brokers, and trucking companies.  DBE vendors must be on the MoDOT-approved [http://contribute.modot.mo.gov/business/contractor_resources/External_Civil_Rights/mrcc.htm MRCC] listing at the bid opening.  After the contract is awarded, the contractors should provide a [http://www.modot.org/business/contractor_resources/documents/RequesttoSubcontract_C-220.pdf Request to Subcontract Work form] for each subcontractor noting the DBE/non-DBE classification.  If a subcontractor is added to the project, they need to be pre-approved by MoDOT prior to performing any work.  The LPA should track the DBE progress throughout the project to ensure the goal is met.  In calculating the percentage of the contract work performed, all prices for sublet work shall be at contract unit bid prices. Sample forms ([[media:136.11.4.doc|Fig. 136.11.4]] and [[media:136.11.5 2015.xls|Fig. 136.11.5]]) may be used for submitting subcontractor information and instructions for completing the form ([[media:136.11.6 2015.doc|Fig. 136.11.6]]) are available.  If there is a concern during the project, contact the External Civil Rights unit.  The prime contractor and LPA should ensure that the DBE vendors used to achieve the goal are performing a Commercially Useful Function (CUF).
Disadvantaged Business Enterprise (DBE) requirements are also covered in [[:Category:146 Disadvantaged Business Enterprise (DBE)|EPG 146 Disadvantaged Business Enterprise (DBE)]].  DBE compliance consists of ensuring that the prime contractors utilize DBEs as indicated in their good faith effort.  These vendors will be a combination of subcontractors working on the project, suppliers, brokers, and trucking companies.  DBE vendors must be on the MoDOT-approved [https://www6.modot.mo.gov/MRCC/Home/PublicSearch MRCC] listing at the bid opening.  After the contract is awarded, the contractors should provide a [https://www.modot.org/media/12323 Request to Subcontract Work form] for each subcontractor noting the DBE/non-DBE classification.  If a subcontractor is added to the project, they need to be pre-approved by MoDOT prior to performing any work.  The LPA should track the DBE progress throughout the project to ensure the goal is met.  In calculating the percentage of the contract work performed, all prices for sublet work shall be at contract unit bid prices. Sample forms ([https://epg.modot.org/forms/general_files/DE/RW-LPA/Request_to_Subcontract_C_220.pdf Fig. 136.11.4] and [[media:136.11.5 Dec 2015.xls|Fig. 136.11.5]]) may be used for submitting subcontractor information and instructions for completing the form ([[media:136.11.6 Dec 2015.pdf|Fig. 136.11.6]]) are available.  If there is a concern during the project, contact the [https://www.modot.org/welcome-external-civil-rights External Civil Rights Division].  The prime contractor and LPA should ensure that the DBE vendors used to achieve the goal are performing a Commercially Useful Function (CUF).


==136.11.9 Commercially Useful Function (CUF)==
==136.11.9 Commercially Useful Function (CUF)==


Commercially Useful Function (CUF) basically consists of checking that the DBE vendor performs the work, supplies the material, has its own labor, and controls its work. The RC or delegated representative shall conduct at least one CUF interview using the [[media:146 CUF May 2015.pdf|CUF Determination form]] for each DBE vendor on the project.  Additional interviews shall occur if the inspector notices a change in the DBE vendor or prime contractors operations.  The verification for CUF varies depending on the capacity the DBE vendor is being used.  See [http://epg.modot.org/index.php?title=Category:146_Disadvantaged_Business_Enterprise_%28DBE%29#146.3_Commercially_Useful_Function_Verifications EPG 146.3] for a detailed description of what constitutes a check for CUF for various DBE uses. Please review the common [http://contribute.modot.mo.gov/business/lpa/documents/COMMERCIALUSEFULFUNCTIONSREDFLAGS.pdf red flags] found on CUF reviews.
Commercially Useful Function (CUF) basically consists of checking that the DBE vendor performs the work, supplies the material, has its own labor, and controls its work. The RC or delegated representative shall conduct at least one CUF interview using the [https://epg.modot.org/forms/CM/CUF_Determination_Form.pdf CUF Determination form] for each DBE vendor on the project.  Additional interviews shall occur if the inspector notices a change in the DBE vendor or prime contractors operations.  The verification for CUF varies depending on the capacity the DBE vendor is being used.  See [https://epg.modot.org/index.php?title=Category:146_Disadvantaged_Business_Enterprise_%28DBE%29#146.3_Commercially_Useful_Function_Verifications EPG 146.3] for a detailed description of what constitutes a check for CUF for various DBE uses. Please review the common [http://contribute.modot.mo.gov/business/lpa/documents/COMMERCIALUSEFULFUNCTIONSREDFLAGS.pdf red flags] found on CUF reviews.


==136.11.10 On-the-job Training (OJT)==
==136.11.10 On-the-job Training (OJT)==
Line 136: Line 160:
On-the-job Training (OJT) requirements are also covered in [[136.9 Plans, Specs and Estimates (PS & E)#136.9.4.1.1.16 On the Job Training (OJT) (23 CFR Section 230)|EPG 136.9.4.1.1.16 On the Job Training]].  All training goals are established by the MoDOT External Civil Rights (ECR) Division prior to letting.  
On-the-job Training (OJT) requirements are also covered in [[136.9 Plans, Specs and Estimates (PS & E)#136.9.4.1.1.16 On the Job Training (OJT) (23 CFR Section 230)|EPG 136.9.4.1.1.16 On the Job Training]].  All training goals are established by the MoDOT External Civil Rights (ECR) Division prior to letting.  


Prior to the notice to proceed, the contractor shall submit the [http://www.modot.mo.gov/business/contractor_resources/documents/TraineeNotificaiton1.doc Trainee Notification form] to the RC or delegated representative. They will then forward the notification to MoDOT ECR Division for approval of the proposed trainee(s).  This process will be repeated if a trainee is added anytime during the project.  
Prior to the notice to proceed, the contractor shall submit the [https://epg.modot.org/forms/CM/OJT_1_Trainee_Notification.pdf Trainee Notification form] to the RC or delegated representative. They will then forward the notification to MoDOT ECR Division for approval of the proposed trainee(s).  This process will be repeated if a trainee is added anytime during the project.  


In addition to the trainee notification form, the contractor must submit [http://contribute.modot.mo.gov/business/contractor_resources/External_Civil_Rights/documents/MonthlyTraineeReport2.pdf monthly trainee reports] throughout the course of the training and the [http://contribute.modot.mo.gov/business/contractor_resources/External_Civil_Rights/documents/Train-CompletionReport3.pdf trainee completion form]. The final trainee summary shall be completed at the end of the project or when the trainee goal on the project has been achieved. These forms shall also be submitted to the RC or delegated representative. The LPA will then forward the notification to MoDOT ECR Division for approval. The monthly trainee reports will be verified by the RC or delegated representative against the certified payroll for accuracy and then forwarded to MoDOT ECR Division.  
In addition to the trainee notification form, the contractor must submit [https://epg.modot.org/forms/CM/OJT_2_Contractor_Monthly_Trainee_Report.pdf monthly trainee reports] throughout the course of the training and the [https://epg.modot.org/forms/CM/OJT_3_Training_Completion.pdf trainee completion form]. The final trainee summary shall be completed at the end of the project or when the trainee goal on the project has been achieved. These forms shall also be submitted to the RC or delegated representative. The LPA will then forward the notification to MoDOT ECR Division for approval. The monthly trainee reports will be verified by the RC or delegated representative against the certified payroll for accuracy and then forwarded to MoDOT ECR Division.  


For further information and guidance about the OJT program and the submittal forms, you may access [http://www.modot.mo.gov/business/contractor_resources/External_Civil_Rights/jobtraining.htm the ECR website] or call (573) 751-1216.
For further information and guidance about the OJT program and the submittal forms, you may access [https://www.modot.org/job-trainingcontract-compliance the ECR website] or call (573) 751-2978.


==136.11.11 Value Engineering Change Proposals==
==136.11.11 Value Engineering Change Proposals==


Value engineering change proposals (VECP) are meant to provide a product of equal or improved quality that will reduce the project cost, improve safety or decrease the time required to complete the project.  See [http://www.modot.mo.gov/business/standards_and_specs/Sec0104.pdf Sec 104.6] and [http://epg.modot.org/index.php?title=Category:130_Value_Engineering#130.2_Contractor_initiated_VECPs EPG 130.2] for guidelines on contractor proposals for value engineering.  A VECP must be approved by the contractor, consultant engineer (if applicable), LPA, MoDOT and FHWA (if applicable).  
Value engineering change proposals (VECP) are meant to provide a product of equal or improved quality that will reduce the project cost, improve safety or decrease the time required to complete the project.  See [http://www.modot.org/business/standards_and_specs/SpecbookEPG.pdf#page=4 Sec 104.6] and [https://epg.modot.org/index.php?title=Category:130_Value_Engineering#130.2_Contractor_initiated_VECPs EPG 130.2] for guidelines on contractor proposals for value engineering.  A VECP must be approved by the contractor, consultant engineer (if applicable), LPA, MoDOT and FHWA (if applicable).  


==136.11.12 Construction Administration==
==136.11.12 Construction Administration==


===136.11.12.1 Consultant Conflict of Interest===
===136.11.12.1 Consultant Conflict of Interest===
Under [http://edocket.access.gpo.gov/cfr_2004/aprqtr/pdf/23cfr1.33.pdf 23 CFR 1.33], neither a consulting engineering firm, nor any of its employees, that is providing engineering and inspection services for the contracting agency shall be allowed to perform work that is the construction contractor's responsibility.  
Under [https://www.ecfr.gov/cgi-bin/text-idx?SID=004674eb2f1f808c87da0c3713c3662e&mc=true&node=se23.1.1_133&rgn=div8 23 CFR 1.33], neither a consulting engineering firm, nor any of its employees, that is providing engineering and inspection services for the contracting agency shall be allowed to perform work that is the construction contractor's responsibility.  


It is unacceptable for a consultant to provide both project engineering services for the LPA and engineering services for the project construction contractor. Operating under this arrangement gives the appearance of a possible conflict of interest and is not allowed for federal-aid work, although, surveying will be permitted.
It is unacceptable for a consultant to provide both project engineering services for the LPA and engineering services for the project construction contractor. Operating under this arrangement gives the appearance of a possible conflict of interest and is not allowed for federal-aid work, although, surveying will be permitted.
Line 167: Line 191:


==136.11.13 Documentation Requirements==
==136.11.13 Documentation Requirements==
All costs incurred by the local agency for which federal reimbursement is sought must be supported by original source documents or documentation that provides adequate assurance the quantities of completed work were determined accurately and on a uniform basis. The primary source of administration information is found in two basic sources, the project inspector’s diary and payment diary. These diaries are the primary documents used to verify construction progress and payment and may become a crucial element if any disputes or issues arise on the project.
Diaries are essential to provide a description of day-to-day activities that occurred on the project, valuable quality control information and historical information of how the project was constructed.  As such, the diary is a document focusing on critical project information and used as a communication tool to assist in explaining what the contractor did that day and what took place on the job site.  By completing a diary, this provides assurances to MoDOT, taxpayers and FHWA there was compliance and quality control on the project.  The diary serves as the primary source of information to ensure pay quantities were measured and paid for accordingly.  It should also summarize the labor, material, equipment, work accomplished and other events that affect or explain the contractors progress.  The diary then becomes a factual, historical document used to review project compliance, contractor claims or dispute resolution, and serves as the project documentation during an audit.
Diaries are written such that they are:
:1. Clear; including  handwriting and meaning.  Refrain from words such as they, he, she.  Instead use specific names of individuals.
:2. Concise; use minimum number of words and be factual
:3. Correct; numerous corrected errors give impression of quality of work
:4. Complete; include all information needed to be clear.  Document as if describing to someone unfamiliar with the project.  Include items such as activities and testing that took place, the result of those activities and tests and any action taken from those results.
:5. Concurrent; document as the events happen, not after.  Waiting too long to document makes it easy to forget the specifics.


All costs incurred by the local agency for which federal reimbursement is sought must be supported by original source documents or documentation that provides adequate assurance that the quantities of completed work were determined accurately and on a uniform basis.  The primary source of administration information shall be found in two basic sources, the project inspector’s diary and payment diary.  These diaries are the primary documents used to verify construction progress and payment and may become a crucial element if any disputes or issues arise on the project.  Samples of documentation may be obtained from the local MoDOT representative.
Samples of documentation may be obtained from the district MoDOT representative.


===136.11.13.1 Project Diaries===
===136.11.13.1 Project Diaries===
Diaries and field books can be handwritten bound documents or saved as computer files. Handwritten diaries shall be completed in ink in securely bound high-grade field books. Any corrections shall be made by lining out the entry, initialing and dating. Do not use erasures or correction fluids to make changes.
Diaries and field books can be handwritten, bound documents or electronic and part of electronic construction management software systems. Diaries must be accurate, well-documented and completed in a timely manner, whether that be as the day progresses, at the end of the day or no later than the next day.
 
Handwritten diaries shall be completed in ink in securely bound, high-grade field books. Any corrections shall be made by lining out the entry, initialing and dating. Do not use erasures or correction fluids to make changes.


If computer files are used, a secure back up shall be maintained. Any computer generated diaries must be kept in an [[media:Fig. 136.11.16.docx|approved software system]] that secures the documents from editing once created.
If electronic systems are used, a secure back up shall be maintained. Any electronically generated diaries must be kept in a software system which meets the following criteria:
:1. Contract administrator(s) shall not have the capability of deleting any diary information
:2. Any changes to diary entries shall be documented with
::a. Previous entry
::b. Corrected entry
::c. Name or initials of person making the correction
::d. Date of correction
::e. Reason for correction.


'''The following information shall be included in the daily diary:'''
It is the LPA’s responsibility to ensure electronic diary system meets these requirements.  MoDOT / FHWA may review electronic diaries during any project review or site visit.  If it is determined changes to diary entries were deleted or in any other way compromised, the LPA will be at risk of losing ''all'' federal funding for the project.


:* Include facts only, no opinions.
The project diary is completed daily, even if no work occurs, and includes the following: 
:* Facts only, no opinions
:* Date
:* Date
:* Weather information including statement related to whether conditions are suitable for construction progress.
:* Weather including statements related to whether conditions are suitable for construction progress and any delays due to weather.  If not working due to weather, make such notation for the day.
:* Running total of contract time charged and reasons for days credited.
:* Progress of work as a percentage; suggested as a bar chart in a suitable scale to indicate the percentage of work completed to date 
:* Contractor information for each contractor on the project including:
:* Pay item documentation including work by local forces
::* Name of contractor
:* Instructions to contractor
::* List of contractor personnel by job classification
:* Unusual occurrences effecting project activities 
::* List of contractors major equipment
:* Determination of physical condition of work performed, i.e. temporary traffic control items, erosion control items
::* Note if contractor is a DBE
:* Documentation of tests performed and test results
::* Work performed by the contractor
:* Contractor work hours
::* Notable discussion or interaction between the inspector and the contractor; e.g. deficient work order, etc.
:* Completion of check lists
:* Noted events for the day examples may include:
:* Objective remarks of end product
::* Status of project Traffic Control Operations including any changes made to the traffic control plan
:* Visitors and communication on the project site
::* Status of project’s erosion control including any changes made to the erosion control plan
:* Labor, equipment and material on site including usage, delays, breakdowns, idle time, inefficiencies, work accomplished and other events that affect or explain contractor progress.  If not working due to materials shortages, equipment breakdowns, rejected material, etc., make note of such.
::* Work or materials rejected and reasons why
:* Number of employees in each trade and each employee matched with their item of work and equipment including any specific to DBE
::* Length and cause of any delay
:* Signature of inspector completing the diary
::* Unusual conditions and effect on job
:* If a working day contract, the running total of contract time charged and reasons for days credited.
::* Visitors to the project site
:* Examples of noted events for the day are recommended to include:
::* Other inspector action i.e. note wage interviews, DBE compliance checks, major material status etc.
::Status of project Traffic Control Operations including any changes made to the traffic control plan
:* Signature of Inspector completing the diary.
::Status of project’s erosion control including any changes made to the erosion control plan
 
::Work or materials rejected and reasons why
For more information on federal requirements and guidelines, see the [http://www.fhwa.dot.gov/programadmin/contracts/ FHWA – Construction Contract Administration webpage].
::Length and cause of any delay
::Unusual conditions and effect on job; including any crashes that occurred in the work zone
::Visitors to the project site
::Other inspector action, e.g. note wage interviews, DBE compliance checks, major material status, etc.


Scroll down on [http://www.modot.org/business/lpa/cert_train.htm MoDOT's LPA website] to locate a free online NHI training course on Daily Diaries.  
For more information on federal requirements and guidelines, see the [http://www.fhwa.dot.gov/programadmin/contracts/ FHWA – Construction Contract Administration webpage] or scroll down on [http://www.modot.org/business/lpa/NHITraining.htm MoDOT's LPA website] to locate an online NHI training course on Daily Diaries.


===136.11.13.2 Payment Diaries===
===136.11.13.2 Payment Diaries===
Line 207: Line 254:
:* Date
:* Date
:* Inspectors signature or initials
:* Inspectors signature or initials
:* Location of the installed work.
:* Location of the installed work indicated by stations, log miles or location-based reference.  Pictures are also a good documentation source.  
:* Quantity of work installed on that day.
:* Quantity of work installed on that day.
:* Running total of that item of work.
:* Running total of that item of work.
:* Any pertinent calculations or measurements.
:* Any pertinent calculations or measurements including charge orders, extra work or work by local forces.  
:* Material received and approved (or rejected and reasoning).  
:* Material received and approved (or rejected and reasoning).  
:* Receipt of materials certification.
:* Receipt of materials certification.
Line 218: Line 265:


===136.11.13.3 Invoices===
===136.11.13.3 Invoices===
The LPA must submit invoices to MoDOT for reimbursement of costs contained in the agreements and contracts as they are incurred.  The invoices may not be submitted more than once every two weeks. Progress invoices must be submitted monthly.  The final invoice must be submitted within 30 days of final acceptance. For detailed information on the procedures to be followed, see [[136.3 Federal Aid Basics#136.3.15 Reimbursement and Auditing|EPG 136.3.15 Reimbursement and Auditing]]. [[media:Fig. 136.11.14.pdf|Fig. 136.11.14]] and [[media:Fig. 136.11.15.pdf|Fig 136.11.15]] are construction invoices that can be used as examples when preparing a construction invoice for reimbursement.
The LPA must submit invoices to MoDOT for reimbursement of costs contained in the agreements and contracts as they are incurred.  The invoices may not be submitted more than once every two weeks. Progress invoices must be submitted monthly.  The final invoice must be submitted within 30 days of final acceptance. See [[LPA:136.12 Figures, Glossary and Other Useful Links#Construction Reimbursement Form|Figure 136.3.18 for Construction Invoice]] templates. For detailed information on the procedures to be followed, see [[136.3 Federal Aid Basics#136.3.15 Reimbursement and Auditing|EPG 136.3.15 Reimbursement and Auditing]]. In addition, [[media:Fig. 136.11.14 secure.pdf|Fig. 136.11.14]] and [[media:Fig. 136.11.15.pdf|Fig 136.11.15]] are completed construction invoices that can be used as examples when preparing a construction invoice for reimbursement.


===136.11.13.4 Erosion Control===
===136.11.13.4 Erosion Control===
The LPA shall ensure the land disturbance site is inspected on a regular schedule and within a reasonable time period (not to exceed 48 hours) following a runoff event. Regularly scheduled inspections (recommend using MoDOT's [http://epg.modot.mo.gov/forms/CO/Erosion%20Control%20Inspection%20Record.dot Erosion Control Inspection Record]) shall be conducted at a minimum of once every seven days. For disturbed areas where permanent ground cover has not been established, all installed BMPs and other pollution control measures shall be inspected for proper installation, operation and maintenance.  
The LPA shall ensure the land disturbance site is inspected on a regular schedule and within a reasonable time period (not to exceed 48 hours) following a runoff event. Regularly scheduled inspections (recommend using MoDOT's [https://www.modot.org/media/983 Land Disturbance Inspection Record]) shall be conducted at a minimum of once every seven days. For disturbed areas where permanent ground cover has not been established, all installed BMPs and other pollution control measures shall be inspected for proper installation, operation and maintenance.  


Locations where storm water leaves the site shall be inspected for evidence of erosion or sediment deposition. Any deficiencies noted during a weekly inspection shall be corrected within seven calendar days of that inspection. The results of the weekly inspections in a given month shall be recorded in that month’s report. The inspector shall promptly notify the site contractors responsible for operation and maintenance of BMPs of the deficiencies. See [http://epg.modot.org/index.php?title=Category:806_Pollution%2C_Erosion_and_Sediment_Control#806.7_Construction_Inspection_Guidance_for_Sec._806 EPG 806.7 Construction Inspection Guidance for Sec. 806] and [http://epg.modot.org/index.php?title=Category:203_Roadway_and_Drainage_Excavation%2C_Embankment_and_Compaction#Borrow_.28Sec_203.3.29 EPG 203.1 Borrow] for more information regarding storm water and erosion control requirements.
Locations where storm water leaves the site shall be inspected for evidence of erosion or sediment deposition. Any deficiencies noted during a weekly inspection shall be corrected within seven calendar days of that inspection. The results of the weekly inspections in a given month shall be recorded in that month’s report. The inspector shall promptly notify the site contractors responsible for operation and maintenance of BMPs of the deficiencies. See [https://epg.modot.org/index.php?title=Category:806_Pollution%2C_Erosion_and_Sediment_Control#806.7_Construction_Inspection_Guidance_for_Sec._806 EPG 806.7 Construction Inspection Guidance for Sec. 806] and [https://epg.modot.org/index.php?title=Category:203_Roadway_and_Drainage_Excavation%2C_Embankment_and_Compaction#Borrow_.28Sec_203.3.29 EPG 203.1 Borrow] for more information regarding storm water and erosion control requirements.


A log of each inspection shall be kept. The inspection report is to include the following minimum information: inspector’s name, date of inspection, observations relative to the effectiveness of the BMPs, actions taken or necessary to correct deficiencies, and listing of areas where land disturbance operations have permanently or temporarily stopped. The inspection report shall be signed by the inspector.  
A log of each inspection shall be kept. The inspection report is to include the following minimum information: inspector’s name, date of inspection, observations relative to the effectiveness of the BMPs, actions taken or necessary to correct deficiencies, and listing of areas where land disturbance operations have permanently or temporarily stopped. The inspection report shall be signed by the inspector.  


The LPA shall at all times ensure that all pollution control measures and systems are in good order to achieve compliance with the terms of the general permit.  
The LPA shall at all times ensure that all pollution control measures and systems are in good order to achieve compliance with the terms of the general permit.


===136.11.13.5 American’s with Disabilities Act (ADA) Check List===
===136.11.13.5 American’s with Disabilities Act (ADA) Checklist===
Pedestrian facilities must be accessible to all people to the maximum extent feasible in accordance with Title V of the Americans with Disabilities Act of 1990 (ADA).  For detailed information and criteria see [[:Category:642 Pedestrian Facilities|EPG 642 Pedestrian Facilities]].  
Pedestrian facilities must be accessible to all people to the maximum extent feasible in accordance with Title II of the Americans with Disabilities Act of 1990 (ADA).  For detailed information and criteria see [[:Category:642 Pedestrian Facilities|EPG 642 Pedestrian Facilities]].  


Prior to or during the final inspection, the [http://www.modot.org/business/manuals/LPAContacts.htm MoDOT district representative] will utilize the [[media:136.9.4 2015.doc|ADA Checklist, EPG Fig 136.9.4]], to verify the project has been constructed to meet the current ADA requirements.  Providing the checklist to the contractor at the preconstruction conference is considered a best practice.
Prior to or during the final inspection, the [https://www.modot.org/about-lpacontact-us MoDOT district representative] will utilize the [https://epg.modot.org/forms/CM/ADA_Checklist.pdf ADA Checklist, (PDF version of Fig. 136.9.4)] (or the  [https://epg.modot.org/forms/CM/ADA_Checklist.docx MS Word version of the ADA Checklist, Fig. 136.9.4]), to verify the project has been constructed to meet the current ADA requirements.  Providing the checklist to the contractor at the preconstruction conference is considered a best practice.


===136.11.13.6 Progress Reports===
===136.11.13.6 Progress Reports===
The LPA shall submit a copy of a monthly report to the [http://www.modot.org/business/manuals/LPAContacts.htm MoDOT district representative] stating the progress of the work. [[media:136.11.3.doc|Fig. 136.11.3]] provides the Progress Report format. The LPA may elect to summarize construction activities for the project on a weekly basis and consolidate them into the monthly report.
The LPA shall submit a copy of a monthly report to the [https://www.modot.org/about-lpacontact-us MoDOT district representative] stating the progress of the work. [[media:136.11.3 2016.pdf|Fig. 136.11.3]] provides the Progress Report format. The LPA may elect to summarize construction activities for the project on a weekly basis and consolidate them into the monthly report.


===136.11.13.7 Document Retention===
===136.11.13.7 Document Retention===
The MoDOT district or FHWA representative may review daily diaries and payment diaries on the project site at any time.  The LPA shall maintain all books, documents, papers, accounting records and other evidence pertaining to the costs incurred. Such materials shall be available at the LPA’s office for inspection by MoDOT, [http://www.fhwa.dot.gov/ FHWA] or their authorized representatives at all reasonable times during the contract period and for (3) three years after the date on which the local agency receives reimbursement of its final invoice from MoDOT, and copies thereof shall be furnished if requested.  
The MoDOT district or FHWA representative may review daily diaries and payment diaries on the project site at any time.  The LPA shall maintain all books, documents, papers, accounting records and other evidence pertaining to the costs incurred. Such materials shall be available at the LPA’s office for inspection by MoDOT, [http://www.fhwa.dot.gov/ FHWA] or their authorized representatives at all reasonable times during the contract period and for (3) three years after the date on which the local agency receives reimbursement of its final invoice from MoDOT, and copies thereof shall be furnished if requested.


==136.11.14 Labor==
==136.11.14 Labor==
Line 245: Line 292:


===136.11.14.1 Labor Records===
===136.11.14.1 Labor Records===
The LPA shall obtain payrolls and forms related to [http://ecfr.gpoaccess.gov/cgi/t/text/text-idx?c=ecfr&sid=3275bea9e2d87163209535159a10234d&rgn=div5&view=text&node=41:1.2.3.1.1&idno=41 Equal Employment Opportunity (41 CFR 60.1)] and [http://ecfr.gpoaccess.gov/cgi/t/text/text-idx?c=ecfr&sid=3275bea9e2d87163209535159a10234d&rgn=div5&view=text&node=41:1.2.3.1.2&idno=41 (41 CFR 60.2)]. They shall also ascertain that necessary posters (see [[#136.11.13 Documentation Requirements|EPG 136.11.13 Documentation Requirements]]) are in place on the project.  
The LPA shall obtain payrolls and forms related to [https://www.ecfr.gov/cgi-bin/text-idx?tpl=/ecfrbrowse/Title41/41cfr60-1_main_02.tpl Equal Employment Opportunity (41 CFR 60.1)] and [https://www.ecfr.gov/cgi-bin/text-idx?SID=532eba60f86eea33a5dbf5930bf29b41&mc=true&node=pt41.1.60_62&rgn=div5 (41 CFR 60.2)]. They shall also ascertain that necessary posters (see [[#136.11.13 Documentation Requirements|EPG 136.11.13 Documentation Requirements]]) are in place on the project.  


A certified copy of each weekly payroll must be submitted by the prime contractor within 7 days of the payment date of the payroll. The certification may be attached to the payroll or may be on the payroll itself. The prime contractor will be responsible for the submittal of payrolls and certifications for all subcontractors on the project.  In the event that work is temporarily suspended, the last payroll shall be marked appropriately to note that it will be the last payroll until work is resumed.  
A certified copy of each weekly payroll must be submitted by the prime contractor within 7 days of the payment date of the payroll. The certification may be attached to the payroll or may be on the payroll itself. The prime contractor will be responsible for the submittal of payrolls and certifications for all subcontractors on the project.  In the event that work is temporarily suspended, the last payroll shall be marked appropriately to note that it will be the last payroll until work is resumed.  
Line 265: Line 312:


:3. Check the payroll for correct hourly wage and, where applicable, the correct overtime hourly rate.  
:3. Check the payroll for correct hourly wage and, where applicable, the correct overtime hourly rate.  
::a. Check employee’s rate of pay against the state and federal wage rates, where applicable, to make sure he/she is receiving at least the minimum for his/her classification as per the prevailing wage schedule in the contract. For federally funded projects the rate of pay is the highest of either the federal or state wage rates.  
::a. Check employee’s rate of pay against the state and federal wage rates, where applicable, to make sure the employee is receiving at least the minimum for the individual's classification as per the prevailing wage schedule in the contract. For federally funded projects the rate of pay is the highest of either the federal or state wage rates.  
::b. Make sure fringe benefit amount plus base pay amount matches or exceeds the designated fringe benefit amount plus designated base pay amount from the applicable wage order. For example, the base pay amount could be less than that designated as the prevailing wage, if the fringe benefit amount is more than that designated, and the two together meet or exceed the designated gross prevailing wage. The contractor should be encouraged to list the exact fringe paid for each employee on the payroll. If the contractor chooses to certify that the fringe benefits are being paid to approved plans, funds, or programs, the contractor shall provide documentation that the correct payment amount is being paid to the fund for the individual employees.  
::b. Make sure fringe benefit amount plus base pay amount matches or exceeds the designated fringe benefit amount plus designated base pay amount from the applicable wage order. For example, the base pay amount could be less than that designated as the prevailing wage, if the fringe benefit amount is more than that designated, and the two together meet or exceed the designated gross prevailing wage. The contractor should be encouraged to list the exact fringe paid for each employee on the payroll. If the contractor chooses to certify that the fringe benefits are being paid to approved plans, funds, or programs, the contractor shall provide documentation that the correct payment amount is being paid to the fund for the individual employees.  
::Check the daily and weekly hours worked in each classification including actual overtime hours worked (not adjusted hours).  
::Check the daily and weekly hours worked in each classification including actual overtime hours worked (not adjusted hours).  
Line 287: Line 334:


===136.11.14.2 Labor Interviews===
===136.11.14.2 Labor Interviews===
LPA personnel are to conduct one wage rate interview on each project every two weeks. Labor interviews are not required on railroad and other utility adjustments. The interviewer shall determine the employee’s name, the classification of the employee, the actual wage paid, and the posted wage rate. Interviews shall be documented as shown on form, [[media:136.11.7.doc|Fig. 136.11.5 Wage Rate Interview (Labor Compliance/EEO)]].  
LPA personnel are to conduct one wage rate interview on each project every two weeks. Labor interviews are not required on railroad and other utility adjustments. The interviewer shall determine the employee’s name, the classification of the employee, the actual wage paid, and the posted wage rate. Interviews shall be documented as shown on form, [https://epg.modot.org/forms/CM/CR1_Wage_Rate_Interview.pdf Fig. 136.11.5 Wage Rate Interview (Labor Compliance/EEO)].  


The LPA shall submit a semi-annual report to the [http://www.modot.org/business/manuals/LPAContacts.htm MoDOT district representative] containing the following information:  
The LPA shall submit a semi-annual report to the [https://www.modot.org/about-lpacontact-us MoDOT district representative] containing the following information:  


:1. Number of contractors or subcontractors against whom complaints were received  
:1. Number of contractors or subcontractors against whom complaints were received  
Line 301: Line 348:
:6. Amount of liquidated damages assessed under Work Hours Act of 1962
:6. Amount of liquidated damages assessed under Work Hours Act of 1962


The above report is due not later than April 4 for the period from October 1 to March 31 and not later than October 5 for the period from April 1 to September 30. This report shall include all information gathered on all projects.  
The above report is due not later than April 4 for the period from October 1 to March 31 and not later than October 5 for the period from April 1 to September 30. This report shall include all information gathered on all projects.


==136.11.15 Change Orders==
==136.11.15 Change Orders==
Line 308: Line 355:


===136.11.15.1 Change Order Documentation===
===136.11.15.1 Change Order Documentation===
Change orders should be documented on the MoDOT change order report form ([[media:136.11.2.doc|Fig. 136.11.2]]) and be identified by the Federal-aid project number, if applicable. The LPA representative writing the change order should use brief, accurate and complete reasons for the contract changes.  The reasons should include construction facts; such as utility locations, incorrect shrinkage factors, plan sheet errors, excessive erosion, etc.; rather than general statements that merely state quantities vary.  Change order items should be listed in the same order as they appear in the contract.  No combination of items will be permitted.  Controlling specifications should be checked carefully to establish the LPA’s responsibility for payment.  Change orders are to be numbered consecutively per contract.
Change orders should be documented on the MoDOT change order report form ([[media:136.11.2.xlsx|Fig. 136.11.2]]) and be identified by the Federal-aid project number, if applicable. The LPA representative writing the change order should use brief, accurate and complete reasons for the contract changes.  The reasons should include construction facts; such as utility locations, incorrect shrinkage factors, plan sheet errors, excessive erosion, etc.; rather than general statements that merely state quantities vary.  Change order items should be listed in the same order as they appear in the contract.  No combination of items will be permitted.  Controlling specifications should be checked carefully to establish the LPA’s responsibility for payment.  Change orders are to be numbered consecutively per contract.


If the change order includes a contingent item for which the method of payment is not established by the contract specifications, a detail of all work covered by that item and the supplemental specification covering construction of that item must be shown including description, materials, construction requirements, method of measurement and basis of payment. References to the contract specifications may be used when applicable.
If the change order includes a contingent item for which the method of payment is not established by the contract specifications, a detail of all work covered by that item and the supplemental specification covering construction of that item must be shown including description, materials, construction requirements, method of measurement and basis of payment. References to the contract specifications may be used when applicable.
Line 336: Line 383:


There are three levels of change order approval:
There are three levels of change order approval:
 
<div id="Change Order Level 1"></div>
'''Change Order Level 1''' is approved in documentation, by the contractor, consulting engineer (if applicable), the LPA and verbally by the [http://www.modot.org/business/manuals/LPAContacts.htm MoDOT district representative].  Copies of Level 1 change orders must be submitted with the next progress invoice.  Level 1 conditions include:  
'''Change Order Level 1''' is approved in documentation, by the contractor, consulting engineer (if applicable), the LPA and by the [https://www.modot.org/about-lpacontact-us MoDOT district representative].  Level 1 conditions include:  


:1. Any no-cost change orders (used when the direct substitution of a particular line item with a contingent item does not generate an additional cost or cost reduction).  
:1. Any no-cost change orders (used when the direct substitution of a particular line item with a contingent item does not generate an additional cost or cost reduction).  
Line 343: Line 390:
:Examples of a Level 1 change order are available.
:Examples of a Level 1 change order are available.


'''Change Order Level 2''' is approved in documentation, by all listed in Change Order Level 1 and the MoDOT district representative and the FHWA, if applicable. Level 2 conditions include:  
'''Change Order Level 2''' is approved, in documentation, by all listed in Change Order Level 1 and the FHWA on projects designated for federal involvement for change orders on the PODI Matrix. Level 2 conditions include:  


:1. Final change orders  
:1. Final change orders  
Line 370: Line 417:


Development of an Issue Resolution Process – The key players should design their own systems for resolving issues on the project.  Specific teams composed of personnel from the various stakeholders, who are knowledgeable about their particular technical portions of the contract, discuss potential problems and the way they would like to see them handled.  They decide how issues that are not resolved at their level will be escalated to the next level in a timely fashion so that the decision-making process becomes more efficient and costly delays are avoided.
Development of an Issue Resolution Process – The key players should design their own systems for resolving issues on the project.  Specific teams composed of personnel from the various stakeholders, who are knowledgeable about their particular technical portions of the contract, discuss potential problems and the way they would like to see them handled.  They decide how issues that are not resolved at their level will be escalated to the next level in a timely fashion so that the decision-making process becomes more efficient and costly delays are avoided.
The [http://www.modot.mo.gov/business/materials/Project%20Conflict%20Resolution%20Flowchart.pdf MoDOT Conflict Resolution Flowchart] is available.


Contractor Claims – In the event of a claim, contact your MoDOT representative.  If federal-aid participation is desired in a contract claim payment, early and often coordination is necessary between FHWA, MoDOT and the LPA.
Contractor Claims – In the event of a claim, contact your MoDOT representative.  If federal-aid participation is desired in a contract claim payment, early and often coordination is necessary between FHWA, MoDOT and the LPA.
Line 380: Line 425:


===136.11.17.1 Material Acceptance===
===136.11.17.1 Material Acceptance===
Material acceptance is based on the following three types of sampling and testing:  
Material acceptance is based on the following two types of sampling and testing:  


:1. Job control samples are taken and tests are conducted as work progresses to assure the project is constructed in compliance with the applicable specifications. All project sampling and testing of materials shall be performed by the LPA or by a consultant employed by the LPA. The guidelines in the [[Off-Systems Guide Schedule for Federal-Aid Acceptance Sampling and Testing (FAST)|Off-Systems Guide Schedule for Federal-Aid Acceptance Sampling and Testing (FAST) table]] should be followed as a minimum.  
:1. Job control samples are taken and tests are conducted as work progresses to assure the project is constructed in compliance with the applicable specifications. All project sampling and testing of materials shall be performed by the LPA or by a consultant employed by the LPA. The guidelines in the [[Off-Systems Guide Schedule for Federal-Aid Acceptance Sampling and Testing (FAST)|Off-Systems Guide Schedule for Federal-Aid Acceptance Sampling and Testing (FAST) table]] should be followed as a minimum.  
Line 390: Line 435:
:Submission of job control test results to MoDOT is not required unless requested by MoDOT or the FHWA. These test results must be retained as outlined in this article.  
:Submission of job control test results to MoDOT is not required unless requested by MoDOT or the FHWA. These test results must be retained as outlined in this article.  


:2. Independent assurance samples and tests will be performed by MoDOT personnel in accordance with the procedures and at the frequency set forth in [[106.22 Material Inspection Revisions|EPG 106.22 Material Inspection Revisions]]
:2. Independent assurance samples and tests will be performed by MoDOT personnel in accordance with the procedures and at the frequency set forth in [[106.22 Material Inspection Revisions|EPG 106.22 Material Inspection Revisions]].
 
:3. Small quantities of materials may be accepted for an LPA project based on some combination of certification documentation, delivery tickets and visual inspection.  This allowance is intended for materials that will not adversely affect the traffic-carrying capacity of the completed facility and are not to be used for concrete in major structures, permanent mainline or ramp pavements, or other structurally critical items.  The table below provides the schedule of materials quantities which may be accepted without complying with the sampling and testing requirements mentioned above. Any major deviation from this schedule should be approved by MoDOT at the PS&E submission.


===136.11.17.2 Material Documentation===
===136.11.17.2 Material Documentation===
Line 405: Line 448:
==136.11.18 Final Plans==
==136.11.18 Final Plans==


If any project involves work on state right of way or if MoDOT will be maintaining any portion of the completed improvement, the local agency shall furnish to the [http://www.modot.org/business/manuals/LPAContacts.htm MoDOT district representative] two complete sets of final “as built” plans. Final plans shall be submitted within 60 days of final acceptance of the project.  
If any project involves work on state right of way or if MoDOT will be maintaining any portion of the completed improvement, the local agency shall furnish to the [https://www.modot.org/about-lpacontact-us MoDOT district representative] two complete sets of final “as built” plans. Final plans shall be submitted within 60 days of final acceptance (as defined in [[#136.11.19 Final Acceptance|EPG 136.11.19 Final Acceptance]]) of the project.  


For all bridge plans, if there are any design changes, final “as built” bridge plans shall be submitted to the MoDOT district representative.  
For all bridge plans, if there are any design changes, final “as built” bridge plans shall be submitted to the MoDOT district representative.


==136.11.19 Final Acceptance==
==136.11.19 Final Acceptance==


Final acceptance of a project by an LPA can occur through one or more stages.
''Final acceptance'' of a project by an LPA occurs by verifying successful project completion through one or more inspections.  
When the LPA and the contractor presume that project construction is complete, an inspection is scheduled by the LPA. The inspection party includes representatives from the LPA, MoDOT, general contractor, and in some cases, the FHWA and subcontractor(s).   
 
When the LPA and the prime contractor presume that project construction is complete, an inspection is scheduled by the LPA. The inspection party includes representatives from the LPA, MoDOT, prime contractor, and in some cases, the FHWA and subcontractor(s).  
 
The scheduled inspection becomes the ''final inspection'' if it is determined by the inspection party that all contract items have been completed in their entirety and are of satisfactory quality.  By merit of the final inspection, the project also receives ''final acceptance''.
   
The scheduled inspection becomes a ''semi-final inspection'', if it is determined by the inspection party that corrections or exceptions must be made before ''final acceptance''.
:* <u>Corrections</u> are work items that affect the performance and serviceability of the project and impact road users until they are completed.


:* If it is determined by the inspection party that all contract items have been completed in their entirety and are of satisfactory quality, then this inspection constitutes a <u>"final inspection"</u>.   
:* <u>Exceptions</u> are time-dependent work items that do not directly impact road usersThey generally fall into one of the three following categories:


:* If it is determined by the inspection party that corrections must be made before final acceptance, then this inspection constitutes a <u>"semi-final inspection"</u>. After the corrections have been made, another inspection takes place with essentially the same inspection party and if everything is satisfactory, then the inspection becomes the "final inspection".  
::1. Establishment of soil stabilization through seeding/sodding/planting and maintenance of associated temporary erosion control measures,
::2. Traffic signal test periods,
::3. Lighting system test periods.


The LPA may deem the project substantially complete after a semi-final inspection and grant a <u>"partial acceptance"</u>, halting the working/calendar day count until the corrections are made.  Typically, this should only be granted when the corrections can be made without delaying opening the project limits to normal public travel.  Also, completion of the construction activities that constitute substantial completion should be outlined in the original contract agreement.
After the corrections have been successfully completed the LPA may deem the project ''substantially complete'' and halt the working/calendar day count.  


<u>"Final acceptance"</u> by the LPA occurs after the successful final inspection. The LPA takes over maintenance responsibility for the project from the contractor when the corrections are completed.
After corrections <u>and</u> exceptions have been successfully completed, the LPA inspection party shall perform a ''final inspection'' and grant ''final acceptance''. The LPA takes over maintenance responsibility for the project from the contractor.


Final acceptance by MoDOT occurs after the LPA has submitted all the applicable [http://epg.modot.mo.gov/forms/CO/Final%20Acceptance%20Checklist.dot final documents] (certifications) listed in EPG 136.11.20 Project Closeout Certifications. Afterwards, MoDOT will issue a [http://epg.modot.mo.gov/forms/CO/Final%20Acceptance%20-%20Off%20System.dot final acceptance report (form C-239)] to the LPA.
''Final acceptance'' by MoDOT occurs after the LPA has submitted all the applicable [[media:136.11.22.docx| final documents]] (certifications) listed in EPG 136.11.20 Project Closeout Certifications. These documents are to be received within 60 days of the final inspection date. After review and acceptance of the documentation, MoDOT will issue a [[media:Form C-239 2016.pdf|final acceptance report (Form C-239 LPA)]] and process final reimbursement to the LPA.


==136.11.20 Project Closeout Certifications==
==136.11.20 Project Closeout Certifications==
Line 428: Line 480:
Full payment of the final invoice will not be considered until the local agency has electronically furnished the following documents:  
Full payment of the final invoice will not be considered until the local agency has electronically furnished the following documents:  


:1. The local agency’s semi-final inspection letter stating the date of semi-final inspection and listing those who were present. Required for both contractor and local agency work, where applicable.  
:1. The [[media:136.11.23 2016.pdf|LPA Semi-Final Inspection Checklist (Form C-236 LPA)]], that includes the listing of those who were present at the semi-final inspection. This is required for both contractor and local agency work, where applicable.


:2. The LPA’s final acceptance letter showing the number of working days or calendar days charged, completion date and the amount of liquidated damages, if any.  
:2. The LPA’s [[media:136.11.18.docx|final acceptance letter]] showing the number of working days or calendar days charged, completion date and the amount of liquidated damages, if any.  


:3. A final list of acceptance testers used on the project and a certification stating  
:3. A [[media:136.11.19.docx|final list of acceptance testers]] used on the project and a certification stating  


::a. “The results of the tests or acceptance samples indicate that material incorporated in the construction work and the construction operations controlled by sampling and testing were in reasonably close conformity with the approved plans and specifications, and such results compare favorably with the results of independent assurance sampling and testing.” Any deviations from the specifications must be explained along with the reason for acceptance.  
::a. “The results of the tests or acceptance samples indicate that material incorporated in the construction work and the construction operations controlled by sampling and testing were in reasonably close conformity with the approved plans and specifications, and such results compare favorably with the results of independent assurance sampling and testing.” Any deviations from the specifications must be explained along with the reason for acceptance.  
Line 442: Line 494:
:4. Contractor certification and local agency recommendation  
:4. Contractor certification and local agency recommendation  


::a. The [[media:136.11.9.doc|Fig. 136.11.9 Contractor DBE Certification]] showing the final DBE participation on the project including the DBEs used, the type of work performed, and the dollar amount paid to each DBE.  
::a. The [[media:136.11.9 2016.docx|Fig. 136.11.9 Contractor DBE Certification]] showing the final DBE participation on the project including the DBEs used, the type of work performed, and the dollar amount paid to each DBE.  


::b. The local agency’s recommendation regarding the contractor’s fulfillment of the DBE requirements. The local agency shall also provide written documentation from each DBE that they were paid in full for the work identified in the Contractor DBE Certification. Examples of documentation from DBEs may include a letter, e-mail, lien waiver or copies of reimbursement checks. If DBE goals were not met, include documentation as to why.  
::b. The local agency’s recommendation regarding the contractor’s fulfillment of the DBE requirements. The local agency shall also provide written documentation from each DBE that they were paid in full for the work identified in the Contractor DBE Certification. Examples of documentation from DBEs may include a [[media:136.11.20.docx|letter]], e-mail, [[media:136.11.21.docx|lien waiver]] or copies of reimbursement checks. If DBE goals were not met, include documentation as to why.  


:5. Final Invoice  
:5. Final Invoice  
Line 452: Line 504:
:7. [[media:136.11.10.doc|Fig. 136.11.10 Contractor's Affidavit Regarding Settlement of Claims]]  
:7. [[media:136.11.10.doc|Fig. 136.11.10 Contractor's Affidavit Regarding Settlement of Claims]]  


:8. [[media:136.11.2.doc|Final Change Order]] (if needed)  
:8. [[media:136.11.2.xlsx|Final Change Order]] (if needed)  


:9. [[media:136.11.11.doc|Fig. 136.11.11 Affidavit (Compliance with Prevailing Wage Law)]]
:9. [[media:136.11.11.doc|Fig. 136.11.11 Affidavit (Compliance with Prevailing Wage Law)]] from the prime and subcontractors


These documents are to be received within 60 days of the Final Inspection date. Final Reimbursement will be processed once all close out documentation has been reviewed and accepted.
These documents are to be received within 60 days of the Final Inspection date. Final Reimbursement will be processed once all close out documentation has been reviewed and accepted.
Line 460: Line 512:
==136.11.21 Guidance for MoDOT Oversight==
==136.11.21 Guidance for MoDOT Oversight==


The [http://www.modot.org/business/manuals/LPAContacts.htm MoDOT district representative] shall periodically review the local project to verify that project administration procedures are adequate.  A [http://library.modot.mo.gov/RDT/LPA/cy10/LPASiteVisitChecklist.pdf LPA Site Visit Checklist] has been formulated to be used as a guide when visiting a LPA Site.  The checklist covers a wide range of details related to project administration and should be used as a guide by the LPA. The MoDOT review shall cover as many of the areas as possible and notations made regarding the project visits.  A diary entry shall be made by the MoDOT reviewer to document the project visit. Observations from the project and noted items from the LPA Site Visit Checklist should be included in the diary entry.  Any actual documents used or obtained during a site visit shall also be retained by the MoDOT district representative for three (3) years past the final reimbursement for the project by FHWA.
The [https://www.modot.org/about-lpacontact-us MoDOT district representative] shall periodically review the local project to verify that project administration procedures are adequate.  A [[media:136.11.12.doc|LPA Site Visit Checklist]] has been formulated to be used as a guide when visiting a LPA Site.  The checklist covers a wide range of details related to project administration and should be used as a guide by the LPA. The MoDOT review shall cover as many of the areas as possible and notations made regarding the project visits.  A diary entry shall be made by the MoDOT reviewer to document the project visit. Observations from the project and noted items from the LPA Site Visit Checklist should be included in the diary entry.  Any actual documents used or obtained during a site visit shall also be retained by the MoDOT district representative for three (3) years past the final reimbursement for the project by FHWA.


The frequency of the site visits will be at the discretion of the MoDOT district representative and the adequacy of the LPA’s administration.  At least one visit and review at the beginning of the project and near the end of the project shall be conducted.  If any deficiencies are sited or further assistance is required by the LPA more visits are warranted.       
The frequency of the site visits will be at the discretion of the MoDOT district representative and the adequacy of the LPA’s administration.  At least one visit and review at the beginning of the project and near the end of the project shall be conducted.  If any deficiencies are sited or further assistance is required by the LPA more visits are warranted.       

Latest revision as of 12:37, 2 December 2024

This article is intended as a guide to Local Public Agencys (LPAs) to ensure federal-aid project requirements are met while administering the construction of and corresponding documentation required of a typical LPA project. No work is to be initiated on any part of the project until federal funding has been approved (obligated) by FHWA and the local agency has been notified by MoDOT to proceed.

Figures
Fig. 136.3.18, Construction Reimbursement Form
Fig. 136.11.1, General Guidelines for LPA Preconstruction Conference
Fig. 136.11.2, Change Order Form
Fig. 136.11.3, Progress Report
Fig. 136.11.4, Request for Approval of Subcontract
Fig. 136.11.5, DBE Subcontract Worksheet
Fig. 136.11.6, Subcontractor Certification Regarding Affirmative Action
Fig. 136.11.7, Wage Rate Interview (Labor Compliance/EEO)
Fig. 136.11.8, Form FHWA-1391
Fig. 136.11.9, Contractor DBE Certification
Fig. 136.11.10, Contractor’s Affidavit Regarding Settlement of Claims
Fig. 136.11.11, Affidavit (Compliance with Prevailing Wage Law)
Fig. 136.11.12, Site Visit Checklist
Fig. 136.11.13, Job Bulletin Board Checklist
Fig. 136.11.14, Construction Invoice Example 1
Fig. 136.11.15, Construction Invoice Example 2
Fig. 136.11.18, LPA Final Inspection Letter
Fig. 136.11.19, LPA Final List of Acceptance Testers
Fig. 136.11.20, LPA DBE Certification Letter
Fig. 136.11.21, LPA Vendor Lien Waiver
Fig. 136.11.22, LPA Final Acceptance Checklist
Fig. 136.11.23, LPA Semi-Final Inspection Checklist (Form C-236 LPA)
Fig. 136.11.24, LPA Final Acceptance Report (Form C-239 LPA)
Commercially Useful Function (CUF) Determination Form
Off-Systems Guide Schedule for Federal-Aid Acceptance Sampling & Testing (FAST)
"How To" PowerPoint Tutorials
How to Develop and Use the Daily Diary and Payment Diary for LPA Inspectors
How to Complete a Change Order and Get it Approved
How to Close Out a Federal Aid Construction Project
Federal-Aid Essential Videos
Project Construction and Contract Administration
Civil Rights
Brochure
Buy America Requirements for the Federal-Aid Construction Program

136.11.1 Project Oversight

The LPA shall have a person in "responsible charge" (RC) of the administration of the project including construction inspection. This person must be an employee or a paid elected official of the local agency who is accountable for the project. If a consultant is hired to oversee the project the RC should be available at all times to respond to any issues on the project. The RC or designated consultant should have the necessary experience, training and knowledge to ensure that project construction and administration follows all requirements as described in the project documents and standard practice. The RC will be the primary contact for MoDOT regarding any contract administration issues.

All items of work on the project shall be inspected. Major items of work such as bridge deck pouring, paving or other high cost or critical items may require more attention than other minor items of work. MoDOT’s Engineering Policy Guide or MoDOT district representatives are good sources for tools to adequately administer the project.

136.11.2 Work by LPA Forces

The LPA may elect, with MoDOT and FHWA approval, to perform work with its own forces (see EPG 136.3.12 Federal-aid Participation for Local Work for more information), if done so they will not need to comply with the labor records, postings, payroll checking, interviews, and Davis-Bacon minimum prevailing wages requirements. However, it will be necessary for the LPA to comply with the provisions of Form PR-1273, Required Federal-Aid Provisions - All Federal-Aid Construction Contracts, Section II - Equal Opportunity, and Section III - Non-segregated Facilities. These two sections essentially require that the local agency be an “Equal Opportunity Employer.” See EPG 136.3.15 Reimbursement and Auditing for required records to support reimbursement for work performed by LPA forces.

136.11.3 Notice to Proceed

Following the concurrence of award of the contract from MoDOT, the LPA must submit executed copies of the contract to MoDOT. The district representative will review the contract for compliance and will inform the LPA that they can issue "notice to proceed" (NTP) and proceed with construction.

No work is to be initiated on any part of the project until FHWA approves (obligates) federal funding and MoDOT notifies the LPA to proceed.

A pre-construction conference must be scheduled and attended by the LPA, the contractor and MoDOT before any work begins on the project.

136.11.4 Preconstruction Conference

A preconstruction conference shall be conducted by the LPA, prior to the start of work, to ensure that all parties involved are aware of their responsibilities. Those invited to attend shall include but not be limited to representatives from the consultant (if applicable), contractor, subcontractors, utilities (if involved), local police, fire, postal, other emergency services (if necessary), any school agencies (if traffic is to be severely restricted or road closed), and MoDOT. Arrangements for and notice given of the meeting shall be completed at least one week prior to the meeting date. Fig. 136.11.1 General Guidelines for LPA Preconstruction Conference outlines this conference. Note that the initial data pertaining to the project is required within two working days after the start of work.

For projects that have specified contractor furnished borrow or require disposal of waste material off the LPA right of way, the contractor should be reminded of the requirement that the affected areas must be reviewed by DNR for environmental clearances that will include, but not be limited to the Clean Water Act, the Endangered Species Act, the National Historic Preservation Act, the Farmland Protection Act, Resource Conservation and Recovery Act, Comprehensive Environmental Response, Compensation, and Liability Act and RSMo Chapter 194, Section 194.400 Unmarked Human Burial Sites. A copy of the correspondence from these agencies should be filed with the MoDOT district representative. More information on contractor furnished borrow and waste sites can be found in EPG 136.6 Environmental and Cultural Requirements. Failure to comply with this requirement can cause loss of federal funding.

If ADA improvements are included within the project, then the ADA Checklist, (PDF version of Fig. 136.9.4) (or the MS Word version of the ADA Checklist, Fig. 136.9.4) should be included in the discussion.

Initial Data from LPA

Within two working days after the start of work, the LPA shall furnish a letter to MoDOT containing the following information:

1. Project identification;
2. Contractor’s name and address;
3. Construction Inspector’s name, address, and phone number;
4. Name of full-time employee of agency to be in "responsible charge" of project, including projects with consultant services (23 CFR 635.105). "Responsible charge" means:
a. Aware of day-to-day operations on the project
b. Aware of and involved in decisions about changed conditions that require change orders
c. Aware of qualifications, assignments, performance of consultant staff at all stages of the project
d. Visiting the project on a frequency that is commensurate with the magnitude & complexity of the project
5. Name, address, and telephone number of local agency’s consultant, if applicable;
6. Date of construction engineering contract approval;
7. Date of notice to proceed;
8. Completion date or working days;
9. Amount of contract;
10. Location and description of work;
11. Date of letting;
12. Date of award;
13. Date of preconstruction conference;
14. Date on which work actually started; and
15. Summary of Disadvantaged Business Enterprise (DBE) intent.

136.11.5 Subcontracts

Federal-aid contracts require that no less than 30% of the contract work shall be performed by the prime contractor’s own forces and equipment. All contracts shall further hold to the right of approval of any subcontracts prior to performance of subcontract work. The local agency is responsible for assuring the proposed subcontractors are both qualified to perform the proposed items of work and legally bound to comply with all the requirements of the contract as they would apply to the prime contractor, for example, wage rates, equal employment opportunity regulations, submittal of payrolls, etc.

The LPA shall furnish the MoDOT representative the name and address of each subcontractor, the percentage of work sublet to that particular subcontractor, the percentages awarded to DBEs, and the total percentage of work sublet to date. DBEs must be on the MoDOT-approved listing at the time of letting. Subcontract approval forms (Fig. 136.11.4, Fig. 136.11.5 and Fig. 136.11.6) must be used for submitting subcontractor information. FHWA 1273, Required Federal Contract Provisions, is included in all federal aid contracts, and it is the prime contractor’s responsibility to ensure that all subcontract agreements also include a copy of FHWA 1273. The reviewer should perform a random check on the submitted subcontract agreements to help ensure the prime is meeting this requirement.

Upon approval from the prime contractor, subcontractors may sublet a portion of their assigned work to another subcontractor. This relationship is called “2nd tier subcontracting”. A separate Fig.136.11.4, Request for Approval of Subcontract, submitted by the prime, is required for 2nd tier subcontract requests. The contractor shall disclose the name of the 1st tier subcontractor on the form.

The Request for Approval of Subcontract for the 1st tier subcontractor should list all of the work items they plan to perform, as well as all work they plan to sublet to their second tier subcontractors. The quantity and unit price for each line shall be that designated in the subcontract agreement between the prime contractor and the first tier subcontractor. The Request for Approval of Subcontract for the 2nd tier subcontract work lists only the work the 2nd tier sub will perform, and shows the quantity and price from the subcontract agreement between the 1st and 2nd tier subcontractors.

136.11.6 Information Posters

The contracts for highway construction projects require certain information to be conspicuously displayed on the project where employees regularly congregate in preparation for the day’s work. The RC or a delegated representative is to conduct inspections of the bulletin boards. The first inspection should occur when employees begin work on the project. After the initial review, inspections should be conducted every other month until the project is completed to ensure the bulletin board is in good condition and still displays the required posters. The list of required information to be posted both on the project and in the project office is located in EPG 110.2. Many of the posters can be downloaded from MoDOT’s internet contractor resources website. A checklist of the job bulletin board posters is also available. All posters shall be completed as required, showing names and telephone numbers where indicated. For more information on the Federal Davis-Bacon prevailing wage rates see EPG 136.9.4.1.1.10.1 Federal Wage Rates.

136.11.7 Equal Employment Opportunity Requirements

The EEO requirements (41 CFR 60.1) and (41 CFR 60.2) are contained in the contract. The local agency should be familiar with and enforce those requirements.

The LPA shall furnish the name of the contractor or subcontractor whose contract or subcontract is $10,000.00 or more and must submit Federal-Aid Highway Construction Contractors Annual EEO Report, Fig. 136.11.8, Form FHWA-1391, to the MoDOT External Civil Rights Division. Employment data should total correctly on this report.

If a contractor or subcontractor has been active on a project but no work was performed during the above payroll report period, a “No Work Was Performed” report is to be submitted. If a project has not started, no report is required.

136.11.8 Disadvantaged Business Enterprise (DBE)

Disadvantaged Business Enterprise (DBE) requirements are also covered in EPG 146 Disadvantaged Business Enterprise (DBE). DBE compliance consists of ensuring that the prime contractors utilize DBEs as indicated in their good faith effort. These vendors will be a combination of subcontractors working on the project, suppliers, brokers, and trucking companies. DBE vendors must be on the MoDOT-approved MRCC listing at the bid opening. After the contract is awarded, the contractors should provide a Request to Subcontract Work form for each subcontractor noting the DBE/non-DBE classification. If a subcontractor is added to the project, they need to be pre-approved by MoDOT prior to performing any work. The LPA should track the DBE progress throughout the project to ensure the goal is met. In calculating the percentage of the contract work performed, all prices for sublet work shall be at contract unit bid prices. Sample forms (Fig. 136.11.4 and Fig. 136.11.5) may be used for submitting subcontractor information and instructions for completing the form (Fig. 136.11.6) are available. If there is a concern during the project, contact the External Civil Rights Division. The prime contractor and LPA should ensure that the DBE vendors used to achieve the goal are performing a Commercially Useful Function (CUF).

136.11.9 Commercially Useful Function (CUF)

Commercially Useful Function (CUF) basically consists of checking that the DBE vendor performs the work, supplies the material, has its own labor, and controls its work. The RC or delegated representative shall conduct at least one CUF interview using the CUF Determination form for each DBE vendor on the project. Additional interviews shall occur if the inspector notices a change in the DBE vendor or prime contractors operations. The verification for CUF varies depending on the capacity the DBE vendor is being used. See EPG 146.3 for a detailed description of what constitutes a check for CUF for various DBE uses. Please review the common red flags found on CUF reviews.

136.11.10 On-the-job Training (OJT)

On-the-job Training (OJT) requirements are also covered in EPG 136.9.4.1.1.16 On the Job Training. All training goals are established by the MoDOT External Civil Rights (ECR) Division prior to letting.

Prior to the notice to proceed, the contractor shall submit the Trainee Notification form to the RC or delegated representative. They will then forward the notification to MoDOT ECR Division for approval of the proposed trainee(s). This process will be repeated if a trainee is added anytime during the project.

In addition to the trainee notification form, the contractor must submit monthly trainee reports throughout the course of the training and the trainee completion form. The final trainee summary shall be completed at the end of the project or when the trainee goal on the project has been achieved. These forms shall also be submitted to the RC or delegated representative. The LPA will then forward the notification to MoDOT ECR Division for approval. The monthly trainee reports will be verified by the RC or delegated representative against the certified payroll for accuracy and then forwarded to MoDOT ECR Division.

For further information and guidance about the OJT program and the submittal forms, you may access the ECR website or call (573) 751-2978.

136.11.11 Value Engineering Change Proposals

Value engineering change proposals (VECP) are meant to provide a product of equal or improved quality that will reduce the project cost, improve safety or decrease the time required to complete the project. See Sec 104.6 and EPG 130.2 for guidelines on contractor proposals for value engineering. A VECP must be approved by the contractor, consultant engineer (if applicable), LPA, MoDOT and FHWA (if applicable).

136.11.12 Construction Administration

136.11.12.1 Consultant Conflict of Interest

Under 23 CFR 1.33, neither a consulting engineering firm, nor any of its employees, that is providing engineering and inspection services for the contracting agency shall be allowed to perform work that is the construction contractor's responsibility.

It is unacceptable for a consultant to provide both project engineering services for the LPA and engineering services for the project construction contractor. Operating under this arrangement gives the appearance of a possible conflict of interest and is not allowed for federal-aid work, although, surveying will be permitted.

136.11.12.2 Construction Engineering Expectations

The local agency is the main contact for the contractor and is responsible for overseeing the construction activities, which include the day-to-day review and inspection of the project construction activities and the record keeping necessary for documentation. The local agency shall also have a qualified inspector on the project site. The inspector must verify that work performed and materials incorporated are as specified in the contract documents and that the project is built in accordance with approved plans and specifications and that quantities are documented sufficiently to make payments for completed work. At a minimum, the inspector must be present on the job site during critical construction operations including, but not limited to:

  • structure layout
  • excavation and backfilling
  • driving pile
  • checking of reinforcing steel prior to concrete placement
  • concrete batching and pouring
  • placement of girders
  • placement of surfacing materials

ALL material incorporated into a project MUST be inspected and documented or the federal funds on the project will be jeopardized.

136.11.13 Documentation Requirements

All costs incurred by the local agency for which federal reimbursement is sought must be supported by original source documents or documentation that provides adequate assurance the quantities of completed work were determined accurately and on a uniform basis. The primary source of administration information is found in two basic sources, the project inspector’s diary and payment diary. These diaries are the primary documents used to verify construction progress and payment and may become a crucial element if any disputes or issues arise on the project.

Diaries are essential to provide a description of day-to-day activities that occurred on the project, valuable quality control information and historical information of how the project was constructed. As such, the diary is a document focusing on critical project information and used as a communication tool to assist in explaining what the contractor did that day and what took place on the job site. By completing a diary, this provides assurances to MoDOT, taxpayers and FHWA there was compliance and quality control on the project. The diary serves as the primary source of information to ensure pay quantities were measured and paid for accordingly. It should also summarize the labor, material, equipment, work accomplished and other events that affect or explain the contractors progress. The diary then becomes a factual, historical document used to review project compliance, contractor claims or dispute resolution, and serves as the project documentation during an audit.

Diaries are written such that they are:

1. Clear; including handwriting and meaning. Refrain from words such as they, he, she. Instead use specific names of individuals.
2. Concise; use minimum number of words and be factual
3. Correct; numerous corrected errors give impression of quality of work
4. Complete; include all information needed to be clear. Document as if describing to someone unfamiliar with the project. Include items such as activities and testing that took place, the result of those activities and tests and any action taken from those results.
5. Concurrent; document as the events happen, not after. Waiting too long to document makes it easy to forget the specifics.

Samples of documentation may be obtained from the district MoDOT representative.

136.11.13.1 Project Diaries

Diaries and field books can be handwritten, bound documents or electronic and part of electronic construction management software systems. Diaries must be accurate, well-documented and completed in a timely manner, whether that be as the day progresses, at the end of the day or no later than the next day.

Handwritten diaries shall be completed in ink in securely bound, high-grade field books. Any corrections shall be made by lining out the entry, initialing and dating. Do not use erasures or correction fluids to make changes.

If electronic systems are used, a secure back up shall be maintained. Any electronically generated diaries must be kept in a software system which meets the following criteria:

1. Contract administrator(s) shall not have the capability of deleting any diary information
2. Any changes to diary entries shall be documented with
a. Previous entry
b. Corrected entry
c. Name or initials of person making the correction
d. Date of correction
e. Reason for correction.

It is the LPA’s responsibility to ensure electronic diary system meets these requirements. MoDOT / FHWA may review electronic diaries during any project review or site visit. If it is determined changes to diary entries were deleted or in any other way compromised, the LPA will be at risk of losing all federal funding for the project.

The project diary is completed daily, even if no work occurs, and includes the following:

  • Facts only, no opinions
  • Date
  • Weather including statements related to whether conditions are suitable for construction progress and any delays due to weather. If not working due to weather, make such notation for the day.
  • Progress of work as a percentage; suggested as a bar chart in a suitable scale to indicate the percentage of work completed to date
  • Pay item documentation including work by local forces
  • Instructions to contractor
  • Unusual occurrences effecting project activities
  • Determination of physical condition of work performed, i.e. temporary traffic control items, erosion control items
  • Documentation of tests performed and test results
  • Contractor work hours
  • Completion of check lists
  • Objective remarks of end product
  • Visitors and communication on the project site
  • Labor, equipment and material on site including usage, delays, breakdowns, idle time, inefficiencies, work accomplished and other events that affect or explain contractor progress. If not working due to materials shortages, equipment breakdowns, rejected material, etc., make note of such.
  • Number of employees in each trade and each employee matched with their item of work and equipment including any specific to DBE
  • Signature of inspector completing the diary
  • If a working day contract, the running total of contract time charged and reasons for days credited.
  • Examples of noted events for the day are recommended to include:
• Status of project Traffic Control Operations including any changes made to the traffic control plan
• Status of project’s erosion control including any changes made to the erosion control plan
• Work or materials rejected and reasons why
• Length and cause of any delay
• Unusual conditions and effect on job; including any crashes that occurred in the work zone
• Visitors to the project site
• Other inspector action, e.g. note wage interviews, DBE compliance checks, major material status, etc.

For more information on federal requirements and guidelines, see the FHWA – Construction Contract Administration webpage or scroll down on MoDOT's LPA website to locate an online NHI training course on Daily Diaries.

136.11.13.2 Payment Diaries

The following information shall be recorded neatly and clearly in the payment diary:

  • Date
  • Inspectors signature or initials
  • Location of the installed work indicated by stations, log miles or location-based reference. Pictures are also a good documentation source.
  • Quantity of work installed on that day.
  • Running total of that item of work.
  • Any pertinent calculations or measurements including charge orders, extra work or work by local forces.
  • Material received and approved (or rejected and reasoning).
  • Receipt of materials certification.
  • Notes related to how total compares to plan quantity.
  • If material allowances are used, they must not exceed the estimated quantities required by the job nor the test reports or certifications. Care must also be taken to reduce the material allowance, as the material is paid-in-place. The invoice must be marked paid by the supplier. Being marked paid by the contractor is not allowed.
  • For lump sum items and excavations, an estimated percentage of completed work shall be placed in the summary. Documentation for payment shall be shown in the project diary entries as the work is being accomplished.

136.11.13.3 Invoices

The LPA must submit invoices to MoDOT for reimbursement of costs contained in the agreements and contracts as they are incurred. The invoices may not be submitted more than once every two weeks. Progress invoices must be submitted monthly. The final invoice must be submitted within 30 days of final acceptance. See Figure 136.3.18 for Construction Invoice templates. For detailed information on the procedures to be followed, see EPG 136.3.15 Reimbursement and Auditing. In addition, Fig. 136.11.14 and Fig 136.11.15 are completed construction invoices that can be used as examples when preparing a construction invoice for reimbursement.

136.11.13.4 Erosion Control

The LPA shall ensure the land disturbance site is inspected on a regular schedule and within a reasonable time period (not to exceed 48 hours) following a runoff event. Regularly scheduled inspections (recommend using MoDOT's Land Disturbance Inspection Record) shall be conducted at a minimum of once every seven days. For disturbed areas where permanent ground cover has not been established, all installed BMPs and other pollution control measures shall be inspected for proper installation, operation and maintenance.

Locations where storm water leaves the site shall be inspected for evidence of erosion or sediment deposition. Any deficiencies noted during a weekly inspection shall be corrected within seven calendar days of that inspection. The results of the weekly inspections in a given month shall be recorded in that month’s report. The inspector shall promptly notify the site contractors responsible for operation and maintenance of BMPs of the deficiencies. See EPG 806.7 Construction Inspection Guidance for Sec. 806 and EPG 203.1 Borrow for more information regarding storm water and erosion control requirements.

A log of each inspection shall be kept. The inspection report is to include the following minimum information: inspector’s name, date of inspection, observations relative to the effectiveness of the BMPs, actions taken or necessary to correct deficiencies, and listing of areas where land disturbance operations have permanently or temporarily stopped. The inspection report shall be signed by the inspector.

The LPA shall at all times ensure that all pollution control measures and systems are in good order to achieve compliance with the terms of the general permit.

136.11.13.5 American’s with Disabilities Act (ADA) Checklist

Pedestrian facilities must be accessible to all people to the maximum extent feasible in accordance with Title II of the Americans with Disabilities Act of 1990 (ADA). For detailed information and criteria see EPG 642 Pedestrian Facilities.

Prior to or during the final inspection, the MoDOT district representative will utilize the ADA Checklist, (PDF version of Fig. 136.9.4) (or the MS Word version of the ADA Checklist, Fig. 136.9.4), to verify the project has been constructed to meet the current ADA requirements. Providing the checklist to the contractor at the preconstruction conference is considered a best practice.

136.11.13.6 Progress Reports

The LPA shall submit a copy of a monthly report to the MoDOT district representative stating the progress of the work. Fig. 136.11.3 provides the Progress Report format. The LPA may elect to summarize construction activities for the project on a weekly basis and consolidate them into the monthly report.

136.11.13.7 Document Retention

The MoDOT district or FHWA representative may review daily diaries and payment diaries on the project site at any time. The LPA shall maintain all books, documents, papers, accounting records and other evidence pertaining to the costs incurred. Such materials shall be available at the LPA’s office for inspection by MoDOT, FHWA or their authorized representatives at all reasonable times during the contract period and for (3) three years after the date on which the local agency receives reimbursement of its final invoice from MoDOT, and copies thereof shall be furnished if requested.

136.11.14 Labor

Missouri and federal law requires minimum wage rates (pay) for the various skilled trades. These wage rates are specified in the contract at the time of bidding and are enforced by MoDOT, the LPA, and the MO Department of Labor during the construction of the project. For more information on the Federal Davis-Bacon prevailing wage rates see EPG 136.9.4.1.1.10.1 Federal Wage Rates.

136.11.14.1 Labor Records

The LPA shall obtain payrolls and forms related to Equal Employment Opportunity (41 CFR 60.1) and (41 CFR 60.2). They shall also ascertain that necessary posters (see EPG 136.11.13 Documentation Requirements) are in place on the project.

A certified copy of each weekly payroll must be submitted by the prime contractor within 7 days of the payment date of the payroll. The certification may be attached to the payroll or may be on the payroll itself. The prime contractor will be responsible for the submittal of payrolls and certifications for all subcontractors on the project. In the event that work is temporarily suspended, the last payroll shall be marked appropriately to note that it will be the last payroll until work is resumed.

Payrolls to be submitted shall be checked for compliance with the contract requirements. The local agency shall retain all payrolls for a period of three years after the date on which the local agency receives reimbursement of its final invoice from MoDOT, during which time they shall be open to inspection by MoDOT and/or FHWA.

The LPA shall check payrolls, with the following checks being made to ensure proper labor compliance:

1. The employee’s full name, identifying number (such as last four digits of Social Security Number) and complete address, including zip code, must appear on each payroll. For projects that are only state-funded projects, addresses will be required to be placed on certified payrolls. For federal-aid projects, placing addresses on the payrolls will be optional. The contractor is no longer allowed to include complete Social Security numbers on certified payrolls for projects let after January 18, 2009. In lieu of the Social Security number, the contractor must assign the employee an identification number and place that identification number on the certified payroll. This identification number can be the last four digits of the employee's Social Security number. For those projects that were let prior to January 18, 2009 the contractor must still provide Social Security numbers and addresses on certified payrolls.
2. Check the payroll for correct employee classification.
a. Check to assure each employee has a classification.
b. Make sure classifications are correct as related to the type of work the company has subcontracted.
c. Employees enrolled in the MoDOT training program must be shown on the payroll in the classification they are enrolled in as trainee. (i.e. Crane Operator Trainee, Carpenter, Laborer, etc.)
d. When possible, confirm that employees are classified correctly as to what type work they are performing by using the interview process, jobsite visits, and communication with the inspectors, and by reviewing the Inspector’s Daily Report of Construction.
e. Foremen or supervisors who perform 20% or less of the day with the tools of the trade are exempt from the Davis Bacon Act. They must appear on the payroll as "foreman" or "supervisor" with a breakdown of hours per day and total hours and, since hourly wage rates are not required, they can be listed under Salary Agreement.
f. Foremen or supervisors who work with tools of the trade more than 20% of the day are not entitled to an exemption under the Davis Bacon Act. Thus, if the hourly wage rate is the same for both classifications the employee will be listed on the payroll to show both classifications in which they performed (i.e. Foreman/Carpenter), hours per day listed along with an hourly wage rate, gross amount earned, deductions and net wages paid. But, if the hourly wage rate is not the same for both classifications then multiple listings for the employee shall be included on the payroll to show each classification of work performed in each day along with all the appropriate information.
3. Check the payroll for correct hourly wage and, where applicable, the correct overtime hourly rate.
a. Check employee’s rate of pay against the state and federal wage rates, where applicable, to make sure the employee is receiving at least the minimum for the individual's classification as per the prevailing wage schedule in the contract. For federally funded projects the rate of pay is the highest of either the federal or state wage rates.
b. Make sure fringe benefit amount plus base pay amount matches or exceeds the designated fringe benefit amount plus designated base pay amount from the applicable wage order. For example, the base pay amount could be less than that designated as the prevailing wage, if the fringe benefit amount is more than that designated, and the two together meet or exceed the designated gross prevailing wage. The contractor should be encouraged to list the exact fringe paid for each employee on the payroll. If the contractor chooses to certify that the fringe benefits are being paid to approved plans, funds, or programs, the contractor shall provide documentation that the correct payment amount is being paid to the fund for the individual employees.
Check the daily and weekly hours worked in each classification including actual overtime hours worked (not adjusted hours).
4. All deductions shall be listed and the net wage shown. The Form WH-347 is to be used where fringe benefits are paid into established programs. However, if fringe benefits are paid in cash to the employee, the amount shall be indicated on the payroll and noted on the statement of compliance.
a. All deductions must be identified. If a deduction of “other” is listed on the payroll it must be explained on the statement of compliance.
b. Some typical deductions include
1) State or federal taxes
2) Voluntary insurance, pension, and/or retirement plans
3) Child support and other payments ordered by a court (but not payments to the employer)
4) Prepaid wages
5) Payments to charitable organizations
6) Union dues when agreed to by the union (fines are not allowable)
c. All deductions must be an approved deduction. (If not on the approved list above, documentation giving employee’s permission for the deduction must be on file.)
d. Non-standard deductions can be approved by the Division of Labor on a yearly basis. The contractor must provide documentation along with the payroll when any approved non-standard deductions are in use.
5. To assure that the payrolls are arithmetically correct, approximately 10% of the extensions on the first three payrolls shall be checked. The contractor is to be advised of any violations noted on the labor payroll. All the errors are to be corrected by means of a supplementary payroll.
6. All checking by the local agency shall be initialed by the checker.
7. Final payrolls shall be marked “Final” or “Last Payroll.”
8. The local agency is to maintain a secure record of all payrolls.

The prime contractor and each subcontractor are required to submit a weekly statement of compliance within seven days of the payment date of each payroll period. This statement must be signed by the contractor, subcontractor, or their agent who pays or supervises the payment of persons employed under the contract and shall certify that the payroll for the pay period contains the information required and that such information is correct and complete, Form WH-347, is to be submitted in the prescribed form as set out in the “Required Contract Provisions” included in the contract. The local agency is to maintain a secure record of all statements. This Form WH-347 is available to contractors from the Superintendent of Documents, Government Printing Office, Washington, D.C. 20402.

136.11.14.2 Labor Interviews

LPA personnel are to conduct one wage rate interview on each project every two weeks. Labor interviews are not required on railroad and other utility adjustments. The interviewer shall determine the employee’s name, the classification of the employee, the actual wage paid, and the posted wage rate. Interviews shall be documented as shown on form, Fig. 136.11.5 Wage Rate Interview (Labor Compliance/EEO).

The LPA shall submit a semi-annual report to the MoDOT district representative containing the following information:

1. Number of contractors or subcontractors against whom complaints were received
2. Number of investigations completed (if complaints were received)
3. Number of contractors or subcontractors found in violation
4. Amount of restitution due under:
a. Davis-Bacon and Related Acts
b. Work Hours Act of 1962
(The Davis-Bacon Act encompasses prevailing wage rate violations, whereas the Contract Work Hours Act encompasses daily and weekly overtime violations.)
5. Number of employees due wage restitution under Davis-Bacon and related Acts and/or Work Hours Act of 1962
6. Amount of liquidated damages assessed under Work Hours Act of 1962

The above report is due not later than April 4 for the period from October 1 to March 31 and not later than October 5 for the period from April 1 to September 30. This report shall include all information gathered on all projects.

136.11.15 Change Orders

A change order is a supplement to the contract. It is prepared to provide authority to pay for revisions in quantities and to authorize changes in scope of work, schedule, design concept or specifications. Changes in scope should be limited to the original intent, purpose and limits (length and width) of the job.

136.11.15.1 Change Order Documentation

Change orders should be documented on the MoDOT change order report form (Fig. 136.11.2) and be identified by the Federal-aid project number, if applicable. The LPA representative writing the change order should use brief, accurate and complete reasons for the contract changes. The reasons should include construction facts; such as utility locations, incorrect shrinkage factors, plan sheet errors, excessive erosion, etc.; rather than general statements that merely state quantities vary. Change order items should be listed in the same order as they appear in the contract. No combination of items will be permitted. Controlling specifications should be checked carefully to establish the LPA’s responsibility for payment. Change orders are to be numbered consecutively per contract.

If the change order includes a contingent item for which the method of payment is not established by the contract specifications, a detail of all work covered by that item and the supplemental specification covering construction of that item must be shown including description, materials, construction requirements, method of measurement and basis of payment. References to the contract specifications may be used when applicable.

  • If a contingent item price can be agreed upon between the LPA and the contractor then the substantiating data shall be attached to show how the price was determined including an independent estimate of cost by the LPA.
  • If a contingent item price cannot be agreed upon between the LPA and the contractor and the work has to be performed under force account, then the unit price will consist of the actual local agency or contractor material, labor and equipment costs in accordance with EPG 136.3.15 Reimbursement and Auditing. The unit price should be shown as 1.00 and the units to be constructed would be the estimated cost.

Supplemental information necessary to document the change order should be attached to the change order. The attachments should include the contract number and change order number. A clear description or drawing can expedite processing the change order.

Additional engineering and/or resulting construction costs due to design errors and omissions, resulting in a re-design, are not eligible for federal participation. Participation in added project costs resulting from re-design or plan changes can only be considered in cases where it can definitely be established that the changes were the result of unforeseen site conditions or other causes that would not reasonably be under the control of the LPA or its engineer.

Contract time extensions granted by the local agency which affect project costs or liquidated damages must be fully justified and adequately documented. The local agency will be liable for any liquidated damages for time extensions granted by them and not approved by MoDOT. Under these conditions, the money value of the damages will be deducted from money due the LPA.

The final change order is used to convert quantities to final status as determined at completion of the project. The final change order should be completed within 45 days of Final Inspection. If no final change order is necessary due to all quantities being updated to final status by previous change order, a statement to that effect should be included in the final plans submittal letter.

136.11.15.2 Change Order Approval

Change orders must have approval from the LPA, consultant (if applicable), MoDOT and the FHWA (if applicable) before the work is started. Exceptions are granted for routine or minor changes, or emergency revisions for which verbal approval has been granted. In rare cases it may be necessary to proceed with emergency measures without prior approval. In such cases verbal approval should be sought from the authorizing parties as soon as practicable. Indicate in the diary or letter of transmittal the name of the individual who provided that verbal approval.

The contractor's signature should also be requested on change orders. If the contractor refuses to sign the change order, it should be documented and this documentation included with the change order when submitted to the authorizing parties.

Change orders must be submitted as soon as practicable if they involve contingent items or changes in design features so that approval or rejection will be made before plans to perform the work materialize. Change orders covering overruns or underruns should be submitted promptly since they affect the contractor's monthly payment estimate.

Any electronic copy with digital signatures is considered official however the primary copy should be immediately saved to a protected location with at least one back up. When the contractor’s digitally signed copy is returned it should be saved over the primary copy and further digital signatures, if necessary, should be encoded to that primary copy.

If paper is used, regardless of the approval level, the local agency will produce a total of two copies of change order. The LPA will forward both copies of change order to the contractor for signature. The contractor will sign and return one, and keep the other. The original signed change order will be retained by the LPA for 3 years after final settlement.

There are three levels of change order approval:

Change Order Level 1 is approved in documentation, by the contractor, consulting engineer (if applicable), the LPA and by the MoDOT district representative. Level 1 conditions include:

1. Any no-cost change orders (used when the direct substitution of a particular line item with a contingent item does not generate an additional cost or cost reduction).
2. Any change in a contract or contingency item less than $5,000.
Examples of a Level 1 change order are available.

Change Order Level 2 is approved, in documentation, by all listed in Change Order Level 1 and the FHWA on projects designated for federal involvement for change orders on the PODI Matrix. Level 2 conditions include:

1. Final change orders
2. Any change in a contract item or contingency item from $5,000 to $50,000.
3. Any new contingency item from $5,000 to $50,000.
4. Any specification change.
5. Any revision in a contract unit price.
6. Any change in a major line item greater than 25% from the original contract amount for that line item (in dollars).
7. Any change of the contract amount greater than 25% of the original contract bid amount (also in dollars).
8. Any change in design concept.
9. Any change order not approved by the contractor.
10. Any change order for adjustments due to differing site conditions or significant changes in the character of the work.
11. All value engineering change orders regardless of cost.
12. Any change order granting a time extension.

Change Order Level 3 is approved in documentation, by all listed in Change Order Level 2 and MoDOT’s State Construction and Materials Engineer. Level 3 conditions include:

1. Any change in a contract or contingency item greater than $50,000.
2. Any new contingency item greater than $50,000.
3. Additions greater than 50% of the original contract amount
4. Additions greater than $50,000.

136.11.16 Dispute and Claim Resolution

Occasional Escalation of an Issue – Conflicts are inevitable in any human endeavor. Key players should be encouraged to escalate to the next level of management any issues they are unable to resolve themselves. Escalation saves time and money and may prevent the stakeholders from taking a rigid position and thus keep a relatively minor issue from becoming a claim. Most importantly, escalation of an issue may preserve the working relationship of the key players.

Development of an Issue Resolution Process – The key players should design their own systems for resolving issues on the project. Specific teams composed of personnel from the various stakeholders, who are knowledgeable about their particular technical portions of the contract, discuss potential problems and the way they would like to see them handled. They decide how issues that are not resolved at their level will be escalated to the next level in a timely fashion so that the decision-making process becomes more efficient and costly delays are avoided.

Contractor Claims – In the event of a claim, contact your MoDOT representative. If federal-aid participation is desired in a contract claim payment, early and often coordination is necessary between FHWA, MoDOT and the LPA.

136.11.17 Materials

Testing and certification are necessary for all material incorporated into an LPA project. The testing and certification documentation must show the quantity of material being reported and whether it meets the specifications. . All materials in a Federal-aid LPA project must comply with Buy America requirements.

136.11.17.1 Material Acceptance

Material acceptance is based on the following two types of sampling and testing:

1. Job control samples are taken and tests are conducted as work progresses to assure the project is constructed in compliance with the applicable specifications. All project sampling and testing of materials shall be performed by the LPA or by a consultant employed by the LPA. The guidelines in the Off-Systems Guide Schedule for Federal-Aid Acceptance Sampling and Testing (FAST) table should be followed as a minimum.
All technicians who perform, or are required by the FHWA to witness, such sampling and testing shall be deemed as qualified by virtue of successfully completing the requirements of EPG 106.18 Technician Certification Program, for that specific technical area. They will be identified by a certification card issued by the certifying authority. The card will note the expiration date and each certification level and must be on hand during sample and testing. Any individual who has not been qualified is not eligible to perform these functions on federal-aid projects.
Test reports or certifications are necessary for all material incorporated into the work. The test report or certification must show the quantity of material being reported and whether it meets the specifications.
Submission of job control test results to MoDOT is not required unless requested by MoDOT or the FHWA. These test results must be retained as outlined in this article.
2. Independent assurance samples and tests will be performed by MoDOT personnel in accordance with the procedures and at the frequency set forth in EPG 106.22 Material Inspection Revisions.

136.11.17.2 Material Documentation

The following material documentation shall be kept for 3 years following project acceptance.

  • The name and work area being tested for any personnel conducting materials tests for acceptance.
  • Material receipts must be retained and shall show proper reference to the job and indicate proper weight and measurements and moisture deductions when applicable. Each material ticket must be validated by both the scale inspector and the inspector at the job site. Certain small quantities are exempted from weight requirements. It is suggested that tickets be bound according to type of material and date. Each bundle would then support the entries in the field book.
  • Testing and certification reports must be retained. It is also necessary that they be received by the LPA prior to their payment to the contractor for the material represented. Certain small quantities are exempted from testing requirements. Certification and test reports shall be labeled with the number of the bid item represented and shall be kept in numerical order.

136.11.18 Final Plans

If any project involves work on state right of way or if MoDOT will be maintaining any portion of the completed improvement, the local agency shall furnish to the MoDOT district representative two complete sets of final “as built” plans. Final plans shall be submitted within 60 days of final acceptance (as defined in EPG 136.11.19 Final Acceptance) of the project.

For all bridge plans, if there are any design changes, final “as built” bridge plans shall be submitted to the MoDOT district representative.

136.11.19 Final Acceptance

Final acceptance of a project by an LPA occurs by verifying successful project completion through one or more inspections.

When the LPA and the prime contractor presume that project construction is complete, an inspection is scheduled by the LPA. The inspection party includes representatives from the LPA, MoDOT, prime contractor, and in some cases, the FHWA and subcontractor(s).

The scheduled inspection becomes the final inspection if it is determined by the inspection party that all contract items have been completed in their entirety and are of satisfactory quality. By merit of the final inspection, the project also receives final acceptance.

The scheduled inspection becomes a semi-final inspection, if it is determined by the inspection party that corrections or exceptions must be made before final acceptance.

  • Corrections are work items that affect the performance and serviceability of the project and impact road users until they are completed.
  • Exceptions are time-dependent work items that do not directly impact road users. They generally fall into one of the three following categories:
1. Establishment of soil stabilization through seeding/sodding/planting and maintenance of associated temporary erosion control measures,
2. Traffic signal test periods,
3. Lighting system test periods.

After the corrections have been successfully completed the LPA may deem the project substantially complete and halt the working/calendar day count.

After corrections and exceptions have been successfully completed, the LPA inspection party shall perform a final inspection and grant final acceptance. The LPA takes over maintenance responsibility for the project from the contractor.

Final acceptance by MoDOT occurs after the LPA has submitted all the applicable final documents (certifications) listed in EPG 136.11.20 Project Closeout Certifications. These documents are to be received within 60 days of the final inspection date. After review and acceptance of the documentation, MoDOT will issue a final acceptance report (Form C-239 LPA) and process final reimbursement to the LPA.

136.11.20 Project Closeout Certifications

Full payment of the final invoice will not be considered until the local agency has electronically furnished the following documents:

1. The LPA Semi-Final Inspection Checklist (Form C-236 LPA), that includes the listing of those who were present at the semi-final inspection. This is required for both contractor and local agency work, where applicable.
2. The LPA’s final acceptance letter showing the number of working days or calendar days charged, completion date and the amount of liquidated damages, if any.
3. A final list of acceptance testers used on the project and a certification stating
a. “The results of the tests or acceptance samples indicate that material incorporated in the construction work and the construction operations controlled by sampling and testing were in reasonably close conformity with the approved plans and specifications, and such results compare favorably with the results of independent assurance sampling and testing.” Any deviations from the specifications must be explained along with the reason for acceptance.
b. “All field tests were performed in conformity with the governing specifications and the results were in reasonably close conformity with the specifications.” Explain any deviations and why the work was accepted.
c. “The project was constructed substantially in conformity with the plans and specifications for the project.”
4. Contractor certification and local agency recommendation
a. The Fig. 136.11.9 Contractor DBE Certification showing the final DBE participation on the project including the DBEs used, the type of work performed, and the dollar amount paid to each DBE.
b. The local agency’s recommendation regarding the contractor’s fulfillment of the DBE requirements. The local agency shall also provide written documentation from each DBE that they were paid in full for the work identified in the Contractor DBE Certification. Examples of documentation from DBEs may include a letter, e-mail, lien waiver or copies of reimbursement checks. If DBE goals were not met, include documentation as to why.
5. Final Invoice
6. Final Detailed Estimate of Quantities
7. Fig. 136.11.10 Contractor's Affidavit Regarding Settlement of Claims
8. Final Change Order (if needed)
9. Fig. 136.11.11 Affidavit (Compliance with Prevailing Wage Law) from the prime and subcontractors

These documents are to be received within 60 days of the Final Inspection date. Final Reimbursement will be processed once all close out documentation has been reviewed and accepted.

136.11.21 Guidance for MoDOT Oversight

The MoDOT district representative shall periodically review the local project to verify that project administration procedures are adequate. A LPA Site Visit Checklist has been formulated to be used as a guide when visiting a LPA Site. The checklist covers a wide range of details related to project administration and should be used as a guide by the LPA. The MoDOT review shall cover as many of the areas as possible and notations made regarding the project visits. A diary entry shall be made by the MoDOT reviewer to document the project visit. Observations from the project and noted items from the LPA Site Visit Checklist should be included in the diary entry. Any actual documents used or obtained during a site visit shall also be retained by the MoDOT district representative for three (3) years past the final reimbursement for the project by FHWA.

The frequency of the site visits will be at the discretion of the MoDOT district representative and the adequacy of the LPA’s administration. At least one visit and review at the beginning of the project and near the end of the project shall be conducted. If any deficiencies are sited or further assistance is required by the LPA more visits are warranted.