- 09:2009:20, 14 August 2017 diff hist +330 m 751.50 Standard Detailing Notes →G7. Steel HP Pile: Per BR, revised and added std detailing notes for the anchorage of pile for seismic jobs
- 09:0409:04, 14 August 2017 diff hist +206 m 751.9 Bridge Seismic Design →751.9.3.1.7 T- Joint Connections: Per BR, added link to revised info about anchorage of pile for seismic jobs
- 08:5408:54, 14 August 2017 diff hist +19 m 751.36 Driven Piles →751.36.2 Steel Pile
- 08:5308:53, 14 August 2017 diff hist 0 N File:751.36.2.jpg No edit summary current
- 08:5208:52, 14 August 2017 diff hist +947 m 751.36 Driven Piles →751.36.2 Steel Pile: Per BR, revised the anchorage of pile for seismic jobs
- 07:3907:39, 14 August 2017 diff hist +318 m Category:138 Project Development Chronology added 2017 map
- 06:3806:38, 14 August 2017 diff hist 0 236.5 Property Management No edit summary
11 August 2017
- 13:4613:46, 11 August 2017 diff hist −2 m Main Page No edit summary
- 12:5212:52, 11 August 2017 diff hist +296 m 236.15 Requests from Cities for Annexations Per RW, updated links to form 39
- 12:4712:47, 11 August 2017 diff hist −1,128 m 236.11 Mediation Per RW, updated links to forms
- 11:4911:49, 11 August 2017 diff hist −12,818 m 236.7 Negotiation Per RW, updated links to forms
- 10:2910:29, 11 August 2017 diff hist −3,848 m 236.6 Appraisal and Appraisal Review updated links to forms
- 10:1510:15, 11 August 2017 diff hist −363 m 236.5 Property Management No edit summary
- 10:1010:10, 11 August 2017 diff hist −158 m 236.5 Property Management No edit summary
- 10:0910:09, 11 August 2017 diff hist −8,484 m 236.5 Property Management updated links to forms
- 09:2309:23, 11 August 2017 diff hist −5 m 236.4 Description Writing and Titles No edit summary
- 09:0809:08, 11 August 2017 diff hist −1,580 m 236.4 Description Writing and Titles Per RW, updated form links
10 August 2017
- 09:5709:57, 10 August 2017 diff hist −8 m Main Page EPG 625.1.2
- 09:5509:55, 10 August 2017 diff hist +298 m Category:625 Slab Stabilization →625.1.2 Construction Inspection for Sec 625.10 Slab Undersealing: Per CM, clarified measurement of liquid asphalt cement
- 08:2708:27, 10 August 2017 diff hist −46 m Main Page EPG 760.1
- 08:2308:23, 10 August 2017 diff hist +672 m Category:760 General Construction Inspection for Structures →760.1 Preparation For Inspection: Per CM and BR, clarified overhead work on bridges safety guidance
- 08:1008:10, 10 August 2017 diff hist 0 m Category:950 Automated Traffic Enforcement No edit summary
- 08:0908:09, 10 August 2017 diff hist 0 m 907.3 Travel Safe Zones updated division's name
- 08:0708:07, 10 August 2017 diff hist +8 m 907.1 Safety Program Guidelines No edit summary
- 08:0608:06, 10 August 2017 diff hist −1 m 907.1 Safety Program Guidelines →907.1.3 District Safety Plans and Project Reporting
- 08:0508:05, 10 August 2017 diff hist +4 m 907.1 Safety Program Guidelines updated division's name
- 08:0308:03, 10 August 2017 diff hist +100 m 153.21 Traffic Updated division's name
- 07:0607:06, 10 August 2017 diff hist +1,609 m 237.11 Signing and Sealing Per CADD, moved slightly updated guidance from a link into the "Additional Information" box.
- 06:4406:44, 10 August 2017 diff hist +15 m 237.11 Signing and Sealing updated archaic Design link
9 August 2017
- 14:1414:14, 9 August 2017 diff hist 0 m Main Page No edit summary
- 12:4012:40, 9 August 2017 diff hist +2 m 643.2 Local Utility Adjustments - Public and Private Per Bidding and Est'g, further updated D-12
- 12:4012:40, 9 August 2017 diff hist +4 m 237.9 Submission of Plans and Supporting Documents Per Bidding and Est'g, further updated D-12
- 12:3912:39, 9 August 2017 diff hist 0 N File:D-12 Aug 9 2017.docx No edit summary current
- 12:3912:39, 9 August 2017 diff hist +4 m Category:124 Quality Control / Quality Assurance (QC/QA) Per Bidding and Est'g, further updated D-12
- 12:3812:38, 9 August 2017 diff hist +2 m Category:101 Standard Forms →Design: Per Bidding and Est'g, further updated D-12
- 11:0611:06, 9 August 2017 diff hist 0 N File:756 flow chart 2017.pdf No edit summary current
- 11:0611:06, 9 August 2017 diff hist +5 m Category:756 Seismic Design Per BR, minor updates to Bridge Seismic Design Process Flowchart
8 August 2017
- 12:3112:31, 8 August 2017 diff hist +34 m Main Page No edit summary
- 12:3012:30, 8 August 2017 diff hist +1 m Main Page No edit summary
- 12:2912:29, 8 August 2017 diff hist +44 m Main Page EPG 240
- 12:1312:13, 8 August 2017 diff hist +133 m Category:240 Maintenance and Emergency Crossovers Per TS, revised the standard for Emergency Vehicle Crossovers to 20' wide with 10' radius to allow fire/EMS responders to utilized the emergency crossovers.
7 August 2017
- 13:5913:59, 7 August 2017 diff hist −86 m 616.6 Temporary Traffic Control Zone Devices (MUTCD 6F) →616.6.87 Temporary Rumble Strips (MUTCD 6F.87): Per EPG, updated JSP links
- 13:4013:40, 7 August 2017 diff hist 0 m Main Page No edit summary
- 12:2712:27, 7 August 2017 diff hist +4 m 643.2 Local Utility Adjustments - Public and Private Per Bidding and Est'g, updated D-12
- 12:2612:26, 7 August 2017 diff hist +8 m 237.9 Submission of Plans and Supporting Documents Per Bidding and Est'g, updated D-12
- 12:2612:26, 7 August 2017 diff hist +4 m Category:101 Standard Forms Per Bidding and Est'g, updated D-12
- 12:2512:25, 7 August 2017 diff hist 0 N File:D-12 Aug 2017.docx No edit summary current
- 12:2512:25, 7 August 2017 diff hist +8 m Category:124 Quality Control / Quality Assurance (QC/QA) Per Bidding and Est'g, updated D-12
- 10:1910:19, 7 August 2017 diff hist −230 m Main Page No edit summary