LPA:136.4 Consultant Selection and Consultant Contract Management
If the local agency is not adequately staffed to provide the necessary engineering, architectural, land surveying, right of way and related services (including utility negotiations), they may engage a consultant to provide professional services. Under the Brooks Act, 40 USC 1102, professional services means:
- professional services of an architectural or engineering nature, as defined by state law, if applicable, that are required to be performed or approved by a person licensed, registered or certified to provide the services described in this paragraph;
- professional services of an architectural or engineering nature performed by contract that are associated with research, planning, development, design, construction, alteration or repair of real property; and
- other professional services of an architectural or engineering nature, or incidental services, which members of the architectural and engineering professions (and individuals in their employ) may logically or justifiably perform, including studies, investigations, surveying and mapping, tests, evaluations, consultations, comprehensive planning, program management, conceptual designs, plans and specifications, value engineering, construction phase services, soils engineering, drawing reviews, preparation of operating and maintenance manuals and other related services.
Federal law also recently expanded professional services stating “engineering and design related services are defined in 23 USC§112 (b)(2)(A) and 23 CFR §172.3 to include program management, construction management, feasibility studies, preliminary engineering, design engineering, surveying, mapping or other related services. These other services may include professional engineering related services, or incidental services that may be performed by a professional engineer, or individuals working under their direction, who may logically or justifiably perform these services."
The cost of the above professional services is eligible for federal participation provided that prior approval of the contracts by MoDOT is received. Federal participation in the cost of construction engineering is limited to 15% of the net federal participating construction costs, whether performed by consultant, in-house, or both for all contracts statewide. Construction engineering can be greater than 15% if requested by the local agency on a case-by-case basis prior to the award of the contract. Construction Inspection services may be included in the same agreement with design services. Preliminary engineering charges are permitted through the construction contract award stage. Charges after the award of the construction contract are considered to be construction engineering and cannot be charged against the design portion of the agreement. RW Acquisition Services shall be handled under a separate RW Services Agreement. This contract/agreement will be submitted at the same time the Request for Obligation of RW Funds (A-Date Request) is submitted.
Right of way project cost estimates, title work, right of way plan development and legal description writing may be included in the same agreement with Design Services and are reimbursable as preliminary engineering expenses. All other right of way acquisition activities eligible for reimbursement cannot be incurred or invoiced for reimbursement until the A-Date has been approved and the LPA has been notified.
On federal aid projects, right of way costs and incidental expenses are only reimbursable after MoDOT district staff reviews and approves the LPA personnel or the right of way acquisition contractor that will perform the right of way acquisition activities.
After execution by the local agency and consultant, three (3) copies of the contract are submitted to MoDOT for review and approval. The Fig. 136.6.1 standardized contract format developed by MoDOT is required.
In cases where the preliminary engineering or construction inspection costs in the contract exceed $250,000, MoDOT’s External Civil Rights Division may establish a Disadvantaged Business Enterprise (DBE) goal for the contract. The sponsor will need the established DBE goal before a Request for Proposal (RFP) is sent out to prospective engineering consultants. The RFP must include the DBE Contract Provisions for Engineering Services Contracts (ESCs). The sponsor must first submit an estimate of anticipated activities that will take place during the design or inspection process. Examples include but are not limited to surveying, plan sheet development, design, geological studies, and borings. Estimated hours and rates for each activity are not required. In order to obtain MoDOT approval of the contract in these cases, the consultant must acquire the required DBE participation or supply sufficient evidence as to why the DBE goal was not met.
The local agency should include a letter stating the necessity for utilizing a consultant for the work. If the local agency proposes to engage a consultant who has not been previously utilized by the local agency for the particular type of work involved, the local agency should submit a brochure or other information which outlines the qualifications of the firm's employees and recent past experience in similar work. It is not permissible for a consultant to contract with both the local agency and the contractor on the same project.
If a local agency engages a consultant to conduct an environmental study, the consultant is required to fill out a disclosure statement specifying the consultant has no financial or other interest in the outcome of the project. Additionally, the local agency cannot engage the same consultant for the environmental document and the final design during one contract negotiation process. The same consultant may be used but the local agency must utilize their selection process for the later stages.
All consultants receiving individual awards for $100,000 or more and all subrecipients must certify that the organization and its principals are not suspended or debarred. Each local agency may, but is not required to, check the Nonprocurement List. Copies may be obtained by purchasing a yearly subscription from the Superintendent of Documents, US Government Printing Office, Washington, DC 20402, or by calling the Government Printing Office Inquiry and Order Desk at (202) 783-3238. An electronic version is available. The user will be required to record their name and organization for purposes of the Computer Matching and Privacy Act of 1988.
All required independent assurance samples and tests will be performed by MoDOT, so this work should not be included in consultant contracts. However, required project tests are the local agency's responsibility. Should the local agency not have the required staff to administer these project tests, a consultant testing firm can be obtained and costs will be eligible for federal reimbursement.
136.6.1 Subconsultants
Subconsultant cost exceeding $25,000
If the consultant is using a subconsultant with a cost exceeding $25,000, then the subconsultant shall include page 11 of Fig. 136.6.1, a detailed estimate of cost and an overhead rate breakdown.
Subconsultant cost NOT exceeding $25,000
If the consultant is using a subconsultant with a cost that does not exceed $25,000, then a letter from the subconsultant shall be included that quotes the subconsultant’s cost shown in Attachment A of the contract.
136.6.2 Solicitation and Selection Procedures
Local agencies must use competitive negotiation for the procurement of engineering and design-related services on every project involving federal-aid highway funds. The Brooks Act and 23 CFR 172.3 must be followed if the local agency is seeking federal reimbursement for these services. The QBS process must include a public announcement, advertisement or other acceptable method that assures qualified in-state and out-of-state consultants are given a fair opportunity for consideration, which allows for a minimum two-week response time. It is recommended the local agency use the MoDOT Consultant Resources website to post the public announcement or advertisement (Fig. 136.6.7 Sample Solicitation). The solicitation form should be submitted to the appropriate MoDOT district representative. If the LPA wishes to use an alternative procedure to advertise and solicit qualifications for the RFQ, they must submit a written request with an advertising plan attached that complies with state and federal requirements. The advertisement plan must include advertisement of the availability in a major newspaper of general circulation. The RFQ notice must be advertised at least one time allowing a minimum 14 calendar days prior to the due date. The notice may be advertised multiple times if desired. The advertisement plan should also identify and send the solicitation to organizations qualified to do specified work as well as professional societies and recognized DBE organizations. The request must be approved by MODOT and FHWA prior to advertisement.
Local agencies must submit to MoDOT a description of procedures they use to evaluate and select consultants. When selecting a consultant, the local agency must use criteria listed in RSMo 8.289. If necessary, the local agencies can add criteria to the rating sheet, however, the criteria listed in Fig. 136.6.2 Consultant Selection Criteria Guidance and Rating Sheet must be included in the consultant selection rating process.
To avoid conflict of interest, the local agency may not use a consultant-engineering firm on retainer unless it satisfactorily documents the engineer or the firm was not involved in the solicitation and selection of the firm. These criteria must meet minimum federal requirements and be in compliance with Missouri Revised Statutes Chapter 8 Sections 8.285 through 8.291, RSMo. The local agency may use the criteria specified in federal and state regulations or may develop its own written procedures provided a qualification-based selection procedure commensurate with state policy is used. Local agencies must prepare a written description of the scope of the proposed services. According to state law, the agency must list three highly qualified firms and then select the firm best qualified to perform the desired services. The agency may evaluate current statements of qualifications and performance data of firms on file or solicit statements from other firms interested in the project. It is not necessary for the agency to interview all the firms. Price shall not be used as a factor in the analysis and selection of a firm. Price quotations shall not be requested for consideration prior to selecting a firm. If a local agency cannot negotiate a reasonable price with the consultant selected, it can cease negotiations and select a different firm. The local agency must provide written documentation of the selection procedures used and the names of the three or more firms considered when a contract is submitted for approval. If the local agency chooses to cite the state statute, then the following wording can be used:
- "We have considered the following three firms under procedures outlined in Missouri Law (RSMo Sections 8.285 to 8.291)."
The LPA must verify that firms submitting letters of interest to the solicitation participate in the Federal Work Authorization Program, E-Verify. The state statute requires firms to include an Affidavit of Compliance and a copy of the E-Verify MOU with their letter of interest. Refer to RSMo 285.530 Affidavit and E-Verify MOU Requirement and the State Code of Regulation Attorney General’s Office Code of State Regulation Affidavit of Compliance (15 CSR 60-15.020).
Failure to follow the state and federal provisions outlined above could jeopardize federal funding.
136.6.3 Scope of Services
The local agency should determine the scope of services when issuing an invitation for consultants to submit proposals. The scope of services should be detailed and project specific. In addition to the customary information contained in a scope of services, it is suggested that the following items be included:
1. The proposed design parameters to be used on the project. MoDOT design guidelines are required for projects on MoDOT right of way
2. When applicable, an investigation of Federal Emergency Management Agency's requirements;
3. Provision for 404 Permits, archaeological investigations and other environmental matters as judged necessary; and
4. Degree of construction inspection services to be included in the engineering service contract, if any.
136.6.4 Basis of Payment
The following methods may be used as the basis of payment in a contract:
1. Actual cost plus fixed fee; and
2. Specific rates of pay (for emergency situations only).
The most common basis of payment is actual cost plus fixed fee. Federal regulations prohibit the use of cost plus a percentage of cost and percentage of construction cost methods of compensation.
Subcontractors should be shown in the contract and costs passed through to the local agency at actual cost. Prompt payment of subcontractors is required.
Retainage is no longer designated by MoDOT as a routine part of the contract. Payment may be withheld on any particular work item that has not been completed in accordance with the contract. This can include work incidental to the work item, and required documentation directly related to the work.
136.6.5 Evaluations
Before a contract can be approved, it will be necessary to perform and document a technical evaluation to determine that the estimated man-hours are reasonable. In addition, if the total contract cost exceeds $100,000, an audit evaluation will need to be performed prior to contract execution, to determine that cost aspects are reasonable and that the cost estimate and overhead rates contain only items allowable under federal guidelines. Only those contracts that fall within the guidelines established for pre-negotiation audits by Audit and Investigations, MoDOT, will need to have such an audit evaluation.
136.6.6 Contract Submittal
The contract format illustrated in Fig. 136.6.1 Contract is required. Following is a checklist of items that should be included in or submitted with the contract:
1. Local agency's statement regarding the necessity for utilizing a consultant for the work;
2. Procedures used to evaluate and select consultants and a listing of firms considered;
3. Qualifications and experience resume' for consultant, if consultant has not been previously utilized by the local agency;
4. A method for modifying the contract (extra work or modified work or any change in the contract fee requires the approval of a supplemental agreement by MoDOT and FHWA prior to performing the work or incurring the added cost) (Refer to Article II of Fig. 136.6.1 Contract);
5. A statement that a local agency employee will be responsible for and in direct control of the construction contract even though a consultant may perform inspection work (Refer to Article III-G of Fig. 136.6.1 Contract);
6. A time reference after which all work under the contract will be considered complete (Refer to Article IV of Fig. 136.6.1 Contract);
7. A statement that specifies the basis for allowability of costs will be 23 CFR, Part 172 and 48 CFR, Part 31 (Refer to Article VI_F of Fig. 136.6.1 Contract);
8. Give residual credit for specialized equipment purchased for the contract (Refer to Article VI-H of Fig. 136.6.1 Contract);
9. The following covenant against contingent fees in the contract (Refer to Article VII of Fig. 136.6.1 Contract):
- "The consultant warrants that he has not employed or retained any company or person, other than a bona fide employee working for the consultant, to solicit or secure this contract, and that he has not paid or agreed to pay any company or person, other than a bona fide employee, any fee, commission, percentage, brokerage fee, gifts or any other consideration, contingent upon or resulting from the award or making of this contract. For breach or violation of this warranty, the local agency shall have the right to annul this contract without liability, or, in its discretion to deduct from the contract price or consideration, or otherwise recover, the full amount of such fee, commission, percentage, brokerage fee, gift or contingent fee plus reasonable attorney's fees."
10. An agreement for the retention of records for a period of three years after the consultant receives payment of their final invoice from the local agency (Refer to Article X of Fig. 136.6.1 Contract);
11. An agreement to allow MoDOT and FHWA and other authorized federal agencies to examine records pertaining to the project and costs (Refer to Article X of Fig. 136.6.1 Contract);
12. Ownership of engineering documents by local agency (Refer to Article XI of Fig. 136.6.1 Contract);
13. Procedure for settling disputes arising under the contract (Refer to Article XIII of Fig. 136.6.1 Contract);
14. A nondiscrimination provision (Refer to Article XVII of Fig. 136.6.1 Contract);
15. A cost breakdown as follows (Refer to Attachment A of Fig. 136.6.1 Contract):
- a. man-hours by pay grade and general work function;
- b. basic rates of pay;
- c. overhead rates, projected for the period of performance;
- d. other direct costs (travel, subsistence, etc.);
- e. fixed fee (actual cost);
- f. subcontracts;
- g. contract ceiling;
16. A breakdown of the consultant's overhead rates (Refer to Attachment B of Fig. 136.6.1 Contract) (Refer to Fig. 136.6.6 Common Unallowable Costs.);
17. Debarment certifications as an attachment to the contract (samples are attached in the standardized contract) (Refer to Attachments C and D of Fig. 136.6.1 Contract);
18. When the project is on MoDOT right of way, the Engineering Services Contract (ESC) shall indicate that the design must meet the requirements specified in the Engineering Policy Guide.
This checklist will help to ensure that all necessary documentation related to the project is completed in a timely manner.
136.6.7 Supplemental Agreements
The local agency reserves the right to change the scope of services in the contract. Such changes may include additional task, removal of task or changes to the tasks in the scope of services due to unforeseen conditions on the project. In this event, a supplemental to the agreement shall be executed and submitted for the approval of MoDOT prior to performing the additional or changed work or incurring any additional cost. Any changes in compensation will be covered in the supplement.
No work is to be initiated until MoDOT has notified the local agency to proceed with the activities contained in the supplemental agreement. A sample supplemental agreement is available.
Include the original fee in the supplement, as well as the revised fee. It is required to describe the additional services when submitting for approval. No changes in the fixed fee portion of a cost plus fixed fee contract will be approved in a supplemental agreement unless it is determined that the scope of work has changed significantly. The External Civil Rights Division will need to review the supplemental agreement’s anticipated activities to determine the DBE goal prior to execution of the agreement.
136.6.8 Consultant Performance Appraisal
Local agencies with the assistance of MoDOT and the contractor are requested to complete the Consultant Performance Appraisal after project completion. If any questions arise concerning the Consultant Performance Appraisal, the local agency should contact the MoDOT district representative for assistance.