Category:704 Concrete Masonry Repair

From Engineering_Policy_Guide
Revision as of 11:04, 4 February 2020 by Smithk (talk | contribs) (→‎704.1 Construction Inspection for Sec 704: Per BR, deck rehabilitation guidance has been updated to current methods. Pay items updated for monolithic deck repair to supplementary wearing surface material. Rehabilitation design guidance was expanded)
Jump to navigation Jump to search
Approved Products
Qualified Rapid Set Concrete Patching Material (Horizontal)
Qualified Rapid Set Concrete Patching Material (Vertical and Overhead)

704.1 Construction Inspection for Sec 704

This work consists of removing deteriorated concrete, preparing the repair site, forming where required, placing and finishing new concrete or qualified special mortar and applying epoxy in the required areas.

The types of repair are:

  • Half-Sole Repair
  • Deck Repair With Void Tube Replacement
If the contractor can adequately patch an exposed void tube, then the entire repair is considered either half-sole or monolithic deck repair.
  • Full Depth Repair
  • Modified Deck Repair
  • Superstructure Repair (Unformed)
  • Slab Edge Repair
  • Substructure Repair (Formed)
  • Substructure Repair (Unformed)
  • Epoxy Sealing
  • Monolithic Deck Repair
  • Shallow Deck Repair

Refer to Sec 704.

Excavator hydraulic hammers shall not be used for removal of deck concrete unless otherwise specified on the bridge plans.

704.2 Materials Inspection for Sec 704

For more information regarding Rapid Set Concrete Patching Material, refer to JSP 02-01.

Two lists of qualified rapid set concrete patching materials are maintained by Construction Materials. One list shows approved horizontal patching materials and the other list is for vertical and overhead patching materials.

704.3 Laboratory Testing for Sec 704

704.3.1 Scope

This guidance establishes procedures for Laboratory testing and reporting concrete cylinders representing Class X Concrete.

704.3.2 Procedure

Concrete cylinders shall be tested for compressive strength according to AASHTO T 22. Test results and calculations shall be recorded through SiteManager.

704.3.3 Sample Record

The sample record shall be completed in SiteManager, as described in Sample Record General Information . Appropriate remarks, as described in EPG 106.20 Reporting, are to be included in the remarks to clarify conditions of acceptance or rejection. Test results shall be reported on the appropriate templates under the Tests tab.