103.2 Contract Bond for Sec 103.4

From Engineering_Policy_Guide
Revision as of 15:03, 11 February 2015 by Smithk (talk | contribs) (Per CM, this article completely updated to provide additional information on how to make payment for contract bond and railroad liability insurance)
Jump to navigation Jump to search

Sec. 103.4 provides information regarding the contract bond.

For contracts that include a pay item for mobilization, the contractor may submit a request for an upfront reimbursement payment for the cost of the contract bond, as well as the cost of any railroad liability insurance (see Sec 618). The contractor will need to submit this request to the Resident Engineer along with invoices that verify the cost of the bond and/or railroad liability insurance. The RE will then issue a no-cost change order to add a pay item for these costs and to reduce the cost of mobilization by an equal amount. See the QRG Change Orders-Mobilization and Contract Bond for instructions on how to process this change order in SM. If the change order is exclusively issued to pay bond/insurance, then the contractor’s signature on the change order is not required and no higher level approval is required, including federal oversight projects. Contracts that do not include a pay item for mobilization, such as Job Order Contracts and Contract Level Course projects, are not eligible for this reimbursement since they do not include a pay item for mobilization.