Category:700 STRUCTURES AND HYDRAULICS: Difference between revisions

From Engineering_Policy_Guide
Jump to navigation Jump to search
Smithk (talk | contribs)
m article construction
No edit summary
Line 43: Line 43:
<categorytree mode=all>770 Preventive Maintenance Guidelines for Bridges</categorytree>
<categorytree mode=all>770 Preventive Maintenance Guidelines for Bridges</categorytree>


==700.1 General Construction Inspection for Division 700==
==700.1 Miscellaneous Design
===700.1.1 Bridges Used in Place===
Existing bridges at large stream crossings carrying light traffic may be used in place under certain conditions. Such structures may be narrower and have less loading capacity than the requirements in Figure 4-04.1. Where a location study report does not include a recommendation for the disposition of such structures, the district makes a recommendation, before completing the survey, to the Design Division. Narrow bridges used in place are properly signed with advance warning signs. Guardrail is used at the bridge ends to delineate the width transition.
 
===700.1.2 Temporary Bridges===
When it is undesirable to disrupt traffic with a road closure or staged construction, it may be necessary to construct a temporary bridge. The ends of temporary bridges are to be provided with protection equal to that of a permanent bridge. This protection may consist of installing appropriate crashworthy end terminals or sand filled impact attenuators, or where possible, extending the end of the guardrail outside of the clear zone.
 
===700.1.3 Bridge Drainage===
Bridges are provided with a combination of slab drains and drain basins to drain the bridge surface. The Bridge Division will determine the placement of slab drains. Drain basins should be provided on the down-grade side of all bridges. Consideration should be given to providing drain basins on the up-grade side of bridges where the roadway has curb and gutter and there's a possibility of a significant volume of water being carried onto the bridge. Where interchange ramps with curb are involved at the end of a bridge, consideration should be given to carrying bridge drainage along the ramp curb to an outlet on the ramp in lieu of using curb and gutter or drain basins at the concrete approach pavement. The drainage facility beyond the limits shown in the standard plans is designed to meet the existing conditions at the bridge involved, and is generally shown on the culvert section sheets. The district should make a recommendation for handling drainage when submitting bridge survey reports for concurrence by the Bridge Division at the bridge field check or on the bridge field check memorandum.
 
===700.1.4 Bridge Approach Slabs===
See [[Category:503 Bridge Approach Slabs|Bridge Approach Slabs]] for when to use. Bridge approach slabs are included in the bridge plans prepared by the Bridge Division. Payment for bridge approach slab is included in bridge estimated quantities.
 
===700.1.5 Concrete Approach Pavement===
Concrete approach pavement, as detailed in the standard plans, are specified on the plans at the end of some bridge approach slabs. Details such as type and location of traffic barrier should be coordinated with the Bridge Division. When pavement or bridge drainage required the use of drain basins they will be constructed within the limits of the concrete approach pavement, as detailed in the standard plans for drain basins.
 
===700.1.6 Color of Structural Steel Paint===
The color of structural steel paint shall be gray (Federal Standard #26373) or brown (Federal Standard #30045) except when approved by the District Engineer and the following conditions are met:
 
*An agreement with a local entity sponsoring the color is made indicating the local entity shall pay for all costs associated with providing necessary test data, pay for all costs associated with the finish coat in excess of typical costs associated with standard colors, and pay for future costs for applying the finish coat in excess of typical costs associated with standard colors as a condition of continuing the unique color.  (The agreement should stipulate that the color will be maintained in the future as mutually agreeable by both parties.  The additional cost to the local entity would be determined at that time.  Since we require a previously approved "system" be used, the prime coat will be the same as a standard system and should not fail prematurely.  If the color fades prematurely and the local entity wants it repainted, they would pay proportionately.  If the color fades and the local entity does not want to pay their share, the district would decide when future repainting occurs.)  Provide a copy of the agreement with the local entity to the State Bridge Engineer at least three (3) months prior to the plans due date for the bid opening.
 
*Only approved systems from currently approved manufacturers will be considered (list maintained by the Construction and Materials Division).
 
*The district or local entity shall provide certified performance data from an independent testing laboratory on samples formulated with the finish coat of the desired color from two paint manufacturers.  The Construction and Materials Division maintains the performance data required and can be contacted for further information.
 
==700.2 General Construction Inspection for Division 700==
This section is intended as a guide to adequate and uniform administration of inspection during construction of structures. The specialized structures are not discussed. Sound engineering judgment must be applied to those situations which occur so seldom that it is impractical to consider them in this manual.
This section is intended as a guide to adequate and uniform administration of inspection during construction of structures. The specialized structures are not discussed. Sound engineering judgment must be applied to those situations which occur so seldom that it is impractical to consider them in this manual.


Line 56: Line 81:
manual only supplements design and contract details in a general way.
manual only supplements design and contract details in a general way.


==700.2 Preparation For Inspection==
===700.2.1 Preparation For Inspection===
A good inspector will study plans, specifications and special provisions in great detail. If
A good inspector will study plans, specifications and special provisions in great detail. If
there are questions or an error has been made, immediately consult the resident engineer. The inspector should learn what materials will be used, what samples must be taken, and what on-site tests and measurements must be made. Prepare to answer questions relating to structural plans and specifications at the preconstruction conference. Obtain supplies and equipment needed for the job and check each item carefully to be sure it is in proper working order.
there are questions or an error has been made, immediately consult the resident engineer. The inspector should learn what materials will be used, what samples must be taken, and what on-site tests and measurements must be made. Prepare to answer questions relating to structural plans and specifications at the preconstruction conference. Obtain supplies and equipment needed for the job and check each item carefully to be sure it is in proper working order.
Line 101: Line 126:
::e. Compressive test machine and capping set.
::e. Compressive test machine and capping set.


==700.3 Inspector's Diary==
===700.2.2 Inspector's Diary===
Structure inspectors should keep a daily diary covering all operations. The amount of information to be kept is at the discretion of the resident engineer who must decide how much of
Structure inspectors should keep a daily diary covering all operations. The amount of information to be kept is at the discretion of the resident engineer who must decide how much of
the detailed record will be kept in his own diary. The resident engineer has the ultimate responsibility for maintaining a complete written history of the project, even though delegating
the detailed record will be kept in his own diary. The resident engineer has the ultimate responsibility for maintaining a complete written history of the project, even though delegating
Line 108: Line 133:
On a large bridge, such as a major stream crossing, a well organized inspection team is needed. One or more inspectors should be assigned to each major work phase under general supervision of a chief inspector. Typical major work phases are pile driving, substructure inspection, falsework and grades, superstructure forming, painting, slab inspection, and related work. Many phases may be in progress at the same time. The inspectors assigned to any phase will be the best qualified to prepare a detailed record of events concerning their area of responsibility. Their diary should contain considerable detail such as records of all instructions to the contractor's representative, a detailed description of active work in their area of responsibility, and a complete record of any unusual occurrences on the job, such as methods which might affect job quality, unusual storms, abnormally high water, a list of all equipment and manpower, etc. The diary is a history. It should not be confused with field data books for items such as grades, moisture tests, slump, etc., nor should it duplicate this data. Keep entries neat and systematic.
On a large bridge, such as a major stream crossing, a well organized inspection team is needed. One or more inspectors should be assigned to each major work phase under general supervision of a chief inspector. Typical major work phases are pile driving, substructure inspection, falsework and grades, superstructure forming, painting, slab inspection, and related work. Many phases may be in progress at the same time. The inspectors assigned to any phase will be the best qualified to prepare a detailed record of events concerning their area of responsibility. Their diary should contain considerable detail such as records of all instructions to the contractor's representative, a detailed description of active work in their area of responsibility, and a complete record of any unusual occurrences on the job, such as methods which might affect job quality, unusual storms, abnormally high water, a list of all equipment and manpower, etc. The diary is a history. It should not be confused with field data books for items such as grades, moisture tests, slump, etc., nor should it duplicate this data. Keep entries neat and systematic.


==700.4 Staking Structures==
===700.2.3 Staking Structures===
===700.4.1 General===
====700.2.3.1 General====
Recommended procedures for staking structures are outlined in [[238.4 Construction Surveying#238.4.1.25 Staking structures|Construction Surveying - Staking Structures]]. The responsible Department personnel shall satisfy themselves by independent check that staking is complete and accurate. Sometimes the bridge survey will have been made so far in advance of construction that radical changes have occurred in stream meander and flow lines. Large changes could affect the position of the bridge relative to the stream bed and nullify information shown on the plans. During staking this should be checked by taking a profile across the stream along the roadway centerline and a stream bed profile approximately 300 feet up and downstream. If large changes are found in either of the above, it may be necessary to shift the structure or revise footing elevations. The data should be sent to the district office for review and for transmittal to the Bridge Division if a design review appears warranted. Once staking is complete and checked, the resident engineer or the chief inspector should review the staking in detail with the contractor's authorized representative to be sure she/he knows the location and purpose of each stake.
Recommended procedures for staking structures are outlined in [[238.4 Construction Surveying#238.4.1.25 Staking structures|Construction Surveying - Staking Structures]]. The responsible Department personnel shall satisfy themselves by independent check that staking is complete and accurate. Sometimes the bridge survey will have been made so far in advance of construction that radical changes have occurred in stream meander and flow lines. Large changes could affect the position of the bridge relative to the stream bed and nullify information shown on the plans. During staking this should be checked by taking a profile across the stream along the roadway centerline and a stream bed profile approximately 300 feet up and downstream. If large changes are found in either of the above, it may be necessary to shift the structure or revise footing elevations. The data should be sent to the district office for review and for transmittal to the Bridge Division if a design review appears warranted. Once staking is complete and checked, the resident engineer or the chief inspector should review the staking in detail with the contractor's authorized representative to be sure she/he knows the location and purpose of each stake.


===700.4.2 Control Points===
====700.2.3.2 Control Points====
"Control points" establishing centerline and elevations are responsibilities of MoDOT. Such points should be established by staking methods compatible with instructions in [[238.4 Construction Surveying|Construction Surveying]].
"Control points" establishing centerline and elevations are responsibilities of MoDOT. Such points should be established by staking methods compatible with instructions in [[238.4 Construction Surveying|Construction Surveying]].


Line 126: Line 151:
The division of responsibility under which the engineer is responsible for control points (always set on permanently fixed objects) and the contractor for intermediate points (on forms or temporary objects) is established by [http://modot.mo.gov/business/standards_and_specs/Sec0105.pdf Sec 105.8] of the Standard Specifications.
The division of responsibility under which the engineer is responsible for control points (always set on permanently fixed objects) and the contractor for intermediate points (on forms or temporary objects) is established by [http://modot.mo.gov/business/standards_and_specs/Sec0105.pdf Sec 105.8] of the Standard Specifications.


==700.5 Vertical Clearance==
===700.2.4 Vertical Clearance===
The legal vehicle height in the state of Missouri ranges from 13 ft. 6 in. to 15 ft. 0 in. Any loads over the legal height limit require a permit.
The legal vehicle height in the state of Missouri ranges from 13 ft. 6 in. to 15 ft. 0 in. Any loads over the legal height limit require a permit.


Line 138: Line 163:
in the field and reported when the project is completed.
in the field and reported when the project is completed.


===719.5.1 Responsibility===
====700.2.4.1 Responsibility====
The State Bridge Maintenance Engineer is responsible for keeping a master records of vertical clearance measurements. They furnish this information to the people who issue [[:Category:945 Overdimension / Overweight Permits|overdimension permits]].
The State Bridge Maintenance Engineer is responsible for keeping a master records of vertical clearance measurements. They furnish this information to the people who issue [[:Category:945 Overdimension / Overweight Permits|overdimension permits]].


===719.5.2 Requirements===
====700.2.4.2 Requirements====
Vertical clearance shall be measured on every project. This includes rehabilitation and resurfacing work as well as new construction. Minimum vertical clearance measurements for bridges over state routes and city or county streets shall be taken and reported to the District Construction and Materials Engineer.
Vertical clearance shall be measured on every project. This includes rehabilitation and resurfacing work as well as new construction. Minimum vertical clearance measurements for bridges over state routes and city or county streets shall be taken and reported to the District Construction and Materials Engineer.


====719.5.2.1 Railroads====
====700.2.4.3 Railroads====
When the rehabilitation or new construction involves a structure over a railroad not only should the vertical clearance be taken, but the horizontal clearances to the nearest obstacle should be taken, also. This horizontal measurement should be taken from a point half way between the two rails of the railroad track to the nearest obstacle. If multiple tracks are located under a structure additional measurements should be taken. This information is not only to be sent to the State Bridge Maintenance Engineer and the [[:Category:945 Overdimension / Overweight Permits|Permits Section]] but should also be sent to the Railroad Liaison Engineer located in Multimodal Operations located in General Headquarters of MoDOT. They will in turn submit the information to the respective railroad company for their information.
When the rehabilitation or new construction involves a structure over a railroad not only should the vertical clearance be taken, but the horizontal clearances to the nearest obstacle should be taken, also. This horizontal measurement should be taken from a point half way between the two rails of the railroad track to the nearest obstacle. If multiple tracks are located under a structure additional measurements should be taken. This information is not only to be sent to the State Bridge Maintenance Engineer and the [[:Category:945 Overdimension / Overweight Permits|Permits Section]] but should also be sent to the Railroad Liaison Engineer located in Multimodal Operations located in General Headquarters of MoDOT. They will in turn submit the information to the respective railroad company for their information.


===719.5.3 Measurement===
====719.2.4.3 Measurement====
When measuring vertical clearance, the following should be kept in mind:
When measuring vertical clearance, the following should be kept in mind:


Line 164: Line 189:
It is important that this information be submitted before the obstructed road is opened to traffic, or within 24 hours of completion if the route was never closed to traffic.
It is important that this information be submitted before the obstructed road is opened to traffic, or within 24 hours of completion if the route was never closed to traffic.


===719.5.4 Temporary Restrictions===
====719.2.4.4 Temporary Restrictions====
Temporary vertical clearances and lane width restrictions due to construction work are to be reported to the District Maintenance and Traffic Engineer (District Maintenance Engineer). Submit this information prior to the obstruction being put in place. As soon as restrictions are removed notify the operations engineer in charge of maintenance who will advise the [[:Category:945 Overdimension / Overweight Permits|Permits - Overweight/Overdimension section]].
Temporary vertical clearances and lane width restrictions due to construction work are to be reported to the District Maintenance and Traffic Engineer (District Maintenance Engineer). Submit this information prior to the obstruction being put in place. As soon as restrictions are removed notify the operations engineer in charge of maintenance who will advise the [[:Category:945 Overdimension / Overweight Permits|Permits - Overweight/Overdimension section]].

Revision as of 10:44, 7 September 2007

A bridge is a structure spanning a minimum of 20 feet grade separation or crossing water. There are about 10,000 bridges in Missouri's state highway system. Bridges are described as simple or continuous and according to structure type and material.

Once the need concerning a bridge structure is identified in a project then a core team is established, the scope of the project is developed, a bridge survey is submitted and preliminary design begins. The bridge need could involve rehabilitating or widening an existing structure or building a new structure or retaining wall. There is no perfect bridge type for all situations. With practical design, engineers are expected and encouraged to consider and evaluate all potential solutions and project factors that ultimately impact the cost of the structure. However, any variations to the information in this guide should be discussed in advance with the appropriate Structural Liaison Engineer or Structural Project Manager.


Key Points - Hydraulics

As used in the highway environment, hydraulics is that branch of engineering concerned with the flow of water. Hydraulics includes the gutters, ditches, and storm sewer systems that remove rainfall runoff from a highway and also includes the flow in a waterway traversed by a highway consisting of open channels, culverts and bridges. Hydraulic design frequency and design criteria are based on federal and state laws and regulations, safe operation of the highway facility, and impact to adjacent property owners. Hydraulic structures are typically designed for high flow events, although specific projects may also have low flow criteria.

Category 751 LRFD Manual General not found
Category 770 Preventive Maintenance Guidelines for Bridges not found

==700.1 Miscellaneous Design

700.1.1 Bridges Used in Place

Existing bridges at large stream crossings carrying light traffic may be used in place under certain conditions. Such structures may be narrower and have less loading capacity than the requirements in Figure 4-04.1. Where a location study report does not include a recommendation for the disposition of such structures, the district makes a recommendation, before completing the survey, to the Design Division. Narrow bridges used in place are properly signed with advance warning signs. Guardrail is used at the bridge ends to delineate the width transition.

700.1.2 Temporary Bridges

When it is undesirable to disrupt traffic with a road closure or staged construction, it may be necessary to construct a temporary bridge. The ends of temporary bridges are to be provided with protection equal to that of a permanent bridge. This protection may consist of installing appropriate crashworthy end terminals or sand filled impact attenuators, or where possible, extending the end of the guardrail outside of the clear zone.

700.1.3 Bridge Drainage

Bridges are provided with a combination of slab drains and drain basins to drain the bridge surface. The Bridge Division will determine the placement of slab drains. Drain basins should be provided on the down-grade side of all bridges. Consideration should be given to providing drain basins on the up-grade side of bridges where the roadway has curb and gutter and there's a possibility of a significant volume of water being carried onto the bridge. Where interchange ramps with curb are involved at the end of a bridge, consideration should be given to carrying bridge drainage along the ramp curb to an outlet on the ramp in lieu of using curb and gutter or drain basins at the concrete approach pavement. The drainage facility beyond the limits shown in the standard plans is designed to meet the existing conditions at the bridge involved, and is generally shown on the culvert section sheets. The district should make a recommendation for handling drainage when submitting bridge survey reports for concurrence by the Bridge Division at the bridge field check or on the bridge field check memorandum.

700.1.4 Bridge Approach Slabs

See for when to use. Bridge approach slabs are included in the bridge plans prepared by the Bridge Division. Payment for bridge approach slab is included in bridge estimated quantities.

700.1.5 Concrete Approach Pavement

Concrete approach pavement, as detailed in the standard plans, are specified on the plans at the end of some bridge approach slabs. Details such as type and location of traffic barrier should be coordinated with the Bridge Division. When pavement or bridge drainage required the use of drain basins they will be constructed within the limits of the concrete approach pavement, as detailed in the standard plans for drain basins.

700.1.6 Color of Structural Steel Paint

The color of structural steel paint shall be gray (Federal Standard #26373) or brown (Federal Standard #30045) except when approved by the District Engineer and the following conditions are met:

  • An agreement with a local entity sponsoring the color is made indicating the local entity shall pay for all costs associated with providing necessary test data, pay for all costs associated with the finish coat in excess of typical costs associated with standard colors, and pay for future costs for applying the finish coat in excess of typical costs associated with standard colors as a condition of continuing the unique color. (The agreement should stipulate that the color will be maintained in the future as mutually agreeable by both parties. The additional cost to the local entity would be determined at that time. Since we require a previously approved "system" be used, the prime coat will be the same as a standard system and should not fail prematurely. If the color fades prematurely and the local entity wants it repainted, they would pay proportionately. If the color fades and the local entity does not want to pay their share, the district would decide when future repainting occurs.) Provide a copy of the agreement with the local entity to the State Bridge Engineer at least three (3) months prior to the plans due date for the bid opening.
  • Only approved systems from currently approved manufacturers will be considered (list maintained by the Construction and Materials Division).
  • The district or local entity shall provide certified performance data from an independent testing laboratory on samples formulated with the finish coat of the desired color from two paint manufacturers. The Construction and Materials Division maintains the performance data required and can be contacted for further information.

700.2 General Construction Inspection for Division 700

This section is intended as a guide to adequate and uniform administration of inspection during construction of structures. The specialized structures are not discussed. Sound engineering judgment must be applied to those situations which occur so seldom that it is impractical to consider them in this manual.

Structures include: bridges built of steel, concrete or a combination of both; bridges or trestles built of timber; concrete retaining walls, concrete crib-type retaining walls, or metal bintype retaining walls, single to multiple box culverts of concrete, storm drains, and sewers, and structural plate pipe and structural plate pipe-arch culverts.

Inspection work on structures is a great responsibility. The public safety is often at stake. Substandard construction will often lead to excessive maintenance costs.

Specifications, plans, and special provisions contain many details which the engineer must check. Such provisions govern if they should conflict with instructions in this manual since the manual only supplements design and contract details in a general way.

700.2.1 Preparation For Inspection

A good inspector will study plans, specifications and special provisions in great detail. If there are questions or an error has been made, immediately consult the resident engineer. The inspector should learn what materials will be used, what samples must be taken, and what on-site tests and measurements must be made. Prepare to answer questions relating to structural plans and specifications at the preconstruction conference. Obtain supplies and equipment needed for the job and check each item carefully to be sure it is in proper working order.

The inspector should carefully examine the site and compare the information on the plans with site conditions. Spot check for any errors. If the structure is a bridge, study physical features that may affect the work and its progress and check seasonal conditions, high water levels, or other conditions that could affect the order in which operations might be performed. For a culvert, the inspector should determine if the site will be properly drained to prevent flooding or damage to the structure during construction.

For all structures, particularly in urban work, the inspector should note the position of all utilities. Check all utility agreements and right-of-way plans to see if utility adjustments clear construction. The district office should be notified of any omission to avoid construction delays.

The inspector should promptly set up the necessary field books so that completed work can be measured and entries made promptly in the proper book or on forms furnished for this purpose.

Following is a list of equipment needed for typical structure inspection. Additional items necessary for project management are found in other sections of the manual.

l. All plans, specifications, special provisions, right of way plans and agreements, and utility data that apply to the structure.
2. Survey equipment appropriate to the job.
3. One or more 100 ft. steel tapes, extra plumb bobs, and other equipment necessary for staking the structure.
4. 50 ft. steel tape in case.
5. 6 ft. folding rule.
6. Bound field books for field notes and diaries.
7. Set of current standard drawings applicable to the contract.
8. All necessary standard forms for use on the structure.
9. Equipment for necessary field tests:
a. Compaction test equipment where required.
b. Slump cones and tamping rods.
c. Concrete cylinder molds.
d. Air meters for air-entrained concrete.
e. Compressive test machine and capping set.

700.2.2 Inspector's Diary

Structure inspectors should keep a daily diary covering all operations. The amount of information to be kept is at the discretion of the resident engineer who must decide how much of the detailed record will be kept in his own diary. The resident engineer has the ultimate responsibility for maintaining a complete written history of the project, even though delegating portions of the task to others.

On a large bridge, such as a major stream crossing, a well organized inspection team is needed. One or more inspectors should be assigned to each major work phase under general supervision of a chief inspector. Typical major work phases are pile driving, substructure inspection, falsework and grades, superstructure forming, painting, slab inspection, and related work. Many phases may be in progress at the same time. The inspectors assigned to any phase will be the best qualified to prepare a detailed record of events concerning their area of responsibility. Their diary should contain considerable detail such as records of all instructions to the contractor's representative, a detailed description of active work in their area of responsibility, and a complete record of any unusual occurrences on the job, such as methods which might affect job quality, unusual storms, abnormally high water, a list of all equipment and manpower, etc. The diary is a history. It should not be confused with field data books for items such as grades, moisture tests, slump, etc., nor should it duplicate this data. Keep entries neat and systematic.

700.2.3 Staking Structures

700.2.3.1 General

Recommended procedures for staking structures are outlined in Construction Surveying - Staking Structures. The responsible Department personnel shall satisfy themselves by independent check that staking is complete and accurate. Sometimes the bridge survey will have been made so far in advance of construction that radical changes have occurred in stream meander and flow lines. Large changes could affect the position of the bridge relative to the stream bed and nullify information shown on the plans. During staking this should be checked by taking a profile across the stream along the roadway centerline and a stream bed profile approximately 300 feet up and downstream. If large changes are found in either of the above, it may be necessary to shift the structure or revise footing elevations. The data should be sent to the district office for review and for transmittal to the Bridge Division if a design review appears warranted. Once staking is complete and checked, the resident engineer or the chief inspector should review the staking in detail with the contractor's authorized representative to be sure she/he knows the location and purpose of each stake.

700.2.3.2 Control Points

"Control points" establishing centerline and elevations are responsibilities of MoDOT. Such points should be established by staking methods compatible with instructions in Construction Surveying.

Contractor's forces are responsible for establishing such items as pile position, placing of footing forms and column forms, etc. Once they have done this using control points established by project forces, their request for an independent check should be granted.

As work progresses, it may be necessary to shift control points closer to the work in progress. Typically such points are established on previously completed concrete work such as top of footings or centerline of caps.

Typical items to be checked after the contractor has established their positions are piles, footings, columns, caps, anchor bolt wells, and bearing devices.

The division of responsibility under which the engineer is responsible for control points (always set on permanently fixed objects) and the contractor for intermediate points (on forms or temporary objects) is established by Sec 105.8 of the Standard Specifications.

700.2.4 Vertical Clearance

The legal vehicle height in the state of Missouri ranges from 13 ft. 6 in. to 15 ft. 0 in. Any loads over the legal height limit require a permit.

In order to issue permits for over-height loads, it is important that the department maintain current, accurate records of vertical clearances over and under state marked routes.

District personnel shall be responsible for measuring vertical clearances on all bridges over state routes, other roadways and railroads. This includes measuring clearances on new bridges that are open to traffic and anytime the clearance changes due to construction or maintenance project. All measurements shall be taken on the roadway surfaces only and not on the shoulders, even though the minimum clearance may be less on the shoulders. Measurement shall be made from the bottom of the lowest obstruction (beam, concrete, light fixture, rivet or bolt head, through truss member, etc.) This clearance shall be measured and rounded down to the nearest inch and reported to Bridge Maintenance.

When placing new steel girders over existing roadways or significantly lowering an existing clearance such as 6 in. overlay, the RE's should advise Bridge Maintenance by Email or letter of the temporary change in clearances. The final vertical clearance should be measured in the field and reported when the project is completed.

700.2.4.1 Responsibility

The State Bridge Maintenance Engineer is responsible for keeping a master records of vertical clearance measurements. They furnish this information to the people who issue overdimension permits.

700.2.4.2 Requirements

Vertical clearance shall be measured on every project. This includes rehabilitation and resurfacing work as well as new construction. Minimum vertical clearance measurements for bridges over state routes and city or county streets shall be taken and reported to the District Construction and Materials Engineer.

700.2.4.3 Railroads

When the rehabilitation or new construction involves a structure over a railroad not only should the vertical clearance be taken, but the horizontal clearances to the nearest obstacle should be taken, also. This horizontal measurement should be taken from a point half way between the two rails of the railroad track to the nearest obstacle. If multiple tracks are located under a structure additional measurements should be taken. This information is not only to be sent to the State Bridge Maintenance Engineer and the Permits Section but should also be sent to the Railroad Liaison Engineer located in Multimodal Operations located in General Headquarters of MoDOT. They will in turn submit the information to the respective railroad company for their information.

719.2.4.3 Measurement

When measuring vertical clearance, the following should be kept in mind:

1. One bridge over several routes will require several vertical clearance measurements. Over divided highways, a vertical clearance for each direction shall be measured and reported.

2a. All measurements for roadways are to be taken on the roadway surfaces only - not on the shoulders. Report actual vertical clearance if 18 ft. or less. If greater than 18 ft., show 18 ft. + on the report.

2b. All measurements for railroads are to be taken above the top of the rails and for a width of 12 ft., centered on the rails. Report actual vertical clearance of 23 ft. or less. If greater than 23 ft., show 23 ft. + on the report.

3. Measurements shall be made from the bottom of the lowest obstruction.

4. Measurement information shall include structure identification number, route, and county. Also identify the route over which the structure spans. When several roadways are involved, identify the roadway with the proper clearances. When more than one railroad track is uninvolved, identify each work track with the proper clearance. For clarity, a sketch of the structure with measurements shown can be used.

5. Horizontal clearances are measured from the center of the track to the nearest lateral obstruction (usually the closest pier) . The minimum clearances are normally shown on the plans and this must be maintained upon completion of the project. The plans should indicate a minimum horizontal clearance for temporary construction. If this information is not indicated on the plans, contact the Railroad Liaison Engineer in Multimodal Operation immediately.

It is important that this information be submitted before the obstructed road is opened to traffic, or within 24 hours of completion if the route was never closed to traffic.

719.2.4.4 Temporary Restrictions

Temporary vertical clearances and lane width restrictions due to construction work are to be reported to the District Maintenance and Traffic Engineer (District Maintenance Engineer). Submit this information prior to the obstruction being put in place. As soon as restrictions are removed notify the operations engineer in charge of maintenance who will advise the Permits - Overweight/Overdimension section.