Category:618 Mobilization: Difference between revisions
updated spec link |
deleted link to EPG 103.2 per RR3958 (removing article 103.2) |
||
(2 intermediate revisions by the same user not shown) | |||
Line 10: | Line 10: | ||
No standard plan is associated with mobilization, but the [https://www.modot.org/missouri-standard-specifications-highway-construction Sec 618 Mobilization standard spec] is included in the ''Missouri Standard Specification for Highway Construction''. | No standard plan is associated with mobilization, but the [https://www.modot.org/missouri-standard-specifications-highway-construction Sec 618 Mobilization standard spec] is included in the ''Missouri Standard Specification for Highway Construction''. | ||
==Basis of Payment for Mobilization (Per Sec 618.2 Basis of Payment)== | ==Basis of Payment for Mobilization (Per Sec 618.2 Basis of Payment)== | ||
[https://www.modot.org/ | [https://www.modot.org/missouri-standard-specifications-highway-construction Sec 618] describes how the RE should calculate progress payments for mobilization and when to make each payment. This specification is set up to pay the contractor incrementally for mobilization and discourage excessive mobilization bids. The first payment is made at Notice to Proceed to account for advance start-up costs, including, but not limited to, items such as contract bond and railroad insurance; therefore, no additional reimbursements should be made. | ||
A contractor is allowed to bid any amount for mobilization, however, to discourage excessive mobilization bids, any mobilization bid amount over 10 percent of the contract amount will not be paid until the project is accepted for maintenance (i.e., after all work, corrections and exceptions are complete). | |||
Contracts with a single project will generally have a single mobilization bid item. Contracts with multiple projects will generally have a separate mobilization bid item for each project. For the latter, the mobilization payment schedule should be applied to each project separately. If only one mobilization pay item is provided for a contract with multiple projects, the payment schedule shall be based upon contract completion percentages (if the projects have differing notice to proceed dates, the initial payment will be made at the earliest of those dates). | |||
===Payment Schedule - Calculation of Percent Complete=== | |||
The contract amount | The payment schedule is based on the total amount of completed pay items (shown as Total Posted Pay Items on the estimate) relative to the original contract amount. Contract incentives, material allowances, or other adjustments are not included in this percentage calculation. For contracts with a single project, the percent of contract complete shown on the payment estimate can be used as the threshold for triggering progress payments, except that, keep in mind this percentage is based on the adjusted contract amount. Therefore, if the contract has significant overruns, you will need to hand calculate the percent complete. Contracts with multiple projects and multiple mobilization pay items will require hand calculation of percent completion per project. | ||
'''Example 1 Mobilization bid item is 10 percent or less of the original contract amount.''' | |||
:Original Contract amount is $1,000,000 and Mobilization bid is $90,000: | |||
:The mobilization bid amount is less than 10 percent, so no retainage is required. | |||
:$90,000 is divided into four equal payments (25%) of $22,500. | |||
:Payment 1 of $22,500 will be made at notice to proceed. | |||
:Payment 2 of $22,500 will be made when 10% of the original contract amount is earned. | |||
:Payment 3 of $22,500 will be made when 20% of the original contract amount is earned. | |||
:Payment 4 of $22,500 (final payment) will be made when 30% of the original contract amount is earned. | |||
'''Example 2 Mobilization bid item is greater than 10 percent of the original contract amount.''' | |||
:Original Contract amount is $2,000,000 and Mobilization bid is $260,000: | |||
: | :Ten percent of the original contract amount is $200,000 (2,000,000 x 10%). The mobilization bid is $60,000 ($260,000 – $200,000) over the 10 percent threshold, | ||
: | :The amount over the 10 percent threshold ($60,000) will not be paid until the project is accepted for maintenance. The remaining $200,000 will be paid in four equal payments (25%) of $50,000. | ||
:Payment 1 of $50,000 will be made on an estimate at notice to proceed. | |||
:Payment 2 of $50,000 will be made when 10% of the original contract amount is earned. | |||
:Payment 3 of $50,000 will be made when 20% of the original contract amount is earned. | |||
:Payment 4 of $50,000 will be made when 30% of the original contract amount is earned. | |||
:Payment 5 of $60,000 (retained amount) will be made when the project is accepted for maintenance. | |||
The | |||
: | |||
==Additional Mobilization for Seeding== | ==Additional Mobilization for Seeding== | ||
Additional Mobilization for Seeding provides compensation for additional mobilization to perform temporary or permanent seeding beyond the initial occurrence, per Sec 806.50.2, and as required per terms of the SWPPP. Additional mobilization should be provided on projects where construction activities disturb an acre or more over the life of a project (see Sec 618.3). | Additional Mobilization for Seeding provides compensation for additional mobilization to perform temporary or permanent seeding beyond the initial occurrence, per Sec 806.50.2, and as required per terms of the SWPPP. Additional mobilization should be provided on projects where construction activities disturb an acre or more over the life of a project (see Sec 618.3). |
Latest revision as of 10:58, 19 November 2024
Mobilization includes the movement and preparation of facilities, equipment, supplies and personnel for work on the project. Mobilization costs are included on every project and may be estimated at
- 4% to 5% for pavement surfacing (resurfacing, seal coat, UBAWS, etc.),
- 5% to 6% for grading and turn-key projects,
- 7% to 8% for bridge projects and
- up to 10% for miscellaneous projects.
The percent selected should be applied to the project’s total cost (the cost that includes all items) when the estimate has been completed. This figure will be more carefully analyzed and adjusted by Design.
No standard plan is associated with mobilization, but the Sec 618 Mobilization standard spec is included in the Missouri Standard Specification for Highway Construction.
Basis of Payment for Mobilization (Per Sec 618.2 Basis of Payment)
Sec 618 describes how the RE should calculate progress payments for mobilization and when to make each payment. This specification is set up to pay the contractor incrementally for mobilization and discourage excessive mobilization bids. The first payment is made at Notice to Proceed to account for advance start-up costs, including, but not limited to, items such as contract bond and railroad insurance; therefore, no additional reimbursements should be made.
A contractor is allowed to bid any amount for mobilization, however, to discourage excessive mobilization bids, any mobilization bid amount over 10 percent of the contract amount will not be paid until the project is accepted for maintenance (i.e., after all work, corrections and exceptions are complete).
Contracts with a single project will generally have a single mobilization bid item. Contracts with multiple projects will generally have a separate mobilization bid item for each project. For the latter, the mobilization payment schedule should be applied to each project separately. If only one mobilization pay item is provided for a contract with multiple projects, the payment schedule shall be based upon contract completion percentages (if the projects have differing notice to proceed dates, the initial payment will be made at the earliest of those dates).
Payment Schedule - Calculation of Percent Complete
The payment schedule is based on the total amount of completed pay items (shown as Total Posted Pay Items on the estimate) relative to the original contract amount. Contract incentives, material allowances, or other adjustments are not included in this percentage calculation. For contracts with a single project, the percent of contract complete shown on the payment estimate can be used as the threshold for triggering progress payments, except that, keep in mind this percentage is based on the adjusted contract amount. Therefore, if the contract has significant overruns, you will need to hand calculate the percent complete. Contracts with multiple projects and multiple mobilization pay items will require hand calculation of percent completion per project.
Example 1 Mobilization bid item is 10 percent or less of the original contract amount.
- Original Contract amount is $1,000,000 and Mobilization bid is $90,000:
- The mobilization bid amount is less than 10 percent, so no retainage is required.
- $90,000 is divided into four equal payments (25%) of $22,500.
- Payment 1 of $22,500 will be made at notice to proceed.
- Payment 2 of $22,500 will be made when 10% of the original contract amount is earned.
- Payment 3 of $22,500 will be made when 20% of the original contract amount is earned.
- Payment 4 of $22,500 (final payment) will be made when 30% of the original contract amount is earned.
Example 2 Mobilization bid item is greater than 10 percent of the original contract amount.
- Original Contract amount is $2,000,000 and Mobilization bid is $260,000:
- Ten percent of the original contract amount is $200,000 (2,000,000 x 10%). The mobilization bid is $60,000 ($260,000 – $200,000) over the 10 percent threshold,
- The amount over the 10 percent threshold ($60,000) will not be paid until the project is accepted for maintenance. The remaining $200,000 will be paid in four equal payments (25%) of $50,000.
- Payment 1 of $50,000 will be made on an estimate at notice to proceed.
- Payment 2 of $50,000 will be made when 10% of the original contract amount is earned.
- Payment 3 of $50,000 will be made when 20% of the original contract amount is earned.
- Payment 4 of $50,000 will be made when 30% of the original contract amount is earned.
- Payment 5 of $60,000 (retained amount) will be made when the project is accepted for maintenance.
Additional Mobilization for Seeding
Additional Mobilization for Seeding provides compensation for additional mobilization to perform temporary or permanent seeding beyond the initial occurrence, per Sec 806.50.2, and as required per terms of the SWPPP. Additional mobilization should be provided on projects where construction activities disturb an acre or more over the life of a project (see Sec 618.3).