==127.3.1 Discussion==
==127.3.1 Discussion==


===127.3.1.1 Overview===
===127.3.1.1 Overview===


Transportation investments have major influences on society, with significant economic and social consequences. However, in many instances in the past, impacts on people did not receive the attention they deserve.  The community impact assessment process alerts affected communities and residents, as well as transportation decision-makers, to the likely consequences of a project, and ensures that human values and concerns receive proper attention during project development. Specifically, community impact assessment is important for:
Transportation investments have major influences on society, with potentially significant economic and social consequences. The community impact assessment process alerts affected communities and residents, as well as transportation decision-makers, to the likely consequences of a project, and ensures that human values and concerns receive proper attention during project development. Specifically, community impact assessment is important for:
<center>'''Table 127.3.1.1, Community Impact Assessment Values'''</center>


{| border="1" cellspacing="1"
{| border="1" cellspacing="1"
|-style="background:#CCCCCC"
|-style="background:#CCCCCC"
|style="background:#cccc00"|Quality of Life|| A high-quality standard of living for all Americans means we must protect the essential elements of existence, including neighborhoods and community values.  Community impacts assessment supports sustainable, livable communities; promotes community values and thriving neighborhoods; and contributes to general well being.
|style="background:#cccc00"|Quality of Life|| A high-quality standard of living for all Americans means we must protect the essential elements of existence, including neighborhoods and community values.  Community impacts assessment supports sustainable, livable communities; promotes community values and thriving neighborhoods; and contributes to general well-being.
|-style="background:#CCCCCC"
|-style="background:#CCCCCC"
|style="background:#cccc00"|Responsive Decision-making|| Assessing community impacts helps ensure that transportation policies and investments embrace the concerns of neighborhoods, communities, and society as a whole. Understanding the relationship between transportation actions and community life aids conflict minimization and the resolution of potential problems. Actively involving affected parties leads to better decisions and greater project acceptance, while creating a sense of community ownership and enhancing agency credibility.
|style="background:#cccc00"|Responsive Decision-making|| Assessing community impacts helps ensure that transportation policies and investments embrace the concerns of neighborhoods, communities, and society. Understanding the relationship between transportation actions and community life helps minimize conflict and promotes the resolution of potential problems. Actively involving affected parties leads to better decisions and greater project acceptance, while creating a sense of community ownership and enhancing agency credibility.  
|-style="background:#CCCCCC"
|-style="background:#CCCCCC"
|style="background:#cccc00"|Coordination|| Community impact assessment helps coordinate and integrate independent plans for land use, economics, and transportation to achieve common goals. This process aids communities in meeting state and local regulations and policies, such as zoning ordinances, environmental quality regulations, growth management and adequate facilities legislation, and comprehensive planning.
|style="background:#cccc00"|Coordination|| Community impact assessment helps coordinate and integrate independent plans for land use, economics, and transportation to achieve common goals. This process aids communities in meeting state and local regulations and policies, such as zoning ordinances, environmental quality regulations, growth management and adequate public facilities and services, legislation, and comprehensive planning.  
|-style="background:#CCCCCC"
|-style="background:#CCCCCC"
|style="background:#cccc00"|Nondiscrimination|| Community impact assessment ensures that we act on our obligation to achieve environmental justice through practices and procedures that do not discriminate. It alerts decision-makers to the effects on all segments of society and the potential for disproportionately high adverse effects on specific populations.
|style="background:#cccc00"|Nondiscrimination|| Community impact assessment ensures that we act on our obligation to achieve environmental justice through practices and procedures that do not discriminate. It alerts decision-makers to the effects to all segments of society and the potential for disproportionately high adverse effects to protected populations and others related to age, sex, disability.  
|}
|}


Community impact assessment is a process for evaluating the effects of a transportation action on a community and its quality of life.  The assessment process is an integral part of project planning and development that shapes the outcome of a project.  The information obtained is used to continuously mold the project and provide documentation of the current and anticipated social environment of a geographic area with and without action.  The assessment is to examine all topics of importance to people, such as mobility, safety, employment effects, relocation, isolation, and other community issues.
 
{|style="padding: 0.3em; margin-left:15px; border:1px solid #a9a9a9; text-align:center; font-size: 95%; background:#ffddcc" width="210px" align="right"  
{|style="padding: 0.3em; margin-left:1px; border:1px solid #a9a9a9; text-align:center; font-size: 95%; background:#ffddcc" width="810px" align="center"  
|-
|'''Economics of Highways'''
|-
|[http://library.modot.mo.gov/RDT/reports/Ri07032/or08017.pdf Report 2007]
|-
|[http://library.modot.mo.gov/RDT/reports/Ri05057/or07012.pdf Report 2007]
|-
|[http://library.modot.mo.gov/RDT/reports/Ri00058/ss08002.pdf Summary 2007]
|-
|[http://library.modot.mo.gov/RDT/reports/Ri00058/RDT03013.pdf Report 2003]
|-
|-
|[http://library.modot.mo.gov/RDT/reports/Ri05057/or07010.pdf Report 2007]
|A “protected” population is one that refers to groups specifically protected by additional regulations such as Title VI, Executive Order 12898 on EJ, etc.
|-
|[http://library.modot.mo.gov/RDT/reports/Ri00058/hndout04.pdf Report 2003]
|-
|'''Transportation Development, Social Impact'''
|-
|[http://library.modot.mo.gov/RDT/reports/Ri02012/Brf04July.pdf Summary 2004]
|-
|[http://library.modot.mo.gov/RDT/reports/Ri02012/RDT04020.pdf Report 2004]
|-
|'''See also:''' [http://www.modot.gov/services/OR/byDate.htm Innovation Library]
|}
|}
===127.3.1.2 Laws and Regulations===
 
Community impact assessment is a process for evaluating the effects of a transportation action on a community and its quality of life.  The assessment process is an integral part of project planning and development that shapes the outcome of a project.  The information obtained is used to continuously make improvements to the project and provide documentation of the current and anticipated social environment of a geographic area with and without action.  The assessment is to examine all topics of importance to people, such as mobility, safety, employment effects, relocation, isolation, and other community issues.
 
===127.3.1.2 Laws, Regulations, and Executive Orders (EO)===


In addition to the practical reasons for community impact assessment, multiple major federal regulations, statutes, policies, and Executive Orders legally require and support it.  
In addition to the practical reasons for community impact assessment, multiple major federal regulations, statutes, policies, and Executive Orders legally require and support it.  
* Intermodal Surface Transportations Efficiency Act of 1991 (ISTEA)  
* Intermodal Surface Transportations Efficiency Act of 1991 (EO 13166 on Limited English Proficiency)  
* National Environmental Policy Act of 1969 [[127.14 National Environmental Policy Act (NEPA) Classification and Documents|(NEPA)]]  
* National Environmental Policy Act of 1969 [[127.14 National Environmental Policy Act (NEPA) Classification and Documents|(NEPA)]]  
* Title VI of the Civil Rights Act of 1964 and related statutes  
* Title VI of the Civil Rights Act of 1964 and related statutes  
Line 56: Line 41:


FHWA guidance for the practitioner on community impact assessment includes:
FHWA guidance for the practitioner on community impact assessment includes:
* National Community Impact Assessment Research Design Team Recommendations for Development of the Strategic Plan, prepared for FHWA by the Center for Urban Transportation Research, University of South Florida (April 1999)
* Community Impact Assessment, A Quick Reference for Transportation, Publication No. FHWA-HEP-18-055 (2018 Update) https://www.fhwa.dot.gov/livability/cia/quick_reference/index.cfm
* Community Impact Mitigation Handbook, Publication No. FHWA-PD-98-024 (May 1998)
* [https://www.fhwa.dot.gov/environment/environmental_justice/publications/reference_guide_2015/section00.cfm EJ Reference Guide 2015]
* Community Impact Assessment, A Quick Reference for Transportation, Publication No. FHWA-PD-96-036 (September 1996)
* [https://www.environment.fhwa.dot.gov/env_topics/ej/guidance_ejustice-nepa.aspx FHWA Guidance on EJ and NEPA 2011]
* Guidance for Preparing and Processing Environmental and Section 4(f) Documents, FHWA Technical Advisory T 6640.8A (October 1987)
* [https://www.fhwa.dot.gov/environment/environmental_justice/case_studies/index.cfm Environmental Justice Case Studies]
* [https://www.fhwa.dot.gov/planning/public_involvement/index.cfm FHWA public involvement and public participation]


===127.3.1.3 Process===
===127.3.1.3 Process===


Community impact assessment is integral to the entire project development and decision-making process.  For example, the assessment of community impacts, along with other relevant environmental impact studies, helps shape project decisions and outcomes within the [[127.14 National Environmental Policy Act (NEPA) Classification and Documents|NEPA process]].  The assessment provides critical information about community values for the formulation of project objectives and the development of alternatives.   
Community impact assessment is integral to the entire project development and decision-making process.  For example, the assessment of community impacts, along with other relevant environmental impact studies, helps shape project decisions and outcomes within the [[127.14 National Environmental Policy Act (NEPA) Classification and Documents|NEPA process]].  The assessment provides critical information about community values to formulate project objectives and the development of alternatives.   


Throughout project decision-making activities and until construction, the community impact analyst assures that consequences to the social fabric of an area are given consideration with other environmental impacts. The analyst plays a vital role on the project development team as a vigorous advocate for community values.  
Throughout project decision-making and until construction, the Environmental specialist helps to ensure that consequences to the social fabric of an area are given consideration with other environmental impacts. The specialist plays an important role on the project development team to ensure community values are supported.  


Title VI of the Civil Rights Act of 1964 and Executive Order 12898 on Environmental Justice apply to federal activities. Compliance with the FHWA’s NEPA process will accomplish appropriate implementation of Title VI and EO 12898. This process includes fully identifying social, economic, and environmental effects; considering alternatives; coordinating with agencies; involving the public; and utilizing a systematic interdisciplinary approach. Addressing the issues coupled with full implementation of 23 USC 109(h) (e.g., community cohesion, availability of public facilities and services, adverse employment effects, etc.) will prevent the potential for discrimination or disproportionately high and adverse impacts. Community impact assessment is key to this preventive approach.  
Title VI of the Civil Rights Act of 1964 and Executive Order 12898 on Environmental Justice apply to federal activities. Compliance with the FHWA’s NEPA process will accomplish appropriate implementation of Title VI and EO 12898. This process includes fully identifying social, economic, and environmental effects; considering alternatives; coordinating with agencies; involving the public; and using a systematic interdisciplinary approach. Addressing the issues coupled with full implementation of 23 USC 109(h) (e.g., community cohesion, availability of public facilities and services, adverse employment effects, etc.) will prevent the potential for discrimination or disproportionately high and adverse impacts to protected populations. Community impact assessment is key to this preventive approach.


Although the assessment of community impacts rarely follows a fixed, predictable series of steps, there is a basic logic behind the assessment process, which incorporates the following components:
Although the assessment of community impacts rarely follows a fixed, predictable series of steps, there is a basic logic behind the assessment process, which incorporates the following components. A Community Impact Assessment form that identifies the requirements for the steps must be filled out and included in the RES documents when appropriate. Depending on the complexity of the project, there are two forms, one for a programmatic CE and one for a documented CE.


'''Define the Project Study Area'''
'''Define the Project Study Area'''
Line 81: Line 67:
'''Analyze Impacts'''  
'''Analyze Impacts'''  


Examine the impacts to the community of the proposed action versus no action.  Identify and investigate the consequences of the transportation action.  
Examine the impacts to the community by the proposed action versus no action.  Identify and investigate the consequences of the proposed transportation action.  


'''Identify Solutions'''  
'''Identify Solutions'''  
Line 93: Line 79:
'''Document Findings'''  
'''Document Findings'''  


In addition to oral presentations, prepare the findings of the community impact assessment in written form for use by decision-makers, to record findings, to disseminate to interested parties, and to support subsequent decisions.  
In addition to oral presentations, prepare the findings of the community impact assessment in written form for use by decision-makers, to record findings, to disseminate to interested parties, and to support subsequent decisions. These findings shall be documented in the Request for Environmental Services (RES) form for the project.


'''Iterative Process'''
'''Iterative Process'''


Communities are dynamic and constantly changing. As options change, the analyst must make appropriate re-evaluations and adjustments in findings, particularly if there are substantial time lapses in project development.
Communities are dynamic and constantly changing. As options change, or new information is gathered, the Environmental specialist must appropriately re-evaluate and adjust findings, particularly if there are substantial time lapses in project development.  
 
 
Although the steps in the community impact assessment process are logically sequential, they overlap in practice.  The assessment process is iterative in that analysts must be prepared to revisit prior steps and be aware of future steps in conducting the assessment.  In the early steps, when helping to frame the project and community profile, the community impact analyst must think about the probable relationships between the project and the community so that relevant data are collected.  Later, if new impacts are identified or decisions are made, the analyst must go back to the community profile and gather additional information or data regarding populations affected.
 


==127.3.2  Project Development Milestones==
Although the steps in the community impact assessment process are logically sequential, they overlap in practice. The assessment process is iterative in that specialists must be prepared to revisit prior steps and be aware of future steps in conducting the assessment. In the early steps when helping to frame the project and community profile, the community impact specialist must think about the probable relationships between the project and the community so that relevant data are collected. Later, if new impacts are identified or decisions are made, the specialist must go back to the community profile and gather additional information or data regarding populations affected.


===127.3.2.1  Initial Screening Stage===
In recognition that certain types of projects are unlikely to generate disproportionately high and adverse effect on EJ populations or community impacts, not all projects will require completion of all above steps, however if it is determined at any time in the project screening process that the project requires completion of a full assessment, the rest of the steps must be completed (see CIA CE2 form). Some projects, such as minor improvements, may require a less detailed analysis than a more complex projectThe scale of the analysis should depend not only on the scope of the project but also the context of the project. The environmental specialist must exercise professional judgment when determining the level of detail required for an assessment.
At the initial project screening stage, design division environmental staff performs a cursory identification of potential issues related to community impacts. Initial information collection involves gathering general informationAs potential impacts are identified later in the process, additional data on the community is targeted to specific needs. The environmental specialist uses databases related to these resources and possible contacts with district personnel to determine the likelihood that the project will have a negative impact on the community.


The district initiates this process by submitting an [[127.1 Request for Environmental Services|RES]] to the design division; usually no additional information will be required from the district.  Findings pertinent to the project will be relayed to the district in the RES response, which will also indicate what type of coordination is believed necessary, if any.
==127.3.2 Project Development Milestones==


===127.3.2.Location/Conceptual Plan Stage===
===127.3.2.1 Location/Conceptual Plan Stage===
At the location/conceptual plan stage, design division environmental staff use various tools and databases to screen the project but may also contact local entities to determine whether they have any concerns with the project.
At the location/conceptual plan stage, Design Division environmental staff determine if the project falls under a programmatic categorical exclusion (PCE) on Community Impacts, Environmental Justice, and Title VI Compliance or detailed analysis is needed. The environmental specialists use various tools and databases to screen the project but may also contact local entities and/or district staff to determine whether they have any concerns with the project or additional information that may help in the project review. Initial data collection involves gathering general information. The Specialist uses accepted databases related to these community resources and contacts district personnel, as needed, to determine the likelihood that the project will have a negative impact on the community.


The district initiates this process by submitting an [[127.1 Request for Environmental Services| RES]] to the design division, or for projects that require an Environmental Assessment (EA) or an Environmental Impact Statement (EIS), the design division and the district will determine when to begin this process. The district may be required to gather and submit additional information about the project at this stage. Findings pertinent to the project will be relayed to the district in the RES response and through core team participation.  
The district initiates this process by submitting a [[127.1 Request for Environmental Services|RES]] to the Design Division for every project when it is placed in the scoping section of the STIP or as soon as the project is programmed for those that go directly into the STIP. For projects that require an Environmental Assessment (EA) or an Environmental Impact Statement (EIS), the Design Division and the district will determine when to begin this process since an RES is not submitted for those projects until later in the NEPA process. The district may be required to gather and submit additional information about the project at this stage. Findings pertinent to the project will be relayed to the district in the RES response and through core team participation.  


===127.3.2.2.1 Impact Assessment===
====127.3.2.1.1 Impact Assessment====
{|style="padding: 0.3em; margin-left:7px; border:2px solid #a9a9a9; text-align:left; font-size: 95%; background:#f5f5f5" width="440px" align="right"  
{|style="padding: 0.3em; margin-left:7px; border:2px solid #a9a9a9; text-align:left; font-size: 95%; background:#f5f5f5" width="440px" align="right"  
|-
|-
|style="background:#cccccc" colspan="2"|<center>'''Community Impact Assessment Data List'''</center>
|style="background:#cccccc" colspan="2"|<center>'''Community Impact Assessment Data List'''</center>
|-
|-
|<center>'''Population and Demographic Characteristics'''</center>||rowspan=9|[[image:127.3 historical data.jpg|right|265px|thumb|<center>'''Historical background'''</center>]]  
|<center>'''Population and Demographic Characteristics'''</center>||rowspan=10|[[image:127.3 historical data.jpg|right|265px|thumb|<center>'''Historical background'''</center>]]  
|-
|-
|▪ Trends in population growth and demographics
|▪ Trends in population growth and demographics
|-
|-
|▪ Ethnicity and race  
|▪ Ethnicity and race  
|-
|▪ Languages spoken
|-
|-
|▪ Age and gender distributions  
|▪ Age and gender distributions  
Line 151: Line 133:
|colspan="2"|▪  Tax base  
|colspan="2"|▪  Tax base  
|-
|-
|colspan="2"|▪  Other economic characteristics (e.g., port city, tourism base and lumber town)  
|colspan="2"|▪  Other economic characteristics (e.g., port city, tourism base, and lumber town)  
|-
|-
|colspan="2"|<center>'''Physical Characteristics Relating to Community Activities'''</center>  
|colspan="2"|<center>'''Physical Characteristics Relating to Community Activities'''</center>  
Line 159: Line 141:
|colspan="2"|▪ Infrastructure (e.g., roads, transit, and water and sewage systems)  
|colspan="2"|▪ Infrastructure (e.g., roads, transit, and water and sewage systems)  
|-
|-
|colspan="2"|▪ Public services and facilities (e.g., schools, police, fire, libraries and hospitals)  
|colspan="2"|▪ Public services and facilities (e.g., schools, police, fire, libraries, and hospitals)  
|-
|-
|colspan="2"|▪ Land-use plans and zoning  
|colspan="2"|▪ Land-use plans and zoning  
Line 167: Line 149:
|colspan="2"|▪  Businesses  
|colspan="2"|▪  Businesses  
|-
|-
|colspan="2"|▪  Housing (availability, age, and type)  
|colspan="2"|▪  Housing (e.g., availability, age, and type)  
|-
|-
|colspan="2"|▪  Planned and approved future development  
|colspan="2"|▪  Planned and approved future development  
|-
|-
|colspan="2"|▪ Community focal points or informal meeting places (e.g., places of worship, playgrounds, hair salons and laundromats)  
|colspan="2"|▪ Community focal points or informal meeting places (e.g., places of worship, playgrounds, hair salons, and laundromats)  


Data sources include:  
Data sources include:  
Line 180: Line 162:
!style="background:#cc9900"| Source!! style="background:#cc9900"| Primary Uses
!style="background:#cc9900"| Source!! style="background:#cc9900"| Primary Uses
|-
|-
|width="350px" style="background:#cccccc"| Metropolitan Planning Organizations (MPOs)|| width="350px" style="background:#cccccc"| Economic base, land-use and zoning plans and area planning history
|width="350px" style="background:#cccccc"| Metropolitan Planning Organizations (MPOs)|| width="350px" style="background:#cccccc"| Economic base, land-use and zoning plans, and area planning history
|-
|-
|width="350px" style="background:#cccccc" valign="top"| State and local government planning and community impact assessment service departments/agencies|| width="350px" style="background:#cccccc"|  Economic base, land-use and zoning plans, taxing districts, Community Impact Assessment and economic programs and business and marketing information
|width="350px" style="background:#cccccc" valign="top"| State and local government planning and community impact assessment service departments/agencies|| width="350px" style="background:#cccccc"|  Economic base, land-use and zoning plans, taxing districts, Community Impact Assessment and economic programs and business, and marketing information
|-  
|-  
|width="350px" style="background:#cccccc"| State employment agencies or labor departments|| width="350px" style="background:#cccccc"| Employment trends, unemployment rates and economic base
|width="350px" style="background:#cccccc"| State employment agencies or labor departments|| width="350px" style="background:#cccccc"| Employment trends, unemployment rates, and economic base
|-
|-
|width="350px" style="background:#cccccc"| State, local, and university libraries (for local newspaper clippings and other local sources)|| width="350px" style="background:#cccccc"| General information, community historical background, economic base and business and marketing information
|width="350px" style="background:#cccccc"| State, local, and university libraries (for local newspaper clippings and other local sources)|| width="350px" style="background:#cccccc"| General information, community historical background, economic base, and business and marketing information
|-
|-
|width="350px" style="background:#cccccc" valign="top"| Local historical societies and State Historic Preservation Officer (SHPO)|| width="350px" style="background:#cccccc"| Community historical background and location of historic structures, landmarks, and districts
|width="350px" style="background:#cccccc" valign="top"| Local historical societies and State Historic Preservation Officer (SHPO)|| width="350px" style="background:#cccccc"| Community historical background and location of historic structures, landmarks, and districts
Line 195: Line 177:
{| Border="1"
{| Border="1"
|-
|-
|style="background:#cc9933" colspan="2" align="center"| '''Data Collections and Activities'''
|style="background:#cc9933" colspan="2" align="center"| '''Table 127.3.2.1.1, Data Collections and Activities'''
|-
|-
!style="background:#cc9933"| Source!! style="background:#cc9933"| Primary Uses
!style="background:#cc9933"| Source!! style="background:#cc9933"| Primary Uses
|-
|-
|width="350px" style="background:#cccccc" valign="top"| Census Bureau publications and statistical abstracts|| width="350px" style="background:#cccccc" valign="top"| Population trends and demographics, economic indicators and housing
|width="350px" style="background:#cccccc" valign="top"| U.S. Census Bureau publications and statistical abstracts using EJScreen|| width="350px" style="background:#cccccc" valign="top"| Population trends and demographics, economic indicators, and housing
|-  
|-  
|width="350px" style="background:#cccccc" valign="top"| Aerial maps and [[:Category:138 Project Development Chronology#Speaking of road maps|road maps]]||width="350px" style="background:#cccccc" valign="top"| Community boundaries and physical characteristics; location of activity centers, infrastructure, houses and businesses
|width="350px" style="background:#cccccc" valign="top"| Aerial maps and [[:Category:138 Project Development Chronology#Speaking of road maps|road maps]]||width="350px" style="background:#cccccc" valign="top"| Community boundaries and physical characteristics; location of activity centers, infrastructure, houses and businesses
Line 205: Line 187:
|width="350px" style="background:#cccccc" valign="top"| Field or windshield surveys and reviews||width="350px" style="background:#cccccc" valign="top"| Locations and numbers of structures and activity patterns
|width="350px" style="background:#cccccc" valign="top"| Field or windshield surveys and reviews||width="350px" style="background:#cccccc" valign="top"| Locations and numbers of structures and activity patterns
|-  
|-  
|width="350px" style="background:#cccccc" valign="top"| Yellow Pages or city directories||width="350px" style="background:#cccccc" valign="top"| Businesses and community facility locations and type
|width="350px" style="background:#cccccc" valign="top"| Interviews and public involvement with businesses, community leaders, and residents||width="350px" style="background:#cccccc" valign="top"| Community values and issues
|-
|width="350px" style="background:#cccccc" valign="top"| Dun and Bradstreet (D&B) databases||width="350px" style="background:#cccccc" valign="top"| Business location, type and number of employees
|-
|width="350px" style="background:#cccccc" valign="top"| Donnelley Directory (available on CD-ROM)||width="350px" style="background:#cccccc" valign="top"| Business location, type and number of employees
|-  
|-  
|width="350px" style="background:#cccccc" valign="top"| Tax records||width="350px" style="background:#cccccc" valign="top"| Property values
|style="background:#cccccc" valign="top" colspan="2"| More sources and uses can be found at  https://www.fhwa.dot.gov/livability/cia/quick_reference/index.cfm
|-
|width="350px" style="background:#cccccc" valign="top"| Building-permit records||width="350px" style="background:#cccccc" valign="top"| Approved or built development
|-
|width="350px" style="background:#cccccc" valign="top"| Real estate market surveys, regional real estate journals, and interviews with realtors||width="350px" style="background:#cccccc" valign="top"| Housing prices; trends in sales, age or characteristics of structures; and neighborhood compositions
|-
|width="350px" style="background:#cccccc" valign="top"| Interviews and public involvement with businesses, community leaders, and residents||width="350px" style="background:#cccccc" valign="top"| Community values and issues
|}
|}
|}
|}
For projects that require an EA or an EIS, the community impact analyst will ensure that comments concerning potential impacts to the community are solicited from local entities through written requests. The impact assessment process described previously must be initiated prior to alternatives development and is to be used to guide that development.  This activity fulfills the [[127.14 National Environmental Policy Act (NEPA) Classification and Documents|NEPA requirements]] relating to the selection of alternatives and the information obtained is used in the EA or EIS documentation or Categorical Exclusion determination (CE2).
For all projects, the Environmental specialist, district project team, and/or consultant team will ensure that any comments concerning potential impacts to the community solicited from local entities through the public involvement process are addressed. The impact assessment process described previously must be initiated prior to alternatives development and is to be used to guide that development.  This activity fulfills the [[127.14 National Environmental Policy Act (NEPA) Classification and Documents|NEPA requirements]] relating to the selection of alternatives and the information obtained is used in the EA, EIS, PCE or documented Categorical Exclusion (CE2) documentation.  


Refer to the Community Impact Assessment Data List box to the right for examples of the types of data collected and incorporated into environmental documents.
Refer to Table 127.3.2.1.1, Data Collections and Activities, for examples of the types of data collected and incorporated into environmental documents.


===127.3.2.2.2 Addressing Impacts===
====127.3.2.1.2 Addressing Adverse Impacts====
When adverse community impacts are identified, the community impact analyst will propose potential methods for addressing them. This step of the community impact assessment process involves problem-solving and generating solutions. There are four primary methods for dealing with impacts, to be considered in the order listed below.  
When adverse community impacts are identified, the Environmental specialist will propose potential methods for addressing them through mitigation. This step of the community impact assessment process involves problem-solving and generating solutions. There are four primary methods to address impacts, which are considered in the order listed below.  


'''Avoidance'''  
'''Avoidance'''  
Line 241: Line 213:
'''Enhancement'''
'''Enhancement'''


Add a desirable or attractive feature to the project to make it fit more harmoniously into the community.  (Not intended to replace lost resources or alleviate impacts caused by the project.)
Add a desirable or attractive feature to the project to make it fit more harmoniously into the community.  It is not intended to replace lost resources or alleviate impacts caused by the project.


Project design options are typically based on an ideal engineering standard.  When adverse community impacts are identified, analysts are to:
Project design options are typically based on an ideal engineering standard.  When adverse community impacts are identified, specialists will:
* Work with the project development team to identify design or engineering options to deal with these impacts—starting with avoidance and then moving on to minimization and mitigation techniques.
* Work with the project development team to identify design or engineering options to deal with these impacts—starting with avoidance and then moving on to minimization and mitigation techniques.
* Finally, consider enhancement opportunities that are a reasonable expenditure of public funds and help the project fit harmoniously into the community.
* Consider enhancement opportunities that are a reasonable expenditure of public funds and help the project fit harmoniously into the community.
Community impact analysts should recognize that an effort to address one impact may create other adverse impacts.  Analysts must consider the potential impacts of these measures on the community, ensuring that the approaches considered support the purpose and need of the project. Whatever approach is selected, it is important to monitor and follow through on commitments.
 
Community impact specialists should recognize that an effort to address one impact may create other adverse impacts.  Specialists must consider the potential impacts of these measures on the community, ensuring that the approaches considered support the purpose and need of the project. Whatever approach is selected, it is important to monitor and follow through on commitments.  


Public involvement can provide important information to aid in identifying acceptable solutions to address adverse impacts.   
Public involvement can provide important information to aid in identifying acceptable solutions to address adverse impacts.   


The [[127.14 National Environmental Policy Act (NEPA) Classification and Documents#127.14.3.1 Categorical Exclusion|Categorical Exclusion (CE)]], [[127.14 National Environmental Policy Act (NEPA) Classification and Documents#127.14.3.2 Environmental Assessment|Finding of No Significant Impact (FONSI)]], and [[127.14 National Environmental Policy Act (NEPA) Classification and Documents#127.14.3.3 Environmental Impact Statement|Record of Decision (ROD)]] documents as well as the draft and final EIS must include the commitments.
The [[127.14 National Environmental Policy Act (NEPA) Classification and Documents#127.14.3.1 Categorical Exclusion|Categorical Exclusion (PCE and CE2)]], [[127.14 National Environmental Policy Act (NEPA) Classification and Documents#127.14.3.2 Environmental Assessment|Finding of No Significant Impact (FONSI)]], and [[127.14 National Environmental Policy Act (NEPA) Classification and Documents#127.14.3.3 Environmental Impact Statement|Record of Decision (ROD)]] documents as well as the draft and final EIS must include the avoidance and minimization measures that have been completed as well as the commitments identified during the process to avoid, minimize, or mitigate any adverse impacts which are then carried forward in the bid documents.  


Practical examples include:
Practical examples include:


'''Avoidance'''
'''Avoidance'''
* Change an alignment so that there are not displacements.
* Change an alignment so that there are no displacements.
* Redesign a road segment as an underpass to avoid cutting off access to a community facility.
* Redesign a road segment as an underpass to avoid cutting off access to a community facility.


Line 262: Line 235:
* Limit interchanges to minimize incompatible land-use development.
* Limit interchanges to minimize incompatible land-use development.
* Phase the project to minimize impedance to business access during peak periods.
* Phase the project to minimize impedance to business access during peak periods.
* Alter an alignment to increase the distance between the facilities and  residences to [[127.13 Noise#127.13.4 Traffic Noise Policy|minimize noise impacts]].
* Alter an alignment to increase the distance between the transportation facilities and  residences to [[127.13 Noise#127.13.4 Traffic Noise Policy|minimize noise impacts]].


'''Mitigation'''
'''Mitigation'''
Line 268: Line 241:
* Erect sound barriers to mitigate noise to surrounding communities.  
* Erect sound barriers to mitigate noise to surrounding communities.  
* Provide a bicycle/pedestrian overpass or underpass to provide access to public facilities.
* Provide a bicycle/pedestrian overpass or underpass to provide access to public facilities.
* Provide compensation for properties acquired (a mandatory measure under the Uniform Act Amendments).
* Provide compensation for properties acquired, a mandatory measure under the Uniform Act Amendments.


'''Enhancement'''
'''Enhancement'''
* Provide signage to recognize specific cultural or historic resources.
* Provide signage to recognize specific cultural or historic resources.
* Development bicycle trails or path adjacent to roadways.
* Development bicycle trails or paths adjacent to roadways.
* Plant trees and add park benches.
* Plant trees and add park benches.
* Add public artwork or a facade to a transportation facility to match the aesthetic design goals of a community.
* Add public artwork or a facade to a transportation facility to match the aesthetic design goals of a community.


There are two types of enhancements:  1) Environmental enhancements, which may be added to a transportation project to improve community acceptance (see 1990 FHWA Environmental Policy Statement) and 2) Transportation enhancements, which are funded through a provision of SAFETEA-LU with funds set aside from the Surface Transportation Program.
There are two types of enhancements:  1) Environmental enhancements, which may be added to a transportation project to improve community acceptance (see 1994 FHWA Environmental Policy Statement) and 2) Transportation enhancements, which are funded through [https://www.fhwa.dot.gov/safetealu/factsheets/transenh.htm a provision of SAFETEA-LU] with funds set aside from the Surface Transportation Program.


Environmental enhancements are incorporated into a project as part of routine decision-making to make it more compatible with and sensitive to community needs.  Transportation enhancement activities offer communities the opportunity to expand transportation choices with safe bicycle and pedestrian facilities, [http://www.modot.org/scenicbyways/ scenic routes], beautification, and other investments that increase opportunities for recreation, accessibility, and safety for everyone beyond traditional highway programs.  Transportation enhancements funding may be available to help meet these needs.
Environmental enhancements are incorporated into a project as part of routine decision-making to make it more compatible with and sensitive to community needs.  Transportation enhancement activities offer communities the opportunity to expand transportation choices with safe bicycle and pedestrian facilities, [http://www.modot.org/scenicbyways/ scenic routes], beautification, and other investments that increase opportunities for recreation, accessibility, and safety for everyone beyond traditional highway programs.  Transportation enhancements funding may be available to help meet these needs.


===127.3.2.Preliminary Plans Stage===
===127.3.2.2 Preliminary Plans Stage===
At the preliminary plans stage, if no community impact issues have been identified previously, a process similar to that described for the initial project screening is repeated.  The district initiates this process by submitting an [[127.1 Request for Environmental Services|RES]] to the design division. The environmental specialist screens the project for changes and verifies that no new information has become available since the last screening. Any new findings pertinent to the project will be relayed to the district in the RES response and the environmental specialist will discuss appropriate actions with the project manager.
If no community impact issues were previously identified or the project fell under the Programmatic Categorical Exclusion (PCE), the preliminary plans stage allows specialists to repeat a similar a process as was conducted during the initial project screening.  The district initiates this process by submitting an [[127.1 Request for Environmental Services|RES]] to the Design Division. The environmental specialist screens the project for changes and determines whether any new information has become available since the last screening. Any new findings pertinent to the project will be relayed to the district in the RES response and the environmental specialist will discuss appropriate actions with the project manager.  


At this stage, if it has been determined that the project could have an impact on a community, the environmental specialist will continue coordinating with local entities and the district to determine and design the necessary solutions.   
At this stage, if it has been determined that the project could have an impact on a community, the environmental specialist will continue coordinating with the district to determine and design the necessary solutions.  The district will continue to coordinate with the local entities.
 
===127.3.2.3 ROW Plan Stage===
At the right-of-way plan stage, if no community impact issues have been previously identified, the process described for earlier stages is repeated. The district initiates this process by submitting an [[127.1 Request for Environmental Services|RES]] to the Design Division, whereupon the environmental specialist will screen the project for changes and  determines whether any new information has become available since the last screening. Any new findings pertinent to the project will be relayed to the district in the RES response and the environmental specialist will discuss appropriate actions with the project manager. If no issues are identified, the district is notified that the community impact assessment issues are clear for this project.


===127.3.2.4  ROW Plan Stage===
At this stage, if it has been determined that the project could have an adverse impact on a community based on analysis of the community and potential impacts to that community, solutions should begin to be identified or should be underway. The environmental specialist helps the project manager identify impacts and solutions. If the NEPA class has been determined and approval been given, the review may need to be re-evaluated.
At the right-of-way plan stage, if no community impact issues have been identified previously, the process described for earlier stages is repeated.  The district initiates this process by submitting an [[127.1 Request for Environmental Services|RES]] to the design division, whereupon the environmental specialist will screen the project for changes and verify that no new information has become available since the last screening.  Any new findings pertinent to the project will be relayed to the district in the RES response and the environmental specialist will discuss appropriate actions with the project manager.


At this stage, if it has been determined that the project could have an impact on a community, solutions with the affected entities should begin or should be underway. 
===127.3.2.4 Final Design Stage===
 
At final design stage, if there have been no community issues identified to date, the process prescribed for earlier stages is repeated.  The district submits an [[127.1 Request for Environmental Services|RES]] to the Design Division and the environmental specialist screens the project for changes and determines whether any new information has become available since the last screening. Any new findings pertinent to the project are relayed to the district in the RES response and the environmental specialist will discuss appropriate actions with the project manager. If no issues are identified, the district is notified that the community impact assessment issues are clear for this project.
===127.3.2.Final Design Stage===
At final design stage, if there have been no community issues identified to date, the process described for earlier stages is repeated.  The district submits an [[127.1 Request for Environmental Services|RES]] to the design division and the environmental specialist screens the project for changes and verifies that no new information has become available since the last screening. Any new findings pertinent to the project are relayed to the district in the RES response and the environmental specialist will discuss appropriate actions with the project manager. If no issues are identified, the district is notified that the community impact assessment issues are clear for this project.
Solutions to community impacts that are part of the project design should be finalized at this point and the project manager has committed to them.  Any commitments shall be documented in the RES and carried forward by the project manager into bid, letting and award.  
 
Solutions to community impacts that are part of the project design should be finalized at this point.


===127.3.2.Bid Opening===
===127.3.2.5 Bid Opening===
Agreements with local entities and design elements that are part of community impact solutions must be clearly described in the project proposals for accurate bids.
Agreements with local entities and design elements that are part of community impact solutions identified as commitments in the NEPA document must be clearly described in the project proposals for accurate bids.  


===127.3.2.Post-Bid Opening Activities===
===127.3.2.6 Post-Bid Opening Activities===
At this stage, the primary concern is assuring that all MoDOT resident engineers and inspectors are informed of any community issues, requirements, and JSPs prior to construction. Contractors should also be informed of these issues prior to construction. If MoDOT fails to implement the agreed upon measures, lengthy project delays could result.
At this stage, commitments made during the design of the project must be communicated to the MoDOT resident engineer (RE) and inspectors prior to construction.  All MoDOT REs and inspectors shall be informed of any community issues, requirements, and JSPs carried forward as commitments. Contractors should also be informed of these commitments prior to construction. If MoDOT fails to implement the agreed upon measures, lengthy project delays could result and possible loss of Federal funding.


==127.3.3 Maintenance Activities==
==127.3.3 Maintenance Activities==
Schedule and implement special maintenance activities required to address community impacts as stipulated in agreements with local entities.
If agreements with local entities stipulate additional activities required to address community impacts, local maintenance employees will be involved to schedule and implement those special instances.  


[[Category:127 MoDOT and the Environment|127.03]]
[[Category:127 MoDOT and the Environment|127.03]]

Latest revision as of 09:46, 5 March 2024

127.3.1 Discussion

127.3.1.1 Overview

Transportation investments have major influences on society, with potentially significant economic and social consequences. The community impact assessment process alerts affected communities and residents, as well as transportation decision-makers, to the likely consequences of a project, and ensures that human values and concerns receive proper attention during project development. Specifically, community impact assessment is important for:

Table 127.3.1.1, Community Impact Assessment Values
Quality of Life A high-quality standard of living for all Americans means we must protect the essential elements of existence, including neighborhoods and community values. Community impacts assessment supports sustainable, livable communities; promotes community values and thriving neighborhoods; and contributes to general well-being.
Responsive Decision-making Assessing community impacts helps ensure that transportation policies and investments embrace the concerns of neighborhoods, communities, and society. Understanding the relationship between transportation actions and community life helps minimize conflict and promotes the resolution of potential problems. Actively involving affected parties leads to better decisions and greater project acceptance, while creating a sense of community ownership and enhancing agency credibility.
Coordination Community impact assessment helps coordinate and integrate independent plans for land use, economics, and transportation to achieve common goals. This process aids communities in meeting state and local regulations and policies, such as zoning ordinances, environmental quality regulations, growth management and adequate public facilities and services, legislation, and comprehensive planning.
Nondiscrimination Community impact assessment ensures that we act on our obligation to achieve environmental justice through practices and procedures that do not discriminate. It alerts decision-makers to the effects to all segments of society and the potential for disproportionately high adverse effects to protected populations and others related to age, sex, disability.


A “protected” population is one that refers to groups specifically protected by additional regulations such as Title VI, Executive Order 12898 on EJ, etc.

Community impact assessment is a process for evaluating the effects of a transportation action on a community and its quality of life. The assessment process is an integral part of project planning and development that shapes the outcome of a project. The information obtained is used to continuously make improvements to the project and provide documentation of the current and anticipated social environment of a geographic area with and without action. The assessment is to examine all topics of importance to people, such as mobility, safety, employment effects, relocation, isolation, and other community issues.

127.3.1.2 Laws, Regulations, and Executive Orders (EO)

In addition to the practical reasons for community impact assessment, multiple major federal regulations, statutes, policies, and Executive Orders legally require and support it.

  • Intermodal Surface Transportations Efficiency Act of 1991 (EO 13166 on Limited English Proficiency)
  • National Environmental Policy Act of 1969 (NEPA)
  • Title VI of the Civil Rights Act of 1964 and related statutes
  • 23 USC 109(h), Federal-Aid Highway Act of 1970
  • 23 CFR 771, Environmental Impact and Related Procedures (1987)
  • Executive Order (EO) 12898 on Environmental Justice (1994) and proposed Department of Transportation Order on Environmental Justice (1996)
  • Farmland Protection Policy Act (1981), as amended in 1994 (7 CFR 658)
  • Uniform Relocation Assistance and Real Property Acquisition Policies Act (1970, referred to as the “Uniform Act”), as amended in 1987
  • FHWA Environmental Policy Statements (1990 & 1994)
  • Recommendations of the President's Council on Sustainable Development

FHWA guidance for the practitioner on community impact assessment includes:

127.3.1.3 Process

Community impact assessment is integral to the entire project development and decision-making process. For example, the assessment of community impacts, along with other relevant environmental impact studies, helps shape project decisions and outcomes within the NEPA process. The assessment provides critical information about community values to formulate project objectives and the development of alternatives.

Throughout project decision-making and until construction, the Environmental specialist helps to ensure that consequences to the social fabric of an area are given consideration with other environmental impacts. The specialist plays an important role on the project development team to ensure community values are supported.

Title VI of the Civil Rights Act of 1964 and Executive Order 12898 on Environmental Justice apply to federal activities. Compliance with the FHWA’s NEPA process will accomplish appropriate implementation of Title VI and EO 12898. This process includes fully identifying social, economic, and environmental effects; considering alternatives; coordinating with agencies; involving the public; and using a systematic interdisciplinary approach. Addressing the issues coupled with full implementation of 23 USC 109(h) (e.g., community cohesion, availability of public facilities and services, adverse employment effects, etc.) will prevent the potential for discrimination or disproportionately high and adverse impacts to protected populations. Community impact assessment is key to this preventive approach.

Although the assessment of community impacts rarely follows a fixed, predictable series of steps, there is a basic logic behind the assessment process, which incorporates the following components. A Community Impact Assessment form that identifies the requirements for the steps must be filled out and included in the RES documents when appropriate. Depending on the complexity of the project, there are two forms, one for a programmatic CE and one for a documented CE.

Define the Project Study Area

In coordination with district engineers, develop various project alternatives that satisfy the project purpose and need and identify areas of potential impact.

Develop a Community Profile

Determine the characteristics of the affected area, such as neighborhood boundaries, locations of residences and businesses, demographic information, economic data, social history of communities, and land use plans.

Analyze Impacts

Examine the impacts to the community by the proposed action versus no action. Identify and investigate the consequences of the proposed transportation action.

Identify Solutions

Identify and recommend potential solutions to address adverse impacts. Techniques include avoidance, minimization, mitigation, and enhancement.

Use Public Involvement

Use public participation as a basis to develop project alternatives, a source of information to develop the community profile, a tool to identify and evaluate impacts, and a method to identify acceptable ways to address impacts. Public involvement is an integral element of all the above steps.

Document Findings

In addition to oral presentations, prepare the findings of the community impact assessment in written form for use by decision-makers, to record findings, to disseminate to interested parties, and to support subsequent decisions. These findings shall be documented in the Request for Environmental Services (RES) form for the project.

Iterative Process

Communities are dynamic and constantly changing. As options change, or new information is gathered, the Environmental specialist must appropriately re-evaluate and adjust findings, particularly if there are substantial time lapses in project development.

Although the steps in the community impact assessment process are logically sequential, they overlap in practice. The assessment process is iterative in that specialists must be prepared to revisit prior steps and be aware of future steps in conducting the assessment. In the early steps when helping to frame the project and community profile, the community impact specialist must think about the probable relationships between the project and the community so that relevant data are collected. Later, if new impacts are identified or decisions are made, the specialist must go back to the community profile and gather additional information or data regarding populations affected.

In recognition that certain types of projects are unlikely to generate disproportionately high and adverse effect on EJ populations or community impacts, not all projects will require completion of all above steps, however if it is determined at any time in the project screening process that the project requires completion of a full assessment, the rest of the steps must be completed (see CIA CE2 form). Some projects, such as minor improvements, may require a less detailed analysis than a more complex project. The scale of the analysis should depend not only on the scope of the project but also the context of the project. The environmental specialist must exercise professional judgment when determining the level of detail required for an assessment.

127.3.2 Project Development Milestones

127.3.2.1 Location/Conceptual Plan Stage

At the location/conceptual plan stage, Design Division environmental staff determine if the project falls under a programmatic categorical exclusion (PCE) on Community Impacts, Environmental Justice, and Title VI Compliance or detailed analysis is needed. The environmental specialists use various tools and databases to screen the project but may also contact local entities and/or district staff to determine whether they have any concerns with the project or additional information that may help in the project review. Initial data collection involves gathering general information. The Specialist uses accepted databases related to these community resources and contacts district personnel, as needed, to determine the likelihood that the project will have a negative impact on the community.

The district initiates this process by submitting a RES to the Design Division for every project when it is placed in the scoping section of the STIP or as soon as the project is programmed for those that go directly into the STIP. For projects that require an Environmental Assessment (EA) or an Environmental Impact Statement (EIS), the Design Division and the district will determine when to begin this process since an RES is not submitted for those projects until later in the NEPA process. The district may be required to gather and submit additional information about the project at this stage. Findings pertinent to the project will be relayed to the district in the RES response and through core team participation.

127.3.2.1.1 Impact Assessment

Community Impact Assessment Data List
Population and Demographic Characteristics
Historical background
▪ Trends in population growth and demographics
▪ Ethnicity and race
▪ Languages spoken
▪ Age and gender distributions
▪ Income levels
▪ Educational attainment
▪ Employment status
▪ Community Impact Assessment population subgroups, such as disabled persons
▪ Indian tribal governments, as appropriate
Economic and Community Impact Assessment History/Characteristics
▪ Community historical background and context
▪ Community values and issues (e.g., security and solitude)
▪ Economic base (e.g., agriculture, manufacturing, and service)
▪ Property values
▪ Tax base
▪ Other economic characteristics (e.g., port city, tourism base, and lumber town)
Physical Characteristics Relating to Community Activities
▪ Community centers/activity centers
▪ Infrastructure (e.g., roads, transit, and water and sewage systems)
▪ Public services and facilities (e.g., schools, police, fire, libraries, and hospitals)
▪ Land-use plans and zoning
▪ Community Impact Assessment areas, historic districts, and parklands
▪ Businesses
▪ Housing (e.g., availability, age, and type)
▪ Planned and approved future development
▪ Community focal points or informal meeting places (e.g., places of worship, playgrounds, hair salons, and laundromats)

Data sources include:

Contact Points
Source Primary Uses
Metropolitan Planning Organizations (MPOs) Economic base, land-use and zoning plans, and area planning history
State and local government planning and community impact assessment service departments/agencies Economic base, land-use and zoning plans, taxing districts, Community Impact Assessment and economic programs and business, and marketing information
State employment agencies or labor departments Employment trends, unemployment rates, and economic base
State, local, and university libraries (for local newspaper clippings and other local sources) General information, community historical background, economic base, and business and marketing information
Local historical societies and State Historic Preservation Officer (SHPO) Community historical background and location of historic structures, landmarks, and districts

Data collected include:

Table 127.3.2.1.1, Data Collections and Activities
Source Primary Uses
U.S. Census Bureau publications and statistical abstracts using EJScreen Population trends and demographics, economic indicators, and housing
Aerial maps and road maps Community boundaries and physical characteristics; location of activity centers, infrastructure, houses and businesses
Field or windshield surveys and reviews Locations and numbers of structures and activity patterns
Interviews and public involvement with businesses, community leaders, and residents Community values and issues
More sources and uses can be found at https://www.fhwa.dot.gov/livability/cia/quick_reference/index.cfm

For all projects, the Environmental specialist, district project team, and/or consultant team will ensure that any comments concerning potential impacts to the community solicited from local entities through the public involvement process are addressed. The impact assessment process described previously must be initiated prior to alternatives development and is to be used to guide that development. This activity fulfills the NEPA requirements relating to the selection of alternatives and the information obtained is used in the EA, EIS, PCE or documented Categorical Exclusion (CE2) documentation.

Refer to Table 127.3.2.1.1, Data Collections and Activities, for examples of the types of data collected and incorporated into environmental documents.

127.3.2.1.2 Addressing Adverse Impacts

When adverse community impacts are identified, the Environmental specialist will propose potential methods for addressing them through mitigation. This step of the community impact assessment process involves problem-solving and generating solutions. There are four primary methods to address impacts, which are considered in the order listed below.

Avoidance

Alter the project so an impact does not occur.

Minimization

Modify the project to reduce the severity of an impact.

Mitigation

Undertake an action to alleviate or offset an impact or to replace an appropriated resource.

Enhancement

Add a desirable or attractive feature to the project to make it fit more harmoniously into the community. It is not intended to replace lost resources or alleviate impacts caused by the project.

Project design options are typically based on an ideal engineering standard. When adverse community impacts are identified, specialists will:

  • Work with the project development team to identify design or engineering options to deal with these impacts—starting with avoidance and then moving on to minimization and mitigation techniques.
  • Consider enhancement opportunities that are a reasonable expenditure of public funds and help the project fit harmoniously into the community.

Community impact specialists should recognize that an effort to address one impact may create other adverse impacts. Specialists must consider the potential impacts of these measures on the community, ensuring that the approaches considered support the purpose and need of the project. Whatever approach is selected, it is important to monitor and follow through on commitments.

Public involvement can provide important information to aid in identifying acceptable solutions to address adverse impacts.

The Categorical Exclusion (PCE and CE2), Finding of No Significant Impact (FONSI), and Record of Decision (ROD) documents as well as the draft and final EIS must include the avoidance and minimization measures that have been completed as well as the commitments identified during the process to avoid, minimize, or mitigate any adverse impacts which are then carried forward in the bid documents.

Practical examples include:

Avoidance

  • Change an alignment so that there are no displacements.
  • Redesign a road segment as an underpass to avoid cutting off access to a community facility.

Minimization

  • Reroute or shift a highway segment to reduce displacements.
  • Limit interchanges to minimize incompatible land-use development.
  • Phase the project to minimize impedance to business access during peak periods.
  • Alter an alignment to increase the distance between the transportation facilities and residences to minimize noise impacts.

Mitigation

  • Set aside land for a park or add to public recreation areas to replace lost facilities.
  • Erect sound barriers to mitigate noise to surrounding communities.
  • Provide a bicycle/pedestrian overpass or underpass to provide access to public facilities.
  • Provide compensation for properties acquired, a mandatory measure under the Uniform Act Amendments.

Enhancement

  • Provide signage to recognize specific cultural or historic resources.
  • Development bicycle trails or paths adjacent to roadways.
  • Plant trees and add park benches.
  • Add public artwork or a facade to a transportation facility to match the aesthetic design goals of a community.

There are two types of enhancements: 1) Environmental enhancements, which may be added to a transportation project to improve community acceptance (see 1994 FHWA Environmental Policy Statement) and 2) Transportation enhancements, which are funded through a provision of SAFETEA-LU with funds set aside from the Surface Transportation Program.

Environmental enhancements are incorporated into a project as part of routine decision-making to make it more compatible with and sensitive to community needs. Transportation enhancement activities offer communities the opportunity to expand transportation choices with safe bicycle and pedestrian facilities, scenic routes, beautification, and other investments that increase opportunities for recreation, accessibility, and safety for everyone beyond traditional highway programs. Transportation enhancements funding may be available to help meet these needs.

127.3.2.2 Preliminary Plans Stage

If no community impact issues were previously identified or the project fell under the Programmatic Categorical Exclusion (PCE), the preliminary plans stage allows specialists to repeat a similar a process as was conducted during the initial project screening. The district initiates this process by submitting an RES to the Design Division. The environmental specialist screens the project for changes and determines whether any new information has become available since the last screening. Any new findings pertinent to the project will be relayed to the district in the RES response and the environmental specialist will discuss appropriate actions with the project manager.

At this stage, if it has been determined that the project could have an impact on a community, the environmental specialist will continue coordinating with the district to determine and design the necessary solutions. The district will continue to coordinate with the local entities.

127.3.2.3 ROW Plan Stage

At the right-of-way plan stage, if no community impact issues have been previously identified, the process described for earlier stages is repeated. The district initiates this process by submitting an RES to the Design Division, whereupon the environmental specialist will screen the project for changes and determines whether any new information has become available since the last screening. Any new findings pertinent to the project will be relayed to the district in the RES response and the environmental specialist will discuss appropriate actions with the project manager. If no issues are identified, the district is notified that the community impact assessment issues are clear for this project.

At this stage, if it has been determined that the project could have an adverse impact on a community based on analysis of the community and potential impacts to that community, solutions should begin to be identified or should be underway. The environmental specialist helps the project manager identify impacts and solutions. If the NEPA class has been determined and approval been given, the review may need to be re-evaluated.

127.3.2.4 Final Design Stage

At final design stage, if there have been no community issues identified to date, the process prescribed for earlier stages is repeated. The district submits an RES to the Design Division and the environmental specialist screens the project for changes and determines whether any new information has become available since the last screening. Any new findings pertinent to the project are relayed to the district in the RES response and the environmental specialist will discuss appropriate actions with the project manager. If no issues are identified, the district is notified that the community impact assessment issues are clear for this project.

Solutions to community impacts that are part of the project design should be finalized at this point and the project manager has committed to them. Any commitments shall be documented in the RES and carried forward by the project manager into bid, letting and award.

127.3.2.5 Bid Opening

Agreements with local entities and design elements that are part of community impact solutions identified as commitments in the NEPA document must be clearly described in the project proposals for accurate bids.

127.3.2.6 Post-Bid Opening Activities

At this stage, commitments made during the design of the project must be communicated to the MoDOT resident engineer (RE) and inspectors prior to construction. All MoDOT REs and inspectors shall be informed of any community issues, requirements, and JSPs carried forward as commitments. Contractors should also be informed of these commitments prior to construction. If MoDOT fails to implement the agreed upon measures, lengthy project delays could result and possible loss of Federal funding.

127.3.3 Maintenance Activities

If agreements with local entities stipulate additional activities required to address community impacts, local maintenance employees will be involved to schedule and implement those special instances.