3 March 2023

3 June 2022

4 June 2021

9 February 2021

2 February 2021

1 February 2021

  • curprev 13:1113:11, 1 February 2021Smithk talk contribsm 10,260 bytes +6,993 Per EPS, standardized the construction of shoulder widening projects across all districts; Type A2 and Type A3 shoulders are used only in conjunction with the construction of new pavement. EPG 231.4.3 Shoulder Widening Projects revised and moved from EPG Minor Routes Shouldering Project Guidelines

29 September 2020

9 May 2018

2 February 2016

14 May 2015

6 May 2014

7 September 2012

30 August 2012

3 January 2012

12 November 2009

2 February 2009

13 November 2008

14 December 2006